January 12, 2014

Rooftop solar project in Kerala set to miss deadline...

 

Rooftop solar project in Kerala set to miss deadline...

The state government's ambitious plan to set up 35,000 off-grid rooftop solar power units is set to miss the deadline, at least during the current fiscal.

The state government, which first announced its plan to set up 10,000 off-grid rooftop solar units in December 2012, announced in 2013 that 25,000 more such plants would be set up across the state during the 2013-14 financial year.

However, Agency for non-conventional energy and rural technology (ANERT) could so far install only around 6,600 rooftop solar power units. Moreover, the agency has so far transferred the subsidy to only 1,000 people who set up off-grid solar power units of 1 kW capacity.

According to power minister Aryadan Mohammed, the state government could not utilize Rs 13.93 crore set aside in the 2013-14 budget for providing subsidy to 25,000 households for setting up rooftop solar power units. In a written reply to a question, the minister said on Tuesday that the plan for setting up 25,000 off-grid solar power unit programme failed to take off as the central government refused to give grants for the programme since the target set for 2012 was not met by the state. Also, efforts to facilitate low-interest bank loans to beneficiaries failed to elicit any positive response from banks. In this context, the state government plans to release the state subsidy of Rs 39,000 to 3,600 applicants who have submitted applications for setting up solar plants, he added.

But, according to ANERT authorities, the agency had, in fact, planned to set up only 25,000 units during 2012-13 and 2013-14 period together. However, when the second phase plan was announced, it was wrongly stated that the second phase would alone cover 25,000 households, instead of the original plan of 15,000 additional plants.

"Of the 10,000 plants announced in 2012, we have, so far, installed 6,600 units. For this, beneficiaries are promised Rs 53,262 as central government subsidy and Rs 39,000 as state subsidy. Since the project is being rolled out through agencies empaneled by ANERT, the subsidy amount is released to the respective agencies only after they furnish work satisfaction certificate from the beneficiaries. As per this procedure, we have released the subsidy to only 1,000 agencies'', said M Jayaraju, director of ANERT.

Jayaraju said the agency, so far, received only Rs 5 crore as grant for subsidy. "We hope to complete the first milestone of 10,000 off-grid units before June. Once the target for 2012-13 is achieved, we would be able to get subsidy for more such units from the Centre'', he added. As per the scheme, devoid of central and state subsidy, an individual has to chip in Rs 95,000 on an average for setting up a 1 kW solar power unit.

Source

Read More...

November 25, 2013

ANERT to set up 2-MW solar farm in Palakkad...

 

ANERT to set up 2-MW solar farm in Palakkad...Kerala’s first solar farm on the Mega Watt scale is expected to become operational at Kuzhalmandam in Palakkad district by March next year. The Agency for Non-conventional Energy and Rural Technology (ANERT) will implement the project estimated to cost Rs.16 crore.

Utilising crystalline silicon technology, the grid-fed solar power plant of 2 MW capacity will come up on 12 acres of land. Designed in-house by ANERT, it features flat plate collectors and intelligent inverters. Once commissioned, the farm will feed 30 lakh units of power to the grid every year.

Officials said the project was designed to assist in research and development of grid-interactive power plants. The farm would be established as a turnkey project.

DPR released

Chief Minister Oommen Chandy released the detailed project report (DPR) of the solar farm during the inauguration of the new headquarters building of ANERT here on Wednesday.

He said the availability of quality power was a critical element in Kerala’s development.

He said the power situation in the State warranted a focus on non-conventional energy sources and energy conservation.

Mr. Chandy said mini-hydel projects and solar power offered clean and eco-friendly means of power generation ideal for a State like Kerala.

Solution to power crisis

Delivering the presidential address, Electricity Minister Aryadan Mohammed said non-conventional energy sources were the obvious solution to the power crisis faced by the State.

“With no further scope for additional generation through conventional means, the State will have to make maximum use of wind and solar power to bridge the widening gap between demand and supply.”

