Featured Articles...

August 30, 2011

Spark’s update on new Transmission Projects…

image Government has notified five transmission projects for implementation with private sector participation through tariff based competitive bidding route. The notified schemes are inter-State transmission projects and as such these do not belong to any particular state.

Details of the transmission schemes are given below:

Sl Transmission Scheme Estimated line Estimated cost No. Length (km) (Rs. crores)

  1. Transmission system associated with Independent Power Producers (IPPs) of Nagapattinam / Cuddalore Area – Package A – Nagapattinam Pooling Station – 250 650 Salem 765kV D/c line. – Salem – Madhugiri 765 kV S/c line. 250 375
    Total: 1025
  2. Transmission system associated with IPPs of Nagapattinam / Cuddalore Area – Package C – Madhugiri – Narendra 765kV 350 910 D/c line. – Kolhapur – Padghe 765kV D/c 350 910 line (one ckt. via Pune). Total: 1820
  3. Transmission System associated with IPPs of Vemagiri Area- Package A – Vemagiri Pooling Station – 250 650 Khammam 765kV 1xD/c (1st ckt.) line. – Khamam – Hyderabad 765 kV 1xD/c (1stckt.) line. 250 650
    Total: 1300
  4. Transmission System associated with IPPs of Vemagiri Area- Package B – Vemagiri Pooling Station – 250 650 Khammam 765kV 1xD/c (2nd ckt.) line. – Khamam – Hyderabad 765 250 650 kV 1xD/c (2nd ckt.) line. Total: 1300
  5. Transmission System associated with IPPs of Vemagiri Area- Package C – Wardha – Jabalpur Pooling 400 1040 Station 765kV 1xD/c line. Grand Total 6485
  6. Since the above transmission schemes would be implemented through tariff based competitive bidding route, no funds are required to be spent by the Government as Capital expenditure.

Read More...

13 Projects of Coal India awaits environment clearances…

image Thirteen coal mining projects of Coal India Ltd are pending with the environment and forests ministry for approval, Environment and Forests Minister Jayanthi Natarajan told parliament Tuesday.

 
"These projects have not been accorded environmental clearance as on date, due to non-submission of complete information," Natarajan said in a written reply to a question in the Rajya Sabha.

She said the ministry has asked Coal India to provide adequate information on critical environmental parameters so that the clearance would be given the project.

The 13 projects that are awaiting environmental clearance include six new projects and six projects for expansion.

"They are awaiting environmental clearance for varying durations, under the Environmental Impact Assessment (EIA) notification 2006," she said.

Environmental impact assessment notification 2006 provides for a time limit of 105 days for taking a decision after receipt of complete information from the project's proponents.

Read More...

Power finance companies may be hurt by new NBFC provision norms…

image As per the note published by Bank of America Merrill Lynch, the Reserve Bank of India panel's new recommendations on lending and provisioning rules for non-banking financial companies could hurt power sector finance companies such as Power Finance Corp (PFC), Rural Electrification Corp (REC) as well as others like IDFC, Shriram Transport and Manappuram Finance which currently classify NPLs under 180-day norms.

 
Only
Indiabulls Financial Services Ltd and Reliance Capital follow the proposed 90-day norm, the note said. In order to comply with the new rules, PFC and REC could have to provide for on standard assets (~25bps), "which could hurt their earnings in the medium term", the Wall Street bank said in a note.

Shriram could see NPLs more than doubling (to+5.3-5.5 per cent) from present and previous cover come-off (82% now), but they could also be allowed to do so in a phased manner "assuming the worst case, if not in a phased manner, then the impact on FY13 earnings for Shriram could be +3-5 per cent," BofA added.

Read More...

Sahara, Korea join hands for power projects…

image According to reports, Sahara India Power Corporation Ltd, in association with Korea East-West Power Co Ltd, will be setting up power plants through mega projects in India to generate 6,000 MW.

The CEO of Sahara Power Ashok Bhargava and president & CEO of Korea East-West Power, Gil Gu, recently signed a memorandum of agreement (MoA).

While Sahara Power is the Sahara group’s initial venture into the power sector, Korea East-West Power is an undertaking of the government of Korea. Both have agreed to jointly participate in tariff-based bidding for ultra mega power projects (UMPPs) and other opportunities in India.

Both firms have already tied up to set up a 2x660-MW power plant in Titlagarh, Orissa, with an investment of about Rs8,000 crore.

They claim to have jointly brought to India new and innovative thermal power generation technologies by optimizing the resources in terms of fuel consumption, heat recovery and waste water resources and recycling. Pollution levels are also expected to be lower than current Indian norms.

Gil Gu said, “India is an important country for us as it is one of the emerging powers of the world, and with Sahara Power as our partner we are confident that our projects will serve the energy requirements in further development of India.”

Together with Bhargava he met Union ministers including Sushil Kumar Shinde and Sriprakash Jaiswal, and senior functionaries of the Power Grid Corporation of India, a leading provider of power trading solutions.

Read More...

Solar Power can meet 5-7% Power Requirement in India by 2021-22: As per KPMG Report…

image A study published by KPMG, a global consulting company has forecast that solar power can meet 5-7% of India’s total power requirements by 2021-22.

In a written reply to a question in Rajya Sabha today, Minister of New and Renewable Energy Dr. Farooq Abdullah said India has good potential for solar power as it receives solar energy equivalent to over 5,000 trillion kWh per year, which is far more than the total energy consumption of the country. He said the daily average solar energy incident varies from 4 – 7 kWh per square meter of the surface area depending upon the location and time of the year. The Minister added that the solar radiation is available at most locations in the country for about 300 days in a year.

