image Government has notified five transmission projects for implementation with private sector participation through tariff based competitive bidding route. The notified schemes are inter-State transmission projects and as such these do not belong to any particular state.

Details of the transmission schemes are given below:

Sl Transmission Scheme Estimated line Estimated cost No. Length (km) (Rs. crores)

  1. Transmission system associated with Independent Power Producers (IPPs) of Nagapattinam / Cuddalore Area – Package A – Nagapattinam Pooling Station – 250 650 Salem 765kV D/c line. – Salem – Madhugiri 765 kV S/c line. 250 375
    Total: 1025
  2. Transmission system associated with IPPs of Nagapattinam / Cuddalore Area – Package C – Madhugiri – Narendra 765kV 350 910 D/c line. – Kolhapur – Padghe 765kV D/c 350 910 line (one ckt. via Pune). Total: 1820
  3. Transmission System associated with IPPs of Vemagiri Area- Package A – Vemagiri Pooling Station – 250 650 Khammam 765kV 1xD/c (1st ckt.) line. – Khamam – Hyderabad 765 kV 1xD/c (1stckt.) line. 250 650
    Total: 1300
  4. Transmission System associated with IPPs of Vemagiri Area- Package B – Vemagiri Pooling Station – 250 650 Khammam 765kV 1xD/c (2nd ckt.) line. – Khamam – Hyderabad 765 250 650 kV 1xD/c (2nd ckt.) line. Total: 1300
  5. Transmission System associated with IPPs of Vemagiri Area- Package C – Wardha – Jabalpur Pooling 400 1040 Station 765kV 1xD/c line. Grand Total 6485
  6. Since the above transmission schemes would be implemented through tariff based competitive bidding route, no funds are required to be spent by the Government as Capital expenditure.