Featured Articles...

July 26, 2013

DERC increased the tariff for Domestic Consumers; waived the fuel surcharge..

 

delhi tariff hike

Delhi Electricity Regulatory Commission has increased the tariff for the domestic consumers of various distribution utilities of Delhi however has waived the fuel surcharge.  

The effective hikes of different Discoms of Delhi are:

  • BSES: 0.5%
  • TPDDL: 2%
  • NDMC: 4%


According to DERC, the hikes which will come come into effect from 1st August 2013, were allowed to help the Discoms meet their financial constraints.

As per the new tariff structure issued by DERC, the domestic consumer will be charged the tariff as per the below structure:

  • First 200 units: Rs. 3.90 per unit (earlier Rs. 3.70 per unit)
  • Between 201 to 400 Units: RS. 5.8 per unit (earlier Rs. 5.5 per unit)
  • Between 401 to 800 units: Rs. 6.8 per unit (earlier Rs. 6.5 per unit)
  • Beyond 800 Units: Rs. 7.0 per unit


However, post tariff announcement, Chief Minister of Delhi has declared subsidy for the consumers having consumption below 400 units as per the below slab:

  • First 200 units: RS. 1.20 per unit
  • Between 201 to 400 units: Rs. 0.8 per unit

DERC has increased the tariff historically as per the below patern:

  • 22% in 2011
  • 5% in February 2012.
  • 2% in may 2012
  • 26% in July 2012 (For Domestic Consumers)
  • 3% in February 2013

 


Additional Reading...


Read More...

ICRA Report: Long term outlook of Indian wind Energy market to remain strong...

 

wind energy outlook

ICRA Limited (an associate of Moody's Investor Service) has released a report on India's Wind Energy market according to which the fundamental long term demand outlook for wind energy is expected to remain strong, supported by large wind energy requirements to meet the Renewable Purchase Obligation (RPO) requirements in the country.

The report, titled as "Wind Energy Sector: Strong demand potential in the long run, although challenges remain on regulatory front" is analyzing the impacts of latest developments in the regulatory regime of the country specifically in the field of wind energy projects.

According to the Report, the wind projects are also getting benefits due to their increased cost competitiveness against the conventional sources of energy both due to increase in fuel prices (such as coal and gas etc) and persisting fuel shortages in the country.

The demand of Wind Energy is further supported by National Action Plan for Climate Control (NAPCC) set up by Government of India (GoI) in June 2008 recommending a target of renewable energy mix in the overall energy procurement by utilities at 10% (minimum) by 2015 and 15% (minimum) by 2020 and by the remunerative preferential tariff in some of the key wind states namely Maharashtra, Madhya Pradesh, Rajasthan and Andhra Pradesh. Also, going forward, investment demand from IPP segment would remain key growth driver and ICRA expects the share of IPP segment in the capacity addition to increase from currently at about 40-45% to about 60-70% over the next two to three years.

Also, untapped wind resource potential on all India basis (across the key states having windy sites) remains quite significant, as evident from the revision in estimates of gross wind energy potential in India from 49,500 MW to 102,800 MW by Centre of Wind Energy Technology (CWET) in February 2012.

Wind energy projects remain exposed to significant counter-party credit risks, given that the financial position of the state distribution utilities in some of the states (having wind resource potential) continue to have weak liquidity & financial position, which in turn has adversely affected their payment pattern towards the wind energy project developers. With continued delays in payments by state utility in Tamil Nadu, fresh investments in the state have been showing a declining trend, as reflected in a sharp decrease in the wind energy installations in the state during FY 2012-13. As distribution utilities are the principal obligated entities to meet RPO norms, the fundamental improvement in their financial position remains extremely crucial in the long run; as this would also enable them to honor the RPO norms in a more sustained manner. ICRA however notes that implementation of financial restructuring scheme (FRS) under progress across the five states3 having utilities with stressed financial position, as well as trend of retail electricity tariff revisions by SERCs for FY 2012-13 & FY 2013-14 so far, subsequent to ruling by Appellate Tribunal for Electricity (ATE) in November 2011; remain positives for the power sector.

CERC has recently approved implementation of mechanism for Renewable Regulatory Fund (RRF) which is to be implemented from July 15, 2013 for wind projects (of 10 MW and above), which requires them to forecast and schedule their power generation on a day-ahead basis. Wind power projects would have to pay Unscheduled Interchange (UI) charges, if the actual generation deviates by more than 30% from the scheduled generation. While the forecasting for the wind projects can be made possible by way of robust technical/statistical models as well as the availability of past data/weather conditions if in place, it remains a key challenge due to intermittent nature of wind pattern as well as nascent stage of implementation for the entire sector. This in turn, may have financial implications on wind power projects, if the actual variations remain beyond the limit of (+/-) 30% and also, given that UI charges vary widely depending upon the frequency range i.e. between Rs. 0/kwh (@50.2 Hz) and Rs. 9/kwh (@49.5 Hz).