Dr. Farooq Abdullah informed that the total installed capacity of grid connected solar power plants as on date is 45.5 MW. He said the Government has launched Jawaharlal Nehru National Solar Mission in January 2010, which aims to set up 20,000 MW grid solar power by 2022 in addition to 2,000 MW of off-grid solar power. He said deployment of solar power is, thereafter, expected to increase rapidly due to declining prices of solar power, indigenization and technology improvements.

Read More...

RPower sought shareholders’ approval for raising funds through QIP…

image Anil Ambani Group firm Reliance Power has sought the approval of shareholders to raise funds through sale of up to 25 per cent shares to institutional investors for funding projects.


It has also sought the nod for mopping up funds through issuing of securities in international markets, according to the company's annual report for 2010-11.

When contacted, a Reliance Group spokesperson said, "These are merely enabling resolutions that will remain valid till the next AGM, but there are no plans for making any QIP or other offering of securities at this time". Meanwhile, the proposed issue of QIP securities may be made in one or more tranches.


"... the aggregate amount raised by the issue shall not result in the increase of the issued and subscribed equity share capital of the company on the relevant date by more than 25 per cent of the then issued and subscribed equity shares of the company as on the relevant date," the report noted.

 
The proposed sale of securities in international markets would also have a ceiling of 25 per cent of then issued and subscribed equity shares.

Based on today's market capitalisation of Rs 23,422 crore, around 25 per cent stake in the company would be worth over Rs 5,850 crore.

Reliance Power on its own and through its subsidiaries has a planned portfolio of over 35,000 MW generation capacity, including both operational as well as projects under development.

"In order to part finance such a large portfolio of power projects and to enhance its global competitiveness and ability to compete with the peer groups in the domestic and international markets, the company needs to strengthen its financial position and net worth by augmenting its long-term resources," the report said.

In letter to shareholders, Reliance Power Chairman Anil Ambani said the company expects to commission 600-MW Rosa Phase-II project, the 600 MW Butibori project at Nagpur, Maharashtra and one unit of 3,960 MW Sasan Ultra Mega Power Project (UMPP) at Madhya Pradesh, by 2012.

"Besides, we shall commission the open cycle phase of India's largest gas based power project, the 2,400 MW project at Samalkot, in the current financial year and the combined cycle phase by the next year," Ambani wrote.


Reliance Power recorded a profit of Rs 760.44 crore in 2010-11.

Read More...

India to receive 200 Mn EURO loan from EU for Renewable Energy development…

image India will receive a loan of 200 million euros from the European Union to finance private sector projects for the development of renewable energy resources.

The EU's assistance comes as part of its "strategic partnership" with India and will be made available by the European Investment Bank (EIB) to ICICI Bank, India's largest private bank, in the first-ever cooperation between the two financial institutions.

It is intended to provide long-term financing for investments on a number of electricity generating projects, especially in the areas of solar photovoltaic, biomass and onshore wind power by private companies, thereby making a contribution to India's efforts to reduce greenhouse gas emissions, the EIB said on Monday in a press statement.


The loan is being provided under the EIB's Energy Sustainability and Security of Supply Facility (ESF), a 4.5 billion euro programme designed to reinforce the EIB's goal of promoting renewable energy and energy efficiency in non-EU countries.


This is the first cooperation between the long-term financing institution of the 27-nation EU bloc and India under the ESF programme, the statement said.


The ESF is used when the bank does not need a credit guarantee from the EU because the recipients are investment-grade countries or where appropriate security can be provided.


In addition to the ESF, the EIB has an external lending mandate to implement the EU's lending operations outside the bloc as part of its cooperation with those countries and since 1993, the bank has carried out four successive lending operations for Asia and Latin America.


Under the current mandate, covering the period between 2007 and 2013, the EIB is authorized to lend up to 3.8 billion euros for financing projects that contribute to the avoidance or reduction of greenhouse gas emissions through foreign direct investment or technology and know-how transfer.

The lion's share of the funds, amounting to 2.8 billion euros, are earmarked for Latin America, while the Asian region will receive 1 billion euros.


The EIB's loan for India will "support the EU-India strategic partnership, which provides for cooperation in curbing climate change", the statement said.


The projects eligible for financing will bring economic benefits to the region by enhancing the production of energy from renewable resources, reducing the costs for imported energy, expanding the use of domestic resources and curbing greenhouse gas emissions and other airborne pollutants.


"The EIB will ensure that the projects are economically and financially viable, technically adequate and in compliance with the bank's environmental and social requirements," the statement said.

Read More...

Coal linkages: 974 power firms line up for supply…

image The coal ministry has received applications for long-term coal linkage from central and state utilities, independent power producers (IPPs) and captive power producers (CPPs) for 974 power projects with a generation capacity of over 5.96 lakh Mw, as on July 31.

Of the 974 applications, 107 are from central and state utilities for capacity addition of 1,22,405 Mw, 434 applications from CPPs for 37,345.79 Mw and 433 from IPPs for a record 4.25,836.5 Mw capacity addition. The installed capacity of these power projects vary from 10 Mw to 5,280 Mw.

A coal ministry official told Spark: “Some of the applications had already been considered in the past by the standing linkage committee (long term) but deferred the decision due to various reasons. These applications will be taken up in due course to provide long-term coal linkage for the upcoming power projects.”

The official said the standing linkage committee (long term) would take up the proposals wherein the applicant had changed the category from CPP to IPP or enhanced or reduced the generation capacity or modified configuration.

According to the official, adequate reserves — coal reserves upto 1,200 metres deep — have been estimated at 277 billion tonnes as on April 1, 2010 and lignite reserves have been estimated at 39.07 billion tonnes as on March 31, 2009. Of the 277 billion tonnes, 110 billion tonnes of coal reserves have already been identified, 130.65 billion tonnes are indicated and 35.6 billion tonnes inferred.

