Featured Articles...

January 12, 2014

Rooftop solar project in Kerala set to miss deadline...

 

Rooftop solar project in Kerala set to miss deadline...

The state government's ambitious plan to set up 35,000 off-grid rooftop solar power units is set to miss the deadline, at least during the current fiscal.

The state government, which first announced its plan to set up 10,000 off-grid rooftop solar units in December 2012, announced in 2013 that 25,000 more such plants would be set up across the state during the 2013-14 financial year.

However, Agency for non-conventional energy and rural technology (ANERT) could so far install only around 6,600 rooftop solar power units. Moreover, the agency has so far transferred the subsidy to only 1,000 people who set up off-grid solar power units of 1 kW capacity.

According to power minister Aryadan Mohammed, the state government could not utilize Rs 13.93 crore set aside in the 2013-14 budget for providing subsidy to 25,000 households for setting up rooftop solar power units. In a written reply to a question, the minister said on Tuesday that the plan for setting up 25,000 off-grid solar power unit programme failed to take off as the central government refused to give grants for the programme since the target set for 2012 was not met by the state. Also, efforts to facilitate low-interest bank loans to beneficiaries failed to elicit any positive response from banks. In this context, the state government plans to release the state subsidy of Rs 39,000 to 3,600 applicants who have submitted applications for setting up solar plants, he added.

But, according to ANERT authorities, the agency had, in fact, planned to set up only 25,000 units during 2012-13 and 2013-14 period together. However, when the second phase plan was announced, it was wrongly stated that the second phase would alone cover 25,000 households, instead of the original plan of 15,000 additional plants.

"Of the 10,000 plants announced in 2012, we have, so far, installed 6,600 units. For this, beneficiaries are promised Rs 53,262 as central government subsidy and Rs 39,000 as state subsidy. Since the project is being rolled out through agencies empaneled by ANERT, the subsidy amount is released to the respective agencies only after they furnish work satisfaction certificate from the beneficiaries. As per this procedure, we have released the subsidy to only 1,000 agencies'', said M Jayaraju, director of ANERT.

Jayaraju said the agency, so far, received only Rs 5 crore as grant for subsidy. "We hope to complete the first milestone of 10,000 off-grid units before June. Once the target for 2012-13 is achieved, we would be able to get subsidy for more such units from the Centre'', he added. As per the scheme, devoid of central and state subsidy, an individual has to chip in Rs 95,000 on an average for setting up a 1 kW solar power unit.

Source

Read More...

Coal India gets environment ministry nod for 23 projects...

 

Coal India gets environment ministry nod for 23 projects...

Coal India (CIL) has received approval from the Ministry of Environment and Forests for 23 projects after intervention by the Cabinet Committee on Investment (CCI).

"As on December 30, 2013, out of the 20 projects pending with MoEF (Ministry of Environment and Forests) for EC (environment clearance), 16 proposals have been granted EC," the Coal Ministry said in a note highlighting the action-taken report on decisions by the CCI.

Of the four projects awaiting environment approval, three belong to Coal India unit Western Coalfields Ltd and one to South Eastern Coalfields Ltd, another unit.

In addition, two of five projects have been granted stage-II forest clearance (FC), and five of 15 proposals have been given stage-I FC.

Of the projects awaiting stage-II FC, two belong to Central Coalfields Ltd and one to South Eastern Coalfields.

Two projects of Central Coalfields, four of South Eastern Coalfields and four of Central Mine Planning & Design Institute Ltd, Coal India's consultancy firm, have yet to get stage-I FC.

The government set up the CCI to expedite the decision making process for clearance of projects in the infrastructure sector.

The Coal Ministry said four meetings, including one on December 11, have been held among officials of the two ministries and Coal India to review and expedite clearances.

Source

Read More...

South Korea keen on setting up nuclear power plant in India...

 

South Korea keen on setting up nuclear power plant in India...

Keen to enter India's growing nuclear market, South Korea wants to build an atomic power plant here but India is not rushing into it.

The government first wants to complete the projects already initiated, including Koodankulam III and IV and Jaitapur, which are facing hurdles on various counts. However, India is willing to have cooperation with South Korea in other aspects of the nuclear field, like research.

South Korea conveyed its desire to build a nuclear plant in India when a delegation from its Ministry of Science came here recently, sources told a news agency.

This was preceded by a visit of a team of Department of Atomic Energy to South Korea to discuss cooperation in the nuclear field in November last year.

Sources said India not very keen to have Korean nuclear reactors immediately. The DAE first wants to concentrate on existing plants and deal with the issues like liability over which many foreign collaborators have raised questions.

"We would first want to clear the impediments for projects that are already in pipeline and then move on to another projects," said a senior DAE official. Currently, all the power plants are running behind schedule.

The Jaitapur Nuclear Power Plant Project (JNPP) being built with French assistance, the unit 3 and 4 of the Kudankulam Nuclear Power Plant (KKNPP) with Russian assistance and the Mithi Virdhi nuclear plant with the assistance of the US are either stuck because of various reasons or running behind schedule.

Source

Read More...