Featured Articles...

Showing posts with label UPPCL. Show all posts
Showing posts with label UPPCL. Show all posts

January 2, 2014

Noida to get 20 substations...

 

Noida to get 20 substations...

The Uttar Pradesh Power Corporation Limited (UPPCL) will commission around 20 33/11kV substations across Noida during 2014 to ensure equitable distribution of electricity to different sectors. These substations will be constructed by Noida Authority and later handed over to UPPCL.

Power officials said these 20 substations form part of a network designed for transmission and distribution of electricity in Noida through a number of power houses of varying capacities. Other than these substations, two substations of 400kV each and one of 765kV have been approved. These projects too are in different stages of work.

Corporation officials said work is also set to commence on four 220kV substations in Noida. "The smaller-capacity substations will help enable distribution of electricity within a sector or a cluster of sectors. Existing small capacity substations will not be enough to handle the load once more power is brought into the city by the larger substations," said a senior power corporation official.

At present, Noida gets electricity through a single 400kV substation in Pali.

Source

Read More...

December 28, 2013

UPPCL signs power purchase agreement for 110 MW solar power with the solar power developers...

 

UPPCL signs power purchase agreement for 110 MW solar power with the solar power developers...

The UP Power Corporation Limited (UPPCL) has entered into an agreement with solar power developers for purchasing 110mw of power.

The agreement was entered in the presence of UP chief secretary, Javed Usmani, who said that under the state solar policy the state government will be setting up 500mw of power solar power plants in the state.

The UP New Energy Development Authority (UPNEDA) had invited bids for setting up of power plants compositely to the tune of 200mw. The authority had also put in place a competitive bidding process for power tariff from these power plants. Against this, the authority received bids for 130mw. On Friday, the UPPCL signed the agreement for 110mw power.

The solar power plants with which the agreement was signed included, 10mw by Azure Surya Private Limited, 50mw by M/s Essel Infra Project, 20mw by Moser Baer, 10mw by M/s Refex Energy, 10mw by M/s Jackson Power and 10mw to be set up by DK Infracon. All these power plants are proposed to be set up in Bundelkhand region. Usmani said that NEDA would soon invite bids for the rest 370mw.

Source

Read More...

December 4, 2013

UP Cabinet clears over 2100 Mw purchase from private players...

 

UP Cabinet clears over 2100 Mw purchase from private players...

Unfazed by opposition's criticism of power purchase at higher rates, UP cabinet on Tuesday, gave its nod to buying over 2100 Mw of power from three companies for 25 years at a rate ranging between Rs 5.58 per unit and Rs 5.84 per unit.

The cabinet also gave a year's extension to work contract of a Spanish transmission company, Isolux Corsan, engaged in construction of transmission lines to evacuate power from three upcoming plants in Uttar Pradesh.

The purchase of power from three companies-KSK Mahanadi, PTC India Limited and Krishnapattanam- happens to come through under the case-1 bidding process that envisages procurement of 6000 Mw of power for a period of 25 years, beginning 2016 up to 2042. Chief secretary Jawed Usmani said while 1000 Mw of power would be purchased from KSK Mahanadi, PTC will wheel out 361 Mw to the state. Likewise, the Krishnapattanam power corporation will be providing 800 Mw of power to the state. In all, around 2100 Mw of power will be purchased from the three external sources to meet the ever growing demand for power in UP. The issue was earlier cleared by the UP Power Corporation Limited (UPPCL) board as well as the energy task force (ETF) headed by UP chief secretary.

Principal secretary Energy, Sanjay Agarwal, said since power will be purchased at a levelised tariff over a long period, the actual cost of power comes down drastically. For example, in the first year (2016-17) the KSK will be providing power at the rate of Rs 4.713 per unit. The PTC India and Krishnapatnam will provide it at Rs 4.784 and Rs 4.436 per unit, respectively. This increases gradually over a period of time and by 2042, the three companies will be providing power at the rate of Rs 9.682, Rs 11.474 and Rs 18.275 per unit, respectively.

The principal secretary said power purchase under the case-1 bidding was sent for law department clearance which did not allow negotiations to be carried out under the stipulated guidelines. He said clearance was also taken by the UP electricity regulatory commission (UPERC). "Had power been purchased every year, the cost would have gone up dramatically,'' a senior UPPCL official said. Agarwal said guidelines for power purchased under the Case-1 have been changed, hence the cost of coal would be computed accordingly in per unit charge. This raised the chances of a further hike in rate of power to be purchased.

At least seven bidders (L-1 to L7) had come forward. The three companies which bid the lowest prices included NSL power (for providing 300 Mw at the rate of Rs 4.48 per unit), TRN energy (for providing 390 Mw at the rate of Rs 4.886 per unit) and Lanco Babandh (for providing 390 Mw at the rate of Rs 5.074 per unit). The state government has already issued a letter of intent to purchase power from these companies. The state cabinet, however, rejected L4-RKM Powergen (for 350Mw) which bid at the cost of Rs 5.088 per unit, due to its failure in meetings the commitments. Usmani said the state cabinet had decided to invoke company's bid bond of Rs 10.5 crore.

Even as the state government gears up to purchase power from external sources, questions are being raised if this would further raise the debt of the state government. Chief minister Akhilesh Yadav, who also holds the energy portfolio, had been blaming the previous Mayawati government of leaving UPPCL cash-strapped by taking loans that resulted in liability of Rs 25,000 crore.