The power ministry official said it had been pursuing with the coal ministry for an early clearances for both short and long-term coal linkages. “The issue has been discussed with the coal ministry on a regular basis. We are quite optimistic that the ministry will clear these applications expeditiously especially when it has projected a capacity addition of 1,00,000 Mw each in the 12th and 13th Five-Year Plans and most of which is expected to come through coal-based power projects.”

According to the official, Coal India Limited (CIL) has assured to supply about 600 million tonnes in 2016-17. However, the actual availability is likely to be 415 million tonnes leading to a shortfall of 185 million tonnes by the end of the 12th Plan.

Read More...

Spark’s Update on Suzlon Energy…

image Suzlon Energy is turning out to be one interesting turnaround story. After a couple of loss-making years, it appears to be gearing up its businesses, as reflected by its financial performance in 2011 so far. In the March '11 quarter, Suzlon improvised upon its operating margins by more than 500 basis points y-o-y. The June '11 quarter also saw the company post impressive double-digit operating margins.

 
Suzlon registered more than 80% y-o-y growth in revenues in June '11 quarter while its net profit was impressive at 60 crore against a loss of over 900 crore in the June '10 quarter. The raw material cost, as a percentage to sales, also declined by nearly 1000 basis points to 64% in June '11, indicating the cost efficiencies being put in place. It has also succeeded in keeping its wage costs in check, helping it considerably improve its operating margins.

 
Suzlon has maintained its guidance of achieving 24,000-26,000 of sales in FY12, backed by its order book of over 29,000 crore.


Its acquisition of

REpower has played a major role in the turnaround.


Nearly 62% of its current order book is from REpower. Suzlon is now in the final stages of acquiring the remaining 5% stake REpower from minority shareholders for approximately 398 crore.


Even as a turnaround in visible, Suzlon's stock currently trades around 34-36 on the bourses, i.e. its near 52-week low level. Over the past one-year, this counter has returned a negative 27% against the Sensex's negative 12%.

 
Apart from its weak financials in the past, a major concern that is holding back investors is Suzlon's huge

debt which includes the foreign currency convertible bonds loan due for repayment next fiscal.


The management, however, is optimistic about meeting its loan obligation, intending to fund it through operating cash flows, receipts from the stake sale in Hansen Transmissions and also the expected recovery from one of its large US-based debtor by the second half of this fiscal. It has a cash balance of over 3,000 crore as at the end of March '11 while its total debt stood at over 12,500 crore

Read More...

GVK Power & Infra may raise debt to fund Australia’s Hancock buy…

image As flagged by Spark earlier, GVK Power and Infrastructure, which will acquire two coal mines from Australia's Hancock Prospecting for about $2.2 billion, could likely fund the acquisition by raising debt without much strain on key financial parameters as the Hyderabad-based company's leverage is comfortably below industry peers.


The board of GVK is expected to meet soon to take a formal decision on the transaction that has also been approved by its lead banker,

ICICI Bank.

 
The board meet may focus on the route to be adopted to fund the acquisition. According to information available with the Economic Times Intelligence Group, GVK Power's debt:equity ratio - which typically denotes the ability of the company to raise loans - is favorably placed compared to its competitors such as
GMR Infrastructure and Lanco Infratech, who have also acquired coal mines in the recent past to feed their power plants.

GVK Power and Infrastructure's current debt-equity ratio is 1.2 which is much lower than GMR's 2.6 and Lanco's 2.7. As on March 31, 2011, GVK's net debt was Rs 5,548 crore, while its equity stood at Rs 4,540 crore. Power companies typically have a large debt-equity ratio due to the high cost of setting up the projects where large loans are contracted.

 
In this industry, the ratio typically goes up to 2.5 to 3. The special purpose vehicle route, where a newly-formed company would take on the debt, is the most preferred option for power companies. Even if the company were to raise debt of about Rs 4,500 crore for the Hancock transaction, the debt equity of GVK Power will still be lower than its peers, at 2.2, according to an analysis by ETIG

Read More...

August 29, 2011

Floating Solar power plant on Narmada branch canal near Sanand…

image Earlier this year, Tata power partnered with Sunengy, Australia to build the first floating solar plant in India. The construction of the pilot plant in India is expected to commence in August 2011.

The Punjab government in June this year approved the setting up of a project which will generate solar power by utilizing the space over irrigation canals in the state.

 

According to reports, Sanad is now gearing up to house yet another first-of-its-kind project – a solar power plant to be built on Narmada branch canal passing through the town.

As part of a novel concept mooted by the Gujarat chief minister Narendra Modi, the Gujarat government has decided to install solar power panels on one km stretch of Narmada branch canal near Sanand.

“To be developed on public private partnership (PPP) model, the solar plant on Narmada branch canal would generate one Mw of power, once fully operational,” said a top government official.

Interestingly, the solar project is expected to save 100,000 litres of water a year by reducing evaporation of canal water in that particular stretch of one km. The entire stretch would be covered by solar panels, thereby reducing evaporation of water.

As per the industry estimates, a 1 Mw solar power project roughly requires five acres of land. “Installation of solar panels on river canals would also take care of land issue for solar power project,” the government official added. The state government has already roped in one of the leading companies in solar energy space. SunEdison, a subsidiary of US-based global solar energy player MEMC, will be executing the project near Sanand. “This is for the first time such a project is being developed in India,” said a senior official of SunEdison.

The state government has already cleared the project and a new company is being floated to develop the project. “There are different concepts being developed for solar power generation. Developing a solar power generation facility on the water canals is one of such concepts. But for any such effort, first of all a feasibility study needs to be carried out as it is entirely a different ball-game than the existing projects being developed in India,” says Pranav Mehta, founder chairman of Solar Energy Association.

Read More...

Rel Infra, Tata Power gain on tariff hike news…

image Delhi power regulator cleared 22% tariff hike w.e.f. September 1. The last tariff hike in Delhi was made in 2009.

Reliance Infrastructure and Tata Power together control nearly 90% of Delhi power market.

