Featured Articles...

April 29, 2012

Tenders of 2460 MW of Suratgarth & Chhabra Thermal Plants worth Rs. 12,000 Crs scrapped by RUVNL…

imagePower India found that Rajasthan Government has scrapped the tenders it issued for two thermal power projects worth RS. 12,000 Crs which were bagged by Bharat Heavy Electricals Limited (BHEL).

Rajasthan Vidyut Utpadan Nigam Ltd (RVUNL) the state government company has a year ago issued tenders for super critical projects at Suratgarth and Chhabra Thermal Power stations having total capacity of 2,640 MW. The tenders were for design, engineering, manufacture, assembly, testing at works, supply, civil structural and architectural works, erection, testing and commissioning of main plant and balance of plant on EPC basis.

During the bidding process BHEL has emerged as the lower bidder followed by BGR Energy as second lowest bidder in the month of January 2011. Power India found that RUVNL has again initiated price renegotiations with BHEL in January 2012. After that extensive  discussions were happened between RUVNL and BHEL.

 

However, on April 25, 2012  cancellation letters were sent without assigning any reasons.

 

The development was took place at a time when BHEL is grappling with slowdown in its order book.

 

Owing to an overall sluggishness in the power sector, the company's order book more than halved to Rs 22,096 crore last fiscal compared to 2010-11 period.

The scrapping of the tenders would delay the setting up of two projects  in Rajasthan, which is grappling with power shortage. At present, RUVN has an installed capacity of 4,097.35 MW.

 

 

--------------------------------

Power India – A popular blog on Indian Power Sector

This work is licensed under a Creative Commons license.
Read More...

Single Window Clearance Authority to decide on electricity duty exemption for Jayashree Chemicals…

Power India found that the State Level Single Window Clearance Authority (SLSWCA) will decide on the issue of electricity duty exemption for Jayashree Chemicals Ltd, the only manufacturer of caustic soda in Odisha.

 

Burdened by the steep cost of electricity which accounts for 60 per cent of its production cost, the company had sought waiver in electricity duty for a period of 10 years. The hike in power tariff announced recently by power regulator-Odisha Electricity Regulatory Commission (OERC) had nullified the power conservation efforts of the company which was achieved through installation of membrane cell technology.

At a recent meeting held under the chairmanship of Chief Secretary on grant of incentives to Jayashree Chemicals, the state government asked the company to submit a separate proposal, substantiating its plea for the duty waiver. The proposal would then be considered by SLSWCA.
The company said its financial position did not permit it to set up a captive power plant.

 

The state government, has however, decided to offer exemption on value added tax (VAT) on incremental production of the company. Jayashree Chemicals had ramped up caustic soda production capacity of its plant at Ganjam in south Odisha from 22,500 tonnes per annum (tpa) to 53,200 tpa. The company had also invested Rs 150 crore on switching over to membrane cell technology from mercury cell technology.

 

The company which is engaged in the manufacture of caustic soda, liquid chlorine, hydrochloric acid and sodium hypo chlorite counts Emami Paper Mills, Ballarpur Industries Ltd, J K Paper, Hindalco Industries and National Thermal Power Corporation (NTPC) as its major clients.

 

 

 

-----------------------------------

Power India – A popular blog on Indian Power Sector

This work is licensed under a Creative Commons license.
Read More...

Tata Power got legal opinion to strengthen it case of captive mines…

image

After Reliance Power, the company’s arch rival, Tata Power, too, has independently secured a favourable opinion from the country’s top legal brains, including retired Chief Justice of India M N Venkatchaliah and former Solicitor General Dipankar Gupta, over the legality of a government decision allowing Reliance Power to divert surplus coal from the captive mines associated with its Sasan ultra mega power project in Madhya Pradesh.

The opinion given to Tata Power runs contrary to what legal experts have told Reliance Power on their private initiative aimed at strengthening the case on coal diversion. The two companies, which are engaged in a legal battle where Tata Power has challenged the government’s decision in the Supreme Court, are likely to use the legal opinion they secured to strengthen their respective cases ahead of the Saturday’s ministerial panel meeting.

The empowered group of ministers (EGoM) has been convened to examine the official opinion from the Attorney General. At its December meeting, the group headed by finance minister Pranab Mukherjee, had decided to seek fresh legal opinion from the AG Goolam E Vahanvati to defuse the controversy arising from the group’s earlier in-principle decision in 2009 to allow Reliance Power to divert surplus coal following adverse remarks made in a draft report of the Comptroller and Auditor General (CAG) that said that decision meant windfall gain for Reliance Power.

