Central Electronics Limited is planning to put a 40 MW Solar Photovoltaic (SPV) module manufacturing at Shahibabad, Uttar Pradesh.
It has invited bids for the Turnkey Supply for " Setting Up of 40 MW Solar Photovoltaic (SPV) Module Manufacturing Line on 4th December 2013.
Brief details of the Tender is depicted below:
Scope of Work
- Setting Up of 40 MW Solar Photovoltaic (SPV) Module Manufacturing Line (Turnkey Supply)
- The scope shall include supply, layout design and installation, commissioning, inspection, training, process optimization and warranty with spares for 2 years,consumables for 1 year, AMC for 2 year of PV Module manufacturing line (turnkey) for manufacture of 40 MW SPV Modules. In addition IEC certification is also under the scope.
Basis for Capacity Calculation:
- Solar Cell type : 156 × 156 mm
- Cell Power : 4.0 Watt
- No. of Cells/Module : 72 Pcs
- Matrix : 6 × 12 (Cell Size:156 × 156)
- Yearly working Days : 365 Days
- Working hours/ day : 24 Hours
- Total Hours : 8760 Hours
- Watts/Module : 288 Watts
- Lamination Cycle time : 17 min (with fast cure EVA)
- Uptime : 90 %
- Yield : 99%
Technical Specifications:
- Module size : Up to 2000 mm x 1000 mm or larger
- Solar Cell Type : Mono and Multi crystalline
- Solar Cell size : 156 ×156 mm, Half & One third of 156 × 156 mm
- Cell Geometry : Square / Pseudo square
- Cell Thickness : ≥ 180 μm
- Cell breakage (Line) : ≤1%
- Remote assistance & supervision via internet
Earnest Money Deposit by bidders
Rs. 20,00,000/- (Rupees Twenty lakhs only) OR US$ 32,000 (US Dollar Thirty two thousands only)
Bid Validity
90 days fro date of bid opening (i.e. January 10, 2014)
More details on the tender can be found here.