Reliance Infrastructure and Tata Power shares gained substantially post announcement.

At 11:53 hrs Reliance Infrastructure was quoting at Rs 432.50, up Rs 15.80, or 3.79%. It touched an intraday high of Rs 437.80 and an intraday low of Rs 425. It was trading with volumes of 120,579 shares

At 11:53 hrs Tata Power Company was quoting at Rs 1,034.25, up Rs 21.80, or 2.15%. It touched an intraday high of Rs 1,043.90 and an intraday low of Rs 1,017. It was trading with volumes of 9,055 shares

Read More...

Coal India offers 447 MT of coal to power utilities…

image Coal India Limited has offered to supply 447 million tonnes of coal to Power Utilities in 2011-12 subject to availability of wagons by the Railways at an average of 190.4 rakes per day during the year.

This information was given by Minister of State in the ministry of Coal,Shri Pratik Prakashbapu Patil in a written reply to a question in Rajya Sabha today.

The minister informed the house that 216 coal blocks with geological reserves of about 50 billion tones have been allocated to eligible public and private companies under the Coal Mines (Nationalization) Act, 1973. Out of that, 24 coal blocks have been de-allocated. Out of de-allocated coal blocks, two coal blocks were re-allocated to eligible companies under the said Act.

In view of the above, the net allocated blocks are 194 coal blocks with geological reserves of about 44.44 billion tones. Out of these 28 coal blocks have come into production. The rest of the blocks are in various stages of development. Development of coal blocks involves gestation period of 3 to 7 years for reaching the production stage and another two to three years for reaching the optimal production capacity.

The major constraints being faced by the allocates are i) delay in setting up end use projects and ii) time taken for obtaining various clearances for mining and land acquisition.

Read More...

Tata BP Solar commissions 1 MW Solar PV Project…

image According to reports, Tata BP Solar India, a joint venture of Tata Power and BP Solar, on Monday, said it has commissioned its first 1 megawatt (mw) solar photovoltaic power plant in Orissa under the Jawaharlal Nehru National Solar Mission (JNNSM).

The project, owned and developed by S. N. Mohanty at Cuttack in Orissa, was synchronized to the grid on 23 August, the company said in a statement issued here. “Tata BP Solar as an engineering, procurement and construction contractor in association with S. N. Mohanty is very proud in bringing about this first solar photovoltaic plant in Orissa,” the company’s chief executive officer, K. Subramanya, said.

The project, which is designed to run for 25 years, uses 4,400 crystalline silicon modules of 230 Watts each spread out over an area of 5 acres, which will generate electric current when solar radiation falls on them, the release said. The solar power plant is expected to generate 1.41 million units of electricity in the first year.

Tata BP Solar has also taken the contract to provide the operation and maintenance services to the plant for the first 10 years after commissioning, it said.

Mohanty has signed a power purchase agreement (PPA) with the Orissa State Electricity Board for 25 years to supply this power to them.

Tata BP Solar is currently executing projects in different parts of India including Tamil Nadu, Andhra Pradesh, Maharashtra, Chhattisgarh, Orissa, Jharkhand and Uttarakhand under the Indian Renewable Energy Development Agency (IREDA) run scheme.

Read More...

China to fast track India’s Hydel Projects development ! ! !

image While the title of this post seems illogical and surprising at times; the same is becoming a reality now-a-days. With the China factor looming large, the Centre is desperately pushing the Arunachal Pradesh Government to expedite the development of storage hydroelectric projects on the Brahmaputra.

According to reports, China is planning to construct world’s largest hydro-electric project on river Brahmaputra after its own another largest hydro-electric project; Three Gorges Dam.   The proposed project is being constructed on the upper reaches of the river involving the setting up of a massive dam on the bend of the Yarlung Tsangpo — the Tibetan name for the Brahmaputra.

This will force India to speed up its own hydro projects on Brahmaputra to create a strong bargaining position to detract China from building mega hydel projects on the upper reaches of the river.

So far, India's success rate on this front has been dismal. Projects such as the 3,000-MW Dibang have been stuck for over three years now. Just two projects — NEEPCO's 600 MW Kameng and NHPC's 2,000 MW Lower Subhansiri — have a realistic change of coming up on the Brahmaputra over the next six years.

Even as NTPC Ltd has been roped in to prepare a feasibility study for a proposed 9,750-MW Siang Upper hydroelectric project, analysts are sceptical of how fast things can move.

Road and rail links, a prerequisite for transporting equipment to project sites, are lacking desperately. A key transmission link that was to come up for strengthening linkages with the North-Easter during the current Plan period is still held up for funds.

Additionally, the stated position of the Arunachal Government to avoid storage projects involving big dams is a hurdle.

The Ministry of Power has recently stated before the Parliamentary Standing Committee on Energy that it is trying hard to convince the Arunachal Government on the need for storage projects, officials said.

According to Dr. Brahma Chellaney, Professor of Strategic Studies, Centre for Policy Research

“If India harnesses the Brahmaputra in Arunachal through the proposed projects, it will strengthen its case against China's building of a mega-dam at Metog. But, it will have to do it before China does its project. Under the doctrine of prior appropriation, a priority right falls on the first user of river waters,”

The Tsangpo river flows through 1,625 km in Tibet, and then enters Arunachal Pradesh, where it is known as the Siang. Further down, the Siang — after its confluence with the Dibang and Lohit — is known as the Brahmaputra.

India is thus, on the downstream side of all the developments being planned in China on the river.

Read More...

Solar Tariff… Need of re-evaluation ! ! !

image Spark feels a need of re-evaluation of the preferential tariff given to the solar power generation by the Central Electricity Regulatory Commission (CERC)  from regions with less exposure to the sun’s radiation.

