Featured Articles...

January 18, 2014

Renewable Energy Sector in India may miss target 2 years in a row...

 

Renewable Energy Sector in India may miss target 2 years in a row...

The country’s renewable energy sector is likely to miss its capacity addition target for the second year in a row. As against the annual target of 4,325 MW, only 1,922 MW has been achieved during the first nine months of the current fiscal, according to the Ministry of New and Renewable Energy.

However, amid concern over slow progress, the installed capacity for wind power has crossed 20,000 MW this fiscal, while the overall grind-interactive renewable power capacity is set to cross 30,000 MW shortly. With the addition of 1,922 MW in nine months (marginally higher when compared with 1,763 MW in the year-ago period), India’s total grid-interactive renewable energy capacity addition stood at 29,989 MW as on December 31, 2013.

During April-December 2013, wind and solar segments contributed 1096 MW and 495 MW respectively, while the rest was contributed by small hydro, bagasse co-generation, biomass and waste-to-energy categories. Besides, 67 mw of off-grid/ captive power generation capacity from different renewable energy sources were also added during the period.

Presently, wind makes up 67 per cent of India’s total installed capacity of green power. Of the total cumulative capacity of 29,989 MW, wind sector contributed 20,149 MW, followed by small hydro power at 3,763 MW, bagasse cogeneration power at 2,513 MW, solar at 2,180 MW, biomass at 1,285 MW, and waste-to-energy at 99 MW. The cumulative off-grid/ captive power generation capacity from different renewable energy sources in the country stood at 945 MW by the end of December 2013.

Source

Read More...

With CCI approval, Coal India on track to boost output by 50%...

 

With CCI approval, Coal India on track to boost output by 50%...

India’s rising coal imports, increasingly a reason for the country’s wide trade and current account deficits, may be reined in considerably in the next few years, report Raj Kumar Ray and Aftab Ahmed in New Delhi. With the Cabinet Committee on Investment (CCI) approval in hand, the railways is set to complete work on three rail projects by end 2016, helping Coal India and its arms evacuate the black gold from some of their big mines and transport them to industrial hubs. The facility will help increase domestic coal output by 250 million tonnes or nearly 50%.

The three projects — Tori-Shivpur-Kathautia (Hazaribagh) triple line for the North Karanpura Coalfield in Jharkhand, Jharsuguda-Barpalli double line for Ib Valley coalfield in Orissa and Bhupdeopur-Raigur-Mand in Chhattisgarh — were stalled for nearly a decade due to various reasons. With the CCI clearance, work has begun at some of the sites, a senior official told.

“The clearance for these railway lines would be a milestone in terms of efforts to step up domestic production of coal. The rail connectivity has the potential to generate over 250 million tonnes of coal annually, which is almost half of what CIL produces now,” said a coal ministry official, asking not to be named.

India’s domestic coal output, mainly from Coal India, has grown slowly from 431 million tonnes (mt) in 2006-07 to 576 mt last fiscal, while imports more than trebled from 41.5 mt to 138 mt as power plants, steel and other units consumed more fuel to aid growth in Asia’s third-largest economy. Coal imports as a percentage of GDP almost doubled from 0.5% in 2006-07 to 0.9% in 2012-13, and was one of the main reasons along with oil and gold imports for widening the current account deficit.

While many captive coal blocks allotted to private players failed to take off, the pressure has mounted on Coal India to raise output. CIL has often blamed delays in green clearances, land acquisition and lack of rail links from pithead to industrial units as major reason for not being able to scale up its operations.

In this context, the three rail projects will address much of the coal shortage in coming years. The Jharsuguda-Barpalli rail line is essential for transportation of coal from the Ib Valley coalfield of Mahanadi Coalfields with a potential of 90 million tonnes per annum. The North Karanpura Coalfield covers an area of 1,230 square kilometres and has total coal reserves of 13.1 billion tonnes with a potential output of 70 mt annually. The Mand Raigarh Coalfield can supply 100 mt of coal annually once the rail link is built.

The environmental clearance for Jharsuguda-Barpalli was given last month and the project is likely to be completed by June 2016, an official said.

The Rs 2,345-crore Tori-Shivpur-Kathautia project has now got environmental clearance and land acquisition for some stretches is under way. The project is likely to be operational by December 2016.

In the case of the Rs 2,500-crore Bhupdeopur-Raigur-Mand line, the CCI/CCEA has resolved the issue and a special purpose vehicle led by Ircon will be set up by September 2016.

The three railway link projects are a part of the three inter-state rail corridor projects proposed by CIL that are dedicated to coal evacuation in the Naxal-affected areas in Orissa, Chhattisgarh and Jharkhand. CIL’s total investment in these three corridors are of the order of Rs 6,000 crore.

Source

Read More...

11 TN Hydro Power Dams to Get New Lease of Life Under WB Project...

 

11 TN Hydro Power Dams to Get New Lease of Life Under WB Project...

Eleven hydro power dams in the Tamil Nadu State would get a new lease of life under the first phase of the Rs. 745.49-crore World Bank project, a senior official from the Water Resources Organisation (WRO) said.

The official told that 104 of the 127 dams, including 38 Tamil Nadu Electricity Board dams generating hydro-power, would be covered under the funds to enhance them for irrigation and generation of drinking water and hydro-power.

The project would be implemented in four phases and would be completed by 2018. In the first phase, Adavinainar Koil dam, Vadakupachayar dam, Nambiar dam, Kodumudiyar dam and Manimuthar dam in Tirunelveli district, Poigayar dam in Kanyakumari district, Vidur dam and Gomukhinadhi in Villupuram district, Mordhana in Vellore district, Siddhamalli in Ariyalur district and Kodayanar in Dindigul district would be covered.

A total of Rs. 63 crore has been allocated for the purpose, a WRO official said. He added that the technical and administrative procedures had been completed and work was about to be started. The main aim is to enhance the strength of the dams to withstand floods. Most of the dams were scheduled to undergo maintenance as they were 40 to 50 years old. The project would adhere to World Bank procedures.

“First we will be studying the internal behaviour of the dam after which it will be strengthened to withstand natural calamities for a long period of time. A hydrology study is also being conducted simultaneously,” the WRO official said, adding, that steel shutter conditions to regulate floods will also be checked and re-strengthened or replaced depending upon the requirement.

Six hydro-electric dams will also be covered under the project. These include Avalanche dam, Glenmorgan dam, Mukurthy dam and Porthimund dam in Nilgiris district, Kadamparai dam in Coimbatore district and Servalar dam in Tirunelveli district. The WRO official said that the project would also cover the 107-year-old Pechhiparai dam besides 25 others in the second phase. The preliminary process has already been started, the official said.

Source

Read More...