In the opinion given to Tata Power, legal experts have termed the EGoM permission as ‘ultra vires’ as the decision with regard to diversion of coal went against stated policy for allocation of coal blocks. Both Venkatchaliah and Gupta have also said that a change in the terms and conditions of the bid for UMPP in the immediate aftermath of the completion of the bidding process would in effect amount to changing the terms and conditions of the bidding process itself, which is also violation of Article 14 of the Constitution and also arbitrary and unreasonable.

“Tender documents should not be designed to encourage speculation. The allocation of the coal mines is intertwined with the Sasan project and cannot be used for any other project. The permission given by EGoM has augmented the right of the successful bidder for incremental coal. It is ultra vires of the specific provisions of the statute, rules, and the policy governing allocation of coal, and also altered the bid conditions,” Venkatchaliah said in his opinion given to Tata Power.

Tata Power is fighting the issue not solely on government’s decision to allow for diversion of surplus coal, but also the changes the decision made in the bidding condition finalised for Sasan power projects where the company had emerged with the second best bid after Reliance Power. The company has said that as bid conditions were changed after completion of process, fresh bidding for the project should be undertaken with explicit permission on diversion being included in the bid document.

“…In any event, the alterations in the terms and conditions of the contract, which was the subject matter of the tendering process is itself arbitrary, unreasonable and intended to grant undue favours to private parties and against public interest,” Gupta said.

“Tata Power would have a cause of action to file a writ petition under Article 226 for quashing of the award of Sasan UMPP and/ or in any event the grant of permission to use coal from the Captive Coal Mines linked to Sasan UMPP for other projects of RPL, which would have a reasonable chance of success,” Gupta added.

The views given to Tata Power run contrary to views given by legal experts to Reliance Power. Retired chief justices AS Anand and AM Ahmadi and former attorney general Soli Sorabjee in their respective opinion’s have said that there was no violation of Sasan UMPP bid conditions and have cautioned that the cancellation would amount to violation of the principle of promissory estoppel.

The issue between two private sector power entities involves a decision taken by an EgoM in 2009. The group had allowed Reliance Power (RPL), the successful bidder of the Sasan UMPP, to use surplus coal from the Sasan block for another 4,000 mw power project at Chitrangi in Madhya Pradesh.

The government has allocated Moher, Moher-Almohri and Chhatrasal captive coal blocks to help the private developer meet the fuel requirement of the Sasan UMPP, which it bagged through tariff-based competitive bidding.

Tata Power, which bid for the Sasan UMPP, has challenged in court the government’s decision permitting Reliance Power to divert excess coal from the Sasan mines to the Chitrangi power project. Tata Power also cited while tariff for Sasan was 1.19 per unit, the same for Chitrangi has been fixed at 2.45 per unit though coal is coming from the same blocks.

As per existing regulations, captive coal mines are given to specific end-users. Any surplus coal generated from such blocks becomes a property of the central government which then disposes it through its PSU Coal India (CIL). In a few special cases, however, the coal ministry accords permission for sale of excess coal on a temporary basis. With the approval of the bidding process, even captive blocks would now have to be bid.

The EGoM on Saturday is expected to take a view whether its in-principle approval could be could be converted into a final decision after taking legal opinion of the Attorney General.

 

-----------------------------------------------

Power India – A popular blog on Indian Power Sector

This work is licensed under a Creative Commons license.
Read More...

PFC formed an SPV (Deoghar Mega Power Ltd) for 4000 MW UMPP at Jharkhand…

image
Power india found that State-run Power Finance Corp  has formed special purpose vehicle, Deoghar Mega Power Ltd, for developing a 4,000 MW ultra mega power project in Jharkhand.
 
Deoghar would be the second ultra mega power project (UMPP) in the state after Tilaiya, which is being executed by Reliance Power, the company informed the BSE.
Power Finance Corporation, the nodal agency for UMPPs in the country, has awarded four such projects so far.
 
Three UMPPs — Sasan (Madhya Pradesh), Krishnapatnam (Andhra Pradesh) and Tilaya (Jharkhand) were bagged by Reliance Power and one at Mundra in Gujarat is being developed by Tata Power.
 
The first round of bidding for the Bedabahal UMPP in Odisha, which was held in July last year, witnessed interest from 20 bidders. The second or the final round would take place after the government completes the amendments in the standard bidding documents (SBDs) for the UMPPs.
 
The Requests for Qualification (RFQ) or the initial bids for the Sarguja UMPP in Chhattisgarh are likely to be invited in June this year.
 
The preliminary bids for this UMPP have been delayed many times in the past on account of environmental clearance.
 
The government plans to add close to 1,00,000 MW in the next five years, of which a lion’s share would be contributed by these UMPPs.
 
 
-----------------------------------------------
Power India – A popular blog on Indian Power Sector
This work is licensed under a Creative Commons license.
Read More...