According to Spark,  it is illogical to follow a single feed-in-tariff (FIT) concept when it comes to setting up solar power plants. Developed countries such as Germany and the US, wherein Solar Power development is at advanced stage, have multiple tariff system based on the exposure of a particular region to solar radiation. The same policy should be adopted in India.

Similar kind of tariff mechanism is already proposed by CERC and in implementation in various states (such as Maharashtra) for Wind Power Projects wherein the tariff has been declared zone wise which is classified in terms of wind resources.

Under the Jawaharlal Nehru National Solar Mission (JNNSM), CERC has set the tariff at Rs 17.90 per kilowattt hour (kWh) for solar photo voltaic projects and Rs 15.40 per kWh for solar thermal projects. It reviews the cost every year and fixes the tariff accordingly for new projects.

The aim is to install 20,000 MW of solar power by 2022 with the first phase contributing 1000 MW by 2013.

Read More...

Anna shock for NTPC…

image NTPC’s Farakka power project today hit the Anna hurdle as the company had to cancel the commercial production of its new Unit-VI set up at a cost of Rs 2,570 crore.

Finance minister Pranab Mukherjee and power minister Sushil Kumar Shinde were supposed to flag off the 500MW unit but they could not come because of an extended session in Parliament today on the Anna impasse.

Till late on Saturday evening, all parties were trying to find a way out of the Lokpal jigsaw.

NTPC officials will take a decision on when to start the production within 15 days.

The delay in starting the unit, from which Bengal will be getting 147MW, may affect power supply in the state. Two other eastern states — Bihar and Jharkhand — will get 50.5MW and 32.5MW, respectively.

“We had initially demanded that 500MW should be available to us for merchant trading. But we were not allowed. As of now, 75MW from the new unit will remain unallocated,” said S.P. Singh, director (HR), NTPC.

The new unit will raise Farakka power station’s capacity to 2,100MW from 1,600MW.

NTPC also hopes that from 2013 there will be no drop in power generation from Farakka because of low availability of water from the Ganges during summer.

“The water shortage was acute in 2001-02. Then we thought of having a river-bed pump house project to ensure sufficient water supply for the lean period,” said U.P. Pani, executive director, (eastern region 1), NTPC.

The new unit, however, has its dedicated cooling system and will not be affected by the availability of water from the feeder canal.

Read More...

UP signs 600 MW PPA with Gujarat & Adani Power…

image According to reports the Uttar Pradesh Government has entered into a year-long power purchase agreement (PPA) with the Gujarat government and a private utility Adani Power for 600 MW of electricity.


The UP Government’s move of one year PPA seems for political gains as state elections are to be held next year, but it has also helped narrow the demand-supply gap.

 

As per a report of the Central Electricity Authority

, the state received 6,028 MW of power in June against a requirement of 6,564 MW.

 
The
PPA comes at a time when Gujarat is facing a problem of plenty in terms of signing the PPA for its own consumption (Read Here). There are few takers for its 3,000 MW of surplus power, which is set to double in the coming months as private power producers add capacity.


Adani Power's average realization dipped to as low as 2.82 a unit in the first quarter of the current fiscal, as against 3.36 in the corresponding quarter of the previous fiscal. Under the PPA, it will get 4.70 for every unit sold, including transmission charges.

 
Uttar Pradesh, on the other hand, is one of the largest buyers of power in bilateral trade and power exchanges. According to the data published by the Power Exchanges (Indian Energy Exchange and Power Exchange of India), it also pays one of the highest tariffs in the country to procure it. In May, the state accounted for 20% of bilateral power trade, against only 3.8% in 2010 and 5.5% in 2009.

This politics-power nexus may prove to be a bonanza for voters, some of whom may be reluctant to pay a higher price for electricity, but it has its down side: It hampers effective check on power theft and slows down privatization of power distribution. This explains why Gujarat-based Torrent Power will have to wait longer to take over Kanpur's electricity distribution network.

Read More...

August 28, 2011

World’s Largest Power Plants, Spark’s Power Houses Series – Part – 1…

Upon request of lots of readers, Spark has initiated to provide its reader a weekly update on World’s largest Power Plants.

For that Spark started a series called, Spark’s Power House Series.

As a first article of the series, Spark will present the a summary slideshow giving overall information of world’s larges 25 power plants.

So, go ahead, see the article and wait for another…

Read More...

August 27, 2011

India to add 3,500 MW of renewable power during the current fiscal…

image India will be adding about 3,500 MW of renewable power during the current fiscal. which would entail a capital investment of about 29,000 crore, Renewable Energy Minister Farooq Abdullah said on Thursday.

Spark sensed that a power generation capacity of around 3400 MW (grid-interactive) and 130 MW (off-grid / captive) from various renewable energy sources, mainly wind, solar, biomass and small hydro, will be added in the country during the current financial year 2011-12.


Considering the historical trends, half of the capital investment would be towards

wind energy, investments in solar power are expected to be about Rs 9,000 crore. Other renewable sources like small hydro power and bio-power would have investments of about Rs 3,000 crore and Rs 2,500 respectively.

Additional investment of about Rs. 1,000 cr. is envisaged in deployment of decentralized renewable energy systems/ devices like biogas plants, solar water heating systems and SPV lighting systems in remote villages/ hamlets.


These include Generation Based Incentives (GBI) Scheme for wind power and solar power to attract private investment by Independent Power Producers and incentives like capital subsidy and concession on excise duty. The government has also created a contingency fund for solar power projects if state utilities fail to make payments.

Read More...

Planning Commission’s views on coal shortfall…

image The Planning Commission has sounded the alarm over falling coal supplies, saying that special consideration should be made for projects in environmentally sensitive areas.

In its approach paper to the Twelfth Five-Year Plan, the commission has sought a thorough review of the current approach to the environment-versus-development debate, clearly according top priority to the country's development agenda.