Pointing out that 5,000 houses across the State had been provided with subsidized rooftop solar panels generating a total of 5 MW, he stressed the need to popularise the initiative. Mr. Mohammed stressed the need to equip government buildings with green features to save energy.

Saving energy

Highlighting the need for energy conservation, he directed the officials at the open-air venue to switch off the lights that were kept on in broad daylight.

With a built-up area of 25,000 sq ft., the new headquarters complex of ANERT is built on the Green Building concept. It will feature a roof top solar power plant of 15 kW capacity, solar-wind hybrid system, biogas plants, and solar water heaters.

K. Muraleedharan, MLA, Additional Chief Secretary Niveditha P. Haran, and ANERT director M. Jayaraju were among those who spoke.

Source

Read More...

November 21, 2013

Kerala Solar Policy 2013 intends to introduce generation based incentives instead of capital subsidy...

 

Kerala Solar Policy 2013

The Kerala Solar Energy Policy 2013, which seeks to increase the state’s installed solar power capacity to 500 MW in 2017 and 1500 MW by 2030, intends to make solar water heating system (SWHS) mandatory in industrial buildings, government and private hospitals, resorts and hotels.

The policy, unveiled on Wednesday, speaks of generation-based subsidy instead of the usual capital subsidies for off-grid solar projects. “Generation-based incentives will ensure that the systems are installed, maintained and continue to remain functional,” the Policy states. “The existing capital subsidies will be restructured appropriately,” it adds.

The Policy also identifies the entry of “unscrupulous elements” into the field of solar power as one of the reasons for the low popularity of solar power in the state.

As for grid-connected systems, the policy states that the government will initiate a programme under which all public buildings are provided with generation facilities using appropriate technology options.

“As the load cycle of the government offices match with that of the solar plants, they are fitting cases of solar application,” the policy states. The engineering procurement and construction (EPC) mode of implementation will be replaced by a design-build-operate-and-transfer scheme.

The policy states that grid-connected systems will be promoted for domestic consumers in a phased manner. “This will be one after formulating grid connection standards for low tension (LT) distribution in line with this policy,” it states.

Source

Read More...

November 20, 2013

Kerala Cabinet okays Solar Energy Policy...

 

Kerala Cabinet okays Solar Energy Policy

The Kerala Cabinet has approved a Solar Energy Policy that seeks to raise installed capacity of the solar sector to 500 MW by 2017 and 1,500 MW by 2030. The mission is to contribute to long-term energy security of the State well as ecological security by reduction in carbon emissions.

Chief Minister Oommen Chandy told newspersons here that the draft policy had been posted on the website of the Agency for Non-Conventional Energy and Rural Technology.

Comments received from stakeholders, including the general public, have been incorporated to the final document.

Land suitable for development of solar installations in the possession of either Government or private individuals will be identified, as per the original draft.

Such identified lands shall be offered to developers for grid connected solar installations.

Lease rentals fixed by revenue department shall be payable to the land owner. Only lands which do not have an immediate productive use shall be thus identified.

FEED-IN TARIFF

In the case of offsite commercial installations, the State Electricity Regulatory Commission will notify the normative feed-in tariff of solar power for procurement by State power utility.

Feed-in tariff refers to payments made out to ordinary energy users for renewable electricity generated by them.

Net metering shall be applicable for all agencies that consume grid power and have installed solar installations with some form of Government subsidy.

Special feed-in tariff will be made applicable for consumers with monthly consumption of 30 units and below.

For off grid systems, the policy seeks to ensure bank finance at attractive rates and provide generation-based incentives. Existing capital subsidies shall be restructured appropriately.

GENERATION FACILITIES

For grid connected systems, the Government would initiate a programme by which all public buildings are provided with generation facilities using appropriate technology options.

The policy urges all concerned to make use of the rooftop and premises to install solar plants to match maximum demand within a period of two years.

Grid connected systems will be promoted for domestic consumers in a phased manner after formulating grid connection standards for LT distribution.

In this regard cluster-wise installations will be given suitable incentives on a conditional basis for adopting solar installations.