Featured Articles...

December 8, 2013

Tariff hike alone cannot bail out Discoms: Care report

 

Tariff hike alone cannot bail out Discoms: Care report

Structural improvements and financial discipline are far more crucial for improving the health of distribution companies than depending on tariff hikes, rating agency Care has said. According to a Care report, which analyzed 30 Discoms in 11 states, a series of tariff hikes had been effected by these companies in the last three years.

 

"Tariff hike alone can't bailout the Discoms given that there are substantial regulatory assets on their balance sheets," Care Rating said in a report.

The report also said that apart from untreated gap which has left tariffs far from being cost reflective, unsustainable levels of cross-subsidization with a slowdown in high paying subsidizing consumers like commercial and industrial sector and emergence of group captive model wheeling away high paying consumers, have further impacted their financial health. The report observed that total power demand has tapered this fiscal so far with a slowdown in growth and delay in restructuring state Discoms.

According to the study, demand for power grew by only 1.7 per cent in September compared to year-ago period, led by off-take back-down by Discoms coupled with continuing load shedding in tier 2-3 cities in northern and southern region.

"For demand to improve, there is a need for companies to go slow on implementing financial restructuring package, buying power from the open market and entering into fresh long-term power purchase arrangements by inviting case-I/II bids," it said.

Source

Read More...

Heavy Industries Minister concerned over higher ECB cap for power projects...

 

Heavy Industries Minister concerned over higher ECB cap for power projects...

The Heavy Industries Ministry has raised concerns over enhanced external commercial borrowing limit for funding domestic power projects, citing that the move adversely impacts local gear makers including BHEL.

The red flag comes at a time when the domestic power equipment makers are grappling with tough business conditions amid sluggish growth, stiff competition and cheaper imports.

"The Reserve Bank of India's decision to enhance ceiling on External Commercial Borrowings (ECBs) for financing of domestic power projects has further affected the prospects of domestic power equipment makers," an official told PTI.

In this regard, the Heavy Industries Ministry has also written to the Finance Ministry, he added.

The major concern is that higher limit for raising funds overseas also facilitates sourcing of equipment from outside the country for power projects. Such a scenario adversely impacts the business prospects of domestic equipment makers.

Many Indian entities have sourced equipment for their power projects along with finance from overseas, especially from China.

As part of efforts to boost capital inflows into the country, the RBI recently eased ECB norms.

In September, the central bank allowed all types of companies to avail trade credit facility from overseas for import of capital goods.

"On a review, it has been decided to allow companies in all sectors to avail of trade credit not exceeding USD 20 million up to a maximum period of five years for import of capital goods as classified by Director General of Foreign Trade (DGFT)," RBI had said.

Earlier, only companies in the infrastructure sector were allowed to raise such trade credits.

Currently, local players, including state-owned BHEL, are going through a difficult period, especially from 2011-12.

Besides cheaper imports, weak investment sentiment, financing constraints and lack of level-playing field with regard to foreign competitors are hurting the domestic entities.

"... Some of the existing power projects are going slow or are being put on hold due to customer's constraints in releasing payments for deliveries and other constraints faced by them thereby curtailing progress of their projects," the official said.

Source

Read More...

Odisha Govt to set up Solar Power Project at Manmunda in Boudh with Rs 400 Cr investment...

 

Odisha Govt to set up Solar Power Project at Manmunda in Boudh with Rs 400 Cr investment...

In another step towards generation of green power, Energy department of Odisha Govt has proposed for a Solar Power project at Manmunda of Boudh district to be set up by Green Energy Development Corporation of Odisha Ltd. (GEDCOL).

A high level meeting to this effect was held under the Chairmanship of Chief Secretary Jugal Kishore Mohapatra in secretariat conference hall today wherein Secretary Energy Pradeep Kumar Jena outlined the broad features of the project for discussion. Discussions in the meeting reveal that Solar Energy Corporation of India has proposed to set up solar projects of 750 MW in different parts of the country.