 
At the centre of the commission's critique is the 'go and no-go area' policy for coal blocks and the Comprehensive Environmental Pollution Index, or CEPI, norms adopted by the environment and forests ministry.


"Part of the reason for the shortfall in coal production is the implementation of tighter environment-related regulations, and problems in rehabilitation and resettlement and land acquisition," the document notes.


The commission had originally targeted coal production at 680 million tonnes during the ongoing 11th plan (2007-12), but scaled it down to 630 million tonnes during the mid-term appraisal in 2010. The target was further lowered to 554 million tonnes. Coal output expanded at 7% a year during 2004-05 to 2009-10, but stagnated in the previous fiscal. In the past five years, demand grew at an average 8% and is expected to continue at the same rate during the next plan.


Coal projects have struggled to get environment clearances since 2009, when the ministry's no-go classification disallowed mining in 203 coal blocks. According to a coal ministry's projection, the output from those 203 blocks, estimated at 660 million tonnes annually, could have been used to generate around 1.3 lakh megawatts of power a year.


"The environment ministry had adopted the policy of 'go, no-go'a¦ This would have severely impacted the ability to expand domestic production of coal," said a commission official. "The policy had to be reviewed and now some coal blocks have been cleared. This has to be continued to ensure coal availability.''


In January 2010, the environment ministry imposed a temporary ban on development works, including some coal mining projects in Jharkhand and Chattisgarh in industry clusters identified under CEPI norms. CEPI is an index of 88 industrial clusters across India, ranked according to their impact on environment and was developed to plan developmental projects in tandem with environmental protection.


The commission said the CEPI norms had prohibited mining in areas with high pollution index even if pollution was because of some other industry. "Coal being location specific, there is clearly a need for review of this (CEPI norms) approach," the paper notes. Currently the issue is under consideration of a group of ministers headed by

Finance Minister Pranab Mukherjee.


The commission estimates a significant rise in reliance on imported coal as it would not be possible to meet the increased demand from domestic sources. Coal imports are expected to rise to over 200 million tonnes from the current 90 million tonnes by the end of the 12th plan.


The increase in reliance on imports not only portends a significant increase of 30% to 50% in costs for power plants, it also necessitates expensive technological upgradation as the units are not designed to take more than 10-15% of imported coal at present.

Read here the full presentation of Planning Commission on subject mater…

Planning Commission on Twelth Five year plan
Read More...

Discoms to pay higher penalty for over drawl…

image

Spark learnt from the market sources that  the Indian Government proposes to increase penalties on distribution utilities for overdrawing electricity from the grid, a move that is expected to raise demand and prices in the short-term open market and help merchant power plants run by private firms such as Adani Power, Lanco and Monnet Power.
This  move may also be useful in preventing the grid collapse due to over drawl and force the utilities to shed load.

Power prices in the short-term market are closely linked to penalties imposed by the regulator. Distribution utilities prefer purchasing from the open market if charges for overdrawing from grid are high.


Power sector regulator

Central Electricity Regulatory Commission (CERC) has proposed to levy penalties on distribution utilities if grid frequency falls below 49.5 Hz against the earlier limit of 49.2 Hz. Grid frequency falls when demand is greater than generation.

 
The penalties, called unscheduled interchange (UI) rates, are levied on state distribution utilities when they do not draw power as per agreed schedules. The power generators are also charged when they inject less or more power than their declared schedules.

 
"The commission is of the view that the utilities should plan for procurement of power on long-term, medium-term and short-term basis instead of resorting to overdrawal through unscheduled interchange," CERC said in its draft regulations.


A Maharashtra energy department official said the proposal was untimely as most distribution utilities are facing a severe cash crunch. An official in Andhra Pradesh Transmission Corporation said the utility was not in favour of the proposal that would force it to resort to load shedding as power would become costly.

Read More...

August 26, 2011

TD Power IPO over subscribed 2.92 times…

image The initial public offer (IPO) of TD Power Systems was over subscribed 2.92 times on the last day of the issue on Friday.
The company's IPO received bids worth 2.2 crore equity shares till 1700 hrs, as against 75.62 lakh shares on offer, as per the data available with the
National Stock Exchange.
The company has fixed an IPO price band of Rs 256-Rs 261 per equity share.


Air-conditioner generator manufacturer TD Power Systems aims to raise around Rs 227 crore through IPO for expansion and debt repayment.


The company proposes to utilise the proceeds of the issue mainly to finance the expansion of the existing manufacturing plant in Dabaspet, Bangalore and for the construction of a project office in Bangalore.

The net proceeds of the issue will also be utilised for repayment of debt, fund working capital requirements and for other general corporate purposes.


The company's clientele comprises companies operating in cement, steel, paper, chemical, metals, sugar co-generation, bio-mass power plants and hydro-electric power plants.

Enam Securities is the global coordinator and book running lead manager for the Issue. Antique Capital Markets and Equirus Capital are the book running lead managers for the issue.
Read More...

Indian Renewable Energy Certificate (REC) prices to be cut by 15-30%…

image According to reports, the Central Electricity Regulatory Commission has suggested a 15 to 30 per cent cut in prices for renewable energy certificates (RECs) effective April 2012 for five years.

This move is intended to make REC trading attractive.

The CERC has reduced the forbearance price for non-solar REC to Rs 3.3 a unit (Rs 3,300/ MWh), while keeping the floor price at the current level of Rs 1.5 a unit (Rs 1,500/MWh).

For solar REC the forbearance price has been reduced to Rs 13.4 /unit (Rs 13,400/MWh) from Rs 17/unit (Rs 17,000/MWh) and floor price to Rs 9.3/unit (Rs 9,300/MWh) from Rs 12/unit (Rs 12,000/MWh).

But, the industry has been voicing its concern as they felt that downward price revision will jeopardise the flow of investments in green projects. The industry has been seeking that the price should be kept at the same level for the REC mechanism, which is still at a nascent stage to be stabilised.