In another decision, the state cabinet gave a year's extension to Spanish company Isolux Corsan to complete laying of transmission lines to evacuate power from power plants. The company was roped in January 2012 and was supposed to finish its work by January 2014. The company, however, was caught in a controversy after it insisted on changing the specification of conductors. The UPERC, however, rejected the demand. In the process the work on the project got delayed. The company was given the work contract of constructing transmission lines to evacuate power from three power plants-Bara, Meja and Tanda.

The company has now been asked to get the work completed partially by December 2014 to evacuate power from at least one Bara unit of 660 Mw. The rest of the work may be done by August 2015 when the other two units of Bara (660 x 2 Mw), Meja and Tanda get operational.

Source

Read More...

November 26, 2013

Isolux gets more time for laying transmission lines in Uttar Pradesh...

 

Isolux gets more time for laying transmission lines in Uttar Pradesh...

The Energy Task Force headed by UP chief secretary Jawed Usmani on Monday extended the time limit to Isolux Corsan for laying transmission lines. The company is involved in laying transmission lines and construction of power sub-stations.

The final approval in this matter will be given by the Cabinet. Recently the UPPCL had extended the deadline till December 31, 2014, for the first phase of laying the transmission line, and August 31, 2015, for the second phase.

The Energy Task Force on this occasion reserved its decision on giving further extension to the agreement with nine companies. Hence, no decision on the nine power projects could be taken on Monday. The UPPCL had recently in a proposal gave an extension of 18 months to nine power projects signed through the MoU route during the Mayawati regime.

Awadhesh Varma of UP Rajya Vidyut Upbhogta Parishad said Isolux was assigned the task of laying transmission lines in 2011, and it was asked to complete it by January 2014. But, owing to usage of sub-standard conductors, the company came under the scanner and the process of laying transmission lines was delayed. Varma also said that the Parishad will approach the Uttar Pradesh Electricity Regulatory Commission against the decision to grant more time to Isolux.

He also claimed that on earlier occasion too the Upbhogta Parishad had raised the issue with the Uttar Pradesh Electricity Regulatory Commission on the proposal of Isolux to change the configuration of the transmission lines in the Rs 10,000 transmission project. It was only after the UPERC cracked the whip on Spanish Transmission Company that the company agreed to the conditions that it agreed to during the bid process.

Isolux Corsan has been showing interest in installing wires made out of aluminum, termed as All Aluminum Alloy Conductors (AAAC). The company, though, had bid for installation of ACSR conductors instead. Interestingly, in July last year, the Uttar Pradesh Transmission Corporation (UPTCL) had told the commission that the AAAC conductors' line losses will increase by 7% to 11%.

The letter issued by the UPTCL said by using AAAC conductors the company will be saving significantly in the capital cost due to lighter towers, lighter foundation and longer span, which will have a commercial implication on project cost and also on the tariff. The UPPTCL said such post contract changes are not possible as per Central Vigilance Commission guidelines.

The UPERC, in its order dated April 8, said since the conductor type to be used in the transmission line has been associated with ACSR conductor under the scope of work in the bid document, the panel has decided that only ACSR conductors shall be used in the construction of line. The commission also asked the corporation to submit its acceptance of conductors within two weeks from the date of the order under intimation to the commission.

Source

Read More...

November 10, 2013

Default in payment of Unscheduled Interchanges (UI) charges for the energy drawn in excess of the drawl schedule by UPPCL....

 

Default in payment for UI Charges by UPPCL

CERC directed the Uttar Pradesh Power Corporation Limited to submit payment plan of outstanding UI charges to NRLDC including interest due on affidavit by 11th November 2013.

Uttar Pradesh Power Corporation Limited submitted to CERC that it has paid 50% of the outstanding Unscheduled Interchanges (UI) charges by 31.10.2013 and the remaining 50% would be paid by the month of March, 2014 in equal monthly installments.

NRLDC has also confirmed the payment of 50% of the outstanding UI Charges by UPPCL. 

In response to the Commission’s query on the stay by the Hon`ble High Court of Allahabad of 40% UI charges, the representative of NRLDC clarified that stay is still continuing and an amount of ` 371 crore is covered under the stay order.

UPPCL submitted that pursuant to the Financial Restructuring Plan, UPPCL has arranged loans from the banks and made payment for 50% of the outstanding UI charges.

They further submitted that the balance outstanding UI charges would be liquidated in equal monthly installments by 31.3.2014. He further submitted that the outstanding UI charges contained the surcharge of an amount of Rs. 114 crore. As per Commission's direction, a meeting was held with NRPC and the constituents of Northern Region for waiver of late of payment surcharge.

However, none of the recipient constituents has agreed to waive the interest on late payment of UI charges.

UPPCL further submitted that the surcharge of Rs. 114 crore may be waived by the Commission in exercise of power of relaxation under Regulation 12 of UI Regulations and argued that in the past, the Commission has exercised its power of relaxation in other cases and has granted relief to the aggrieved parties.

However, the Commission observed that the request of UPPCL is against the provisions of the UI regulations and would set a precedent for others to make similar requests. The Commission further observed that since the surcharge is payable to the other constituents of the Northern Region, UPPCL has the liberty to take up the matter with the constituents to reimburse the interest portion after the payment dues are cleared by UPPCL with interest.

Read More...