It has been decided in the meeting that GEDCOL will bid for 50 MW solar power to be set up in Odisha at the proposed site. IDCO has been requested to provide land to GEDCOL. It has also been decided that the generated power will be purchased by GRIDCO as per renewable power obligation.

It has been estimated that around 250 acres of land will be necessary to set up the project @ 5 acre for generation of 1 MW of solar power. The proposed minimum cost of the project will be around Rs 400 cr.

It has been in principle decided that the project will be implemented on PPP mode. CMD IDCO Vishal Dev, CMD GRIDCO Hemant Kumar Sharma, CMD GEDCOL Sahadev Khatua, AGM GEDCOL Sanjeeb Kumar Tripathy along with other senior officers department of Energy participated in the discussions.

Source

Read More...

Chinese firm Dongfang in talks to buy Trichy-based power firm...

 

image

Chinese firm Dongfang is in talks to take over Trichy-based power equipment manufacturer Cethar. The acquisition will help the Chinese company have presence in India. It will also help Dongfang control its costs as well as comply with the localisation norms in India.

Cethar, formerly known as Cethar Vessels, manufactures both sub-critical and super-critical boilers, used in power plants. It also designs and constructs thermal power plants up to a capacity of 800 megawatts. In 2010-11, it clocked sales worth Rs 2,430 crore. "The valuation of this company comes to around Rs 500-600 crore. They are currently in talks and the acquisition would help Dongfang have an entry into Indian manufacturing," said a person directly involved with the deal. Neither Cethar nor Dongfang responded to an email questionnaire.

Cethar was founded by K Subburaj, who started it in Trichy as a sub-contractor to Bharat Heavy Electicals (BHEL). Subburaj had worked for the Indian Space Research Organisation (ISRO) prior to starting the venture. The company expanded into power manufacturing and then into a construction company for power plants.

Analysts say Indian facilities can help foreign companies as they have been asked to set up service centres in India to help power plants under construction using the equipment. "This move will help because power companies will definitely prefer firms that have domestic presence," said Piyush Nimgaonkar, manager at CARE Research.

Dongfang, along with Shanghai Electric and Harbin, has already garnered a major market share amongst private power generators. About 24,437 megawatts power capacity is installed in India; plus, 40,000 megawatts of power capacity, based on Chinese equipment, is under construction. This has created a huge furore amongst Indian manufactures such as state-owned Bharat Heavy Electricals (BHEL) and private engineering company Larsen & Toubro.

After multiple representation by industry bodies as well companies, the government has made it mandatory for Chinese companies to have service centres in India. In transmission and distribution sector, state-owned companies are preferring companies having domestic manufacturing facilities. A bulk tender for the country's largest power generator, NTPC, had barred foreign companies which did not have an Indian joint venture partner.

Source

Read More...

December 7, 2013

Central Electronics to put up 40 MW Solar PV manufacturing Unit at Uttar Pradesh; invites bids for supply of equipments...

 

Central Electronics to put up 40 MW Solar PV manufacturing Unit at Uttar Pradesh; invites bids for supply of equipments...

Central Electronics Limited is planning to put a 40 MW Solar Photovoltaic (SPV) module manufacturing at Shahibabad, Uttar Pradesh.

It has invited bids for the Turnkey Supply for " Setting Up of 40 MW Solar Photovoltaic (SPV) Module Manufacturing Line on 4th December 2013.

 

Brief details of the Tender is depicted below:

Scope of Work

  • Setting Up of 40 MW Solar Photovoltaic (SPV) Module Manufacturing Line (Turnkey Supply)
  • The scope shall include supply, layout design and installation, commissioning, inspection, training, process optimization and warranty with spares for 2 years,consumables for 1 year, AMC for 2 year of PV Module manufacturing line (turnkey) for manufacture of 40 MW SPV Modules. In addition IEC certification is also under the scope.

Basis for Capacity Calculation:

  • Solar Cell type : 156 × 156 mm
  • Cell Power : 4.0 Watt
  • No