The REC mechanism is meant to provide an additional stream of revenue for green energy project proponents.

The trading is confined to non-solar projects such as wind power, bio-mass and hydro-electric.

Most of the stakeholders felt that there is a need for longer term control period as RE project developers as well as lenders seek a long term visibility to make necessary decision for participating in the REC mechanism upon evaluating price risk and off take risk.

The complete order of CERC on REC Pricing is embedded below.

 

 

Order on Forbearnace & Floor Price 23-8-2011
Read More...

Update on Wind Power in India…

image A wind power capacity of 565 MW has been installed in the country in the current year (upto July, 2011) with private sector investment of around Rs. 3,400 crore.

Spark learnt that the Minister of New and Renewable Energy has informed that the Government is promoting wind power projects through private sector investment by providing fiscal and promotional incentives such as 80% accelerated depreciation, concessional import duty on certain components of wind electric generators and excise duty exemption to manufacturers.

He said a 10 years tax holiday on income generated from wind power projects is also available. The Minister added that loans for installing windmills are available from Indian Renewable Energy Development Agency (IREDA) and other Financial Institutions while technical support including wind resource assessment is provided by the Centre for Wind Energy Technology (C-WET), Chennai.

Dr.Farooq Abdullah said preferential tariff is also being provided in potential states. He said the Government has also announced a Generation Based Incentive (GBI) under which Rs. 0.50/unit generated from wind power projects is being provided to the projects which do not avail of accelerated depreciation benefit.

Read More...

FDI worth over Rs. 4000 crore in renewable energy sector…

image India has received Rs 4,900 crore in the last three years as Foreign Direct Investment (FDI) in the renewable energy sector, Lok Sabha was informed on Friday.
Spark found that New and Renewable Energy Minister
Farooq Abdullah said in written reply to a Lok Sabha query that: “ Approximately Rs 4,900 crore has been received as FDI equity inflows in the renewable energy sector during the last three years and including the current year,"

The highest investment took place in 2009-10 when Rs 2,872 crore were received in FDI.

In the same context, Spark found that a recent Ernst and Young report has ranked India as the third-best investment destination in the world after China and the US.

The Minister said that several key initiatives taken in the recent past include the introduction of generation-based incentives scheme for wind power to promote projects and the launch of Jawaharlal Nehru National Solar Mission with 22,000 MW target for solar power by 2022.

 
Meanwhile, replying to another query, Abdullah said it is envisaged that a power generation capacity of around 3400 MW grid-interactive and 130 MW off-grid power will be produced from various renewable energy sources in the country during the current financial year 2011-12.

"The same would require capital investment of the order of around Rs 29,000 crore including Rs 14,500 crore in wind power, Rs 2,500 crore in small hydro power, Rs 3,000 crore in bio-power and Rs 9,000 crore in solar power," he said.

 
The Minister said an additional investment of about Rs 1,000 crore is envisaged in deployment of devices like biogas plants, solar water heating systems and SPV lighting systems in remote villages.

Read More...

UMPP Coal usage rules may be revised…

image The government may amend the rules governing bids for ultra mega power projects (UMPPs), where the usage of excess coal from captive mines meant for these large-sized plants may have to be clearly specified upfront. This is being done to usher in transparency and, hence, avoid any potential controversy.

The move to amend the standard bid documents (SBD) for future UMPPs comes in the backdrop of a legal challenge by Tata Power Co. Ltd. It has appealed to the Supreme Court against a decision by a so-called empowered group of ministers (eGoM) in 2008, to allow the winning bidder, Reliance Power Ltd, to use excess coal from captive mines allotted to it for the 4,000 megawatts (MW) Sasan power project for another project it has. Earlier, the Delhi high court had upheld the government’s decision.

“This issue has been raised. Whenever coal reserves are worked out, they are estimated quantities. To assume that there will be a matching quantity is wrong. If it is more, then what is to be done with the coal? It can be used for other projects that have been awarded through the competitive bidding route. There have been discussions. In such a situation some decision should be taken,” said an official associated with the UMPP award process, who did not want to be identified. “Such a condition may be incorporated in the SBD in the next set of projects, which will be awarded after the ones in Chhattisgarh and Orissa,” the same official added.

“We are looking at it,” said a senior power ministry official, who also requested anonymity due to the sensitive nature of the issue.

To be sure, the eGoM had in November 2010, after the decision allowing usage of excess coal from the captive mines at the Sasan UMPP for another project, moved to make this the rule. Accordingly, it asked the coal ministry to issue necessary instructions after getting it legally vetted; however, this is yet to happen.

The UMPP programme has had its share of problems, weighed by ecological concerns and local resistance. Developers, procurers of power—the states —and bankers met on 19 July to discuss changes that need to be made in the SBD. Such a move will also generate greater developer interest in future UMPPs and also bring tariffs down.

“Any such move which enables availability of additional coal resources would certainly help the sector. It is only important that such conditions should be transparently known to every participating developer. Therefore, making resources available will definitely be a welcome move. Once the terms and conditions are transparent and it’s a fair play, the developers would consider such availability to generate extra power and sell at market rates, which is not part of bid quantity and, hence, developers may be in a position to reduce tariff for the bid quantity of power,” said a Tata Power spokesperson.

“Based on the eGoM decision, ministry of coal has granted its approval for utilizing the incremental coal from the captive coal mines allocated for Sasan in the other project of the company, with certain stipulations,” said a Reliance Power spokesperson.

Reliance Power has been the most successful company in terms of UMPPs. Of the four UMPPs awarded till date, it has been the successful bidder for coal pithead projects at Sasan and Tilaiya in Jharkhand, and the imported coal-based project at Krishnapatnam in Andhra Pradesh. The imported coal-based project at Mundra in Gujarat was won by Tata Power.