RPO levels put in place by SERCs across the states vary widely i.e. in the range of 1% to 10.3% as applicable for FY 2013, as against the recommended level of 8% by National Action Plan for Climate Control. According to ICRA, risk of amendment in RPO norms by SERCs cannot be ruled out, as observed in the past in a few states. Also, implementation of the regulations by SERCs to ensure the compliance in RPO norms on an annual basis by obligated entities continues to remain weak, as SERCs tend to carry forward the shortfall in RPO compliance to the subsequent period, instead of directing any penalty or regulatory charges for non-compliance. As a result, price of renewable energy certificate (REC) on the power exchanges has remained depressed since August 2012, which in turn has led to increased risk profile of the wind energy projects preferring the REC route.

As preferential tariff norms by SERCs across the key seven4 states (which have wind resource potential) are not consistent with the guiding principles/norms as stipulated by CERC, project IRR (post tax) based on preferential tariffs for the wind assets too vary. Notwithstanding the same, ICRA notes that the preferential tariffs have been revised upwards by SERCs in all major states, except Karnataka, which have wind resource potential, in last 12 month period, with the upward revision being in the range of 4% and 34%. This in turn, has also led to increased preference of incremental capacity addition by IPPs through preferential tariff route instead of REC route. Project IRR5 for wind energy assets in the state of Maharashtra is estimated to remain high in the range of 14-15%, while the IRR in Madhya Pradesh, Rajasthan and Andhra Pradesh remains satisfactory in the range of 11-13%, based on the prevailing revised tariffs and in turn, incremental investments in the sector in the near to medium term are likely to happen in these states. On the other hand, IRR for wind projects in case of other states such as Tamil Nadu and Karnataka remains below 10%, because of relatively lower feed-in tariffs.

In respect of domestic wind turbine equipment manufacturing segment, overall annual manufacturing capacity has reached close to about 10,000 MW (as per the industry sources) with about 17 players in the market. This represents a significant over-capacity build-up. While this, coupled with slowdown in investments in turn has intensified the competitive pressures among the players, the market continues to be dominated by 4-5 players who cater to about 90% of the demand, especially by those who have a strong land-bank position & project development rights. Further, vulnerability for the domestic manufacturers who aim to target export markets, has increased further due to subdued demand outlook for wind energy installations in the near to medium term particularly in regions such as China, Europe and America.

 

___________________________________________________________________________________________________________________________________________

Additional Reading...

____________________________________________________________________________________________________________________________________________

Read More...

Rooftop Solar at Alappuzha Hospital Kerala...

 

image

The Alappuzha Government Medical College Hospital has installed a 30 kW rooftop Solar Project through which they run around 20 fans, 20 lights, 2 Air Conditioners (1.5 tonne each) and 2 motors (of 1.55 HP each) without taking power from Kerala State Electricity Board (KSEB).

 

According to the Hospital officials, the solar energy system was used for the power consumption of the mortuary building.

 

The complete system consists of Solar Panels, back up unit of Uninterrupted Power Supply (UPS) and batteries which costs around Rs. 80 Lakhs. The Solar Panels were bought from the Uni Solar.

Further some separate solar panels are being used for the Solar Water Heater of 1000 Litre capacity for the activities of the mortuary.

Source

Read More...

Delhi Secretariat to install 5 MW solar project to become energy self sufficient...

 

image

The Delhi Secretariat seems to become self sufficient for its power needs through Solar Energy as it is planning to install around 5 MW Solar Power Project in the premises.

 

In a meeting held between the Union Minister of Ministry of New and Renewable Energy  and Chief Minister of Delhi along with other senior officials, the proposal of 5 MW Solar Project for the secretariat was discussed and finalized.

Construction work will began once land is identified for this purpose and a contract to the EPC Contractor is awarded.

According to the Government, once the project is commissioned, the Secretariat will be able to harness the solar energy at Rs. 5 per unit for the next 25 years. 

However, the current requirement of the Secretariat building is only 2.5 MW; hence the balance power will be supplied to other offices of the Delhi Government such as Old Secretariat, Directorate of Information & Publicity office, Anti Corruption unit etc.

Earlier, the Chhatishgarh New Secretariat in Naya Raipur has installed the Solar Project for its power consumption needs.

___________________________________________________________________________________________________________________________________________

Additional Reading...

http://www.dnaindia.com/india/1865844/report-secretariat-to-generate-its-own-solar-energy

____________________________________________________________________________________________________________________________________________

Read More...

thermax recorded Rs. 611 Crores dip in Annual sales Figures...