Expert opinion over the move was mixed.

“For a competitively bid coal mine or integrated coal mine and power project, it appears prudent to allow optimal utilization of coal, particularly in light of the growing gap in demand and supply of coal, as it will allow unlocking of value of scarce resources and may lead to further aggressive tariff bids,” said Dipesh Dipu, director of consulting, energy and resources, and mining at Deloitte Touche Tohmatsu India Pvt. Ltd.

However, Anish De, chief executive at Mercados EMI Asia, an energy consulting firm, argued: “It is a fairly difficult decision to take because it could result in inadequate supplies to the power projects in the latter part of their operating life. Since the reserves are not precisely known at the time of award of project, any decision in this regard will be based on imperfect information, which could later backfire.”

The government wants to set up 16 UMPPs to meet the needs of the world’s second fastest-growing major economy after China. India has a power generation capacity of 180,000MW and expects to add 62,374MW by 2012.

Read More...

CIL to replace R-Cap on Nifty…

State-run Coal India (CIL) will replace Anil Ambani Group firm Reliance Capital in the National Stock Exchange’s Nifty index from October 10. Earlier this month, CIL had replaced another Anil Ambani Group firm Reliance Infrastructure from BSE’s blue chip index Sensex.

Shares of CIL have been doing well since the company was listed in November last year and has become the third most valued firm after Reliance Industries and ONGC. Apart from S&P CNX Nifty Index, there would be changes in CNX Nifty Junior Index, CNX 100 Index, S&P CNX 500 Index, CNX Midcap Index and sectoral indices among others.

The changes were announced on Thursday by India Index Services & Products (IISL), a joint venture between National Stock Exchange and Crisil for managing Nifty.

The decision to revise constituents of various NSE indices was taken by the Index Committee of the Exchange during its periodic review. Meanwhile, the BSE also announced launch of futures and options trading in CIL with effect from August 26.

BSE said in a circular that it had received approval from market regulator Sebi for introduction of F&O contract on CIL. Subsequently, F&O contracts of CIL would start trading on BSE with effect from August 26.

Read More...

Germany’s SMA Solar eyes 1.4GW of business from India…

Germany’s SMA Solar, the world’s largest maker of solar inverters, expects that in 2014 its Indian unit will win about 40 per cent of a market it forecasts will reach 3,500 megawatts, an official of the domestic unit said.

“We are going with the pace of the Indian industry … but our objective is to be in leadership position in India as we are globally,” Rakesh Khanna, general manager of SMA Solar India, said. The firm, which derives close to 56 per cent of its revenue from exports, has been active in the Indian market since October 2010, has 200 Mw worth of business in the country now and announced establishment of its India unit.

“We strongly believe that India will become, or could become, one of the largest PV markets in the world,” said Marko Werner, board member and Chief Sales Officer, SMA Solar Technology AG. Many global solar firms are expanding their presence in India as the country plans to develop solar power capacity to 1,000 MW by 2013 and grow that to 20 Gw by 2022, with an overall investment of close to US $70 billion.

The strong demand in overseas markets had pushed the German firm to post forecast-busting second quarter profit, while providing an ambitious outlook for 2011. SMA’s competitor and No. 2 solar inverter maker Power-One Inc could offset weakness in its European markets as it expanded into the United States, China and India.

Solar panel maker Canadian Solar Inc recently forayed into India, while India has prominent domestic solar equipment makers such as Tata BP Solar, a joint venture between India’s Tata Power and BP Plc and Moser Baer.

With about 250-300 clear sunny days in a year, India’s solar power reception is about 5,000 trillion kilowatt hours per year, meaning just 1 percent of India’s land area could meet the country’s entire electricity requirements until 2030. The peak power deficit, the shortfall between supply and demand at peak hours, was 10.3 per cent in the last fiscal year to end March.

Read More...

India targets over 50,000 Mw of Nuclear Power by 2030…

India plans to import light water reactors from Russia, US and France to boost its nuclear energy generating capacity to 50,000-60,000 Mw by 2030, said former Atomic Energy Commission (AEC) chairman M R Srinivasan.

Delivering the first Homi Sethna Memorial Lecture on ‘Future of Nuclear Power after Fukushima’, the nuclear scientist said  the country would need around 1,300 Gw of electricity by 2052.

Forty per cent of this requirement is expected to come from coal-based plants, 40 per cent from nuclear facilities and 20 per cent from renewable sources like solar or wind, he said.The present power generating capacity of India’s 20 nuclear units is small, most of them having a capacity of up to 220 Mw. The indigenously designed Tarapur 3&4 are the largest with a capacity of 540 Mw, he said. In a couple of months, the first 1,000 MW nuclear plant, built with Russian help, will start at Kundankulam, Tamil Nadu.

In last one year, the country has started construction of four indigenously-designed reactors of 700 Mw each — two each at Kakrapar, Gujarat, and Rawatbhata, Rajasthan. There are plans to have similar reactors in Madhya Pradesh, Haryana, and possibly even at Kaiga, Karnataka, Srinivasan said.

‘China has the biggest nuclear plant construction programme at present,’ Srinivasan said. ‘While they will review their safety practices after the Japanese experience, they will probably continue to develop nuclear power in a big way.’

Since availability of electricity is a serious constraint for both industry and agriculture, India will build 800 Mw supercritical coal-fired units for many more years. ‘But if we have to cut down carbon emissions, we must build a significant nuclear capacity,’ he said.

India is currently producing a small quantity of enriched uranium. ‘We expect to be in a position to build a commercial uranium enrichment plant between 2020 and 2030,’ Srinivasan said. Explaining the slow-paced nuclear power development in India, Srinivasan said the country had limited uranium. ‘Not only is the quantity small, the ore concentration is low, making extraction more costly here,’ he said.

Read More...