 

image

Thermax Limited, the leading component and services provide to the Indian power sector, recoded a decrease of Rs. 611 Crores in its sales figures for the financial year 2012-13.

 

As per the Annual Report released by the company on 25th July,

  • the total sales figure of the company during 2012-13 was around Rs. 4,532 Crores as compared to Rs. 5,244 Crores during 2011-12.
  • Net Profit After Tax (PAT) during 2012-13 was Rs. 350 Crore compared to Rs. 407 Crores during 2011-12.
  • Order balance of Rs. 4,357 Crores compared to Rs. 4,230 Crores during 2011-12.
  • The company announced a dividend of Rs. 7 (350%) per equity share.

According the company the reasons behind this shortfall in the financials are tough times being faced by power sector both domestically and globally.

Regarding the future plans, company intends to increase its international presence by 40% and is eying countries of South East Asia, Middle East and Africa. Currently, the company has presence in China as well as some Scandinavian countries.

____________________________________________________________________________________________________________________________________________

Additional Reading...

___________________________________________________________________________________________________________________________________________

Read More...

Odisha to invest Rs. 3,600 Crores in four years to strengthen the state transmission & distribution sector...

 

power transmission Odisha

According to sources, Odisha Government is planning to invest around Rs. 3,600 Crores within the next fours years to strengthen the state's power transmission network

Out of the planned investment of Rs. 3,600 Crores, Rs 2,600 Crores will be used for the construction of new 33/11 kV Substations while balance 1,000 Crores will be used for installation of dedicated feeders for the agriculture and fishery sectors.

According to the the government officials both the above projects will be completed in next fours years.


Further, according the government, the above said projects will assist the state power transmission & distribution sector to reduce the AT&C (Aggregate Technical & Commercial) losses by 3%. Reduction of 1% in AT&C shall be translated into the additional savings of Rs. 85 Crores; hence the state will get savings of Rs. 2500 Crores annually due to implementation of above projects.

The current level of AT&C losses in Odisha is around 40%.

According to the estimation done by the state government, around 1200 33/11 kV substations are required to supply quality power to the consumers; as against this only 573 sub stations are existing in the state. The state government has planned to float tenders soon for construction of 520 new 33/11 KV sub-stations.

To promote the agriculture and fisheries industries of the state, government is planning to provide round the clock quality power to them and for that purpose separate dedicated feeds for agriculture and fisheries industries will be constructed.

 

________________________________________________________________________________________________________________________________________

Additional Reading...

http://economictimes.indiatimes.com/news/news-by-industry/energy/power/odisha-to-invest-rs-3600-cr-in-power-sector/articleshow/21343660.cms

_______________________________________________________________________________________________________________________________________

Read More...

MoP seeks urgent solution for unavailability gas to the 14,000 MW gas based power projects of the country...

 

gas supply woes

Power Ministry is considering to have an urgent solution for providing gas to the around 14,000 MW gas based projects which are stalled due to lack of fuel and has urged the gas producers and consumers to spare some gas for power projects after fulfilling their requirements.

As on date as high as around 14,000 MW of gas based thermal power projects having investment outlay of around USD 21 Billion are idle due to unavailability of gas.

 

Currently, the total requirement of 18,713 MW gas based power plants are around 72 Million Cubic meters per day, out of which only 30% is being met. Further around 8,000 MW of gas based projects are constructed and almost ready for commissioning but due to lack of gas they are not able to fire the plants.

No gas flows to 25 power plants that had signed up for 29.74 mmscmd of KG-D6 gas.

Most of the gas being produced are consumed to meet the requirements of fertilizer companies which are needed to produce around 30 Million tonnes of fertilizer/Urea for the agricultural sector. Fertilizer plants have accorded top priority for receipts of gas. 

Issues of gas unavailability for power projects seems to be mainly on account of drastic fall in gas production from Reliance Industries Limited's eastern offshore KG-D6 gas fields. Present output from this fields are around 14 mmscmd which are being used to meet the requirements of fertilizer plants.

According to Power Ministry, during the next meeting of the Empowered Group of Ministers (EGoM), the fuel supply issue for the power projects will be discussed critically and looked into for the solution.

In the meantime, the Power Ministry suggests seeking untied gas currently being produced or likely to be produced by the gas production companies such as ONGC and GSPC. It also urges fertilizer plants to spare some gas after fulfilling their requirements of producing urea.

 

___________________________________________________________________________________________________________________________________________

Additional Reading...

http://www.business-standard.com/article/economy-policy/scindia-seeks-solution-on-fuel-for-21-bn-worth-power-projects-113072500572_1.html

____________________________________________________________________________________________________________________________________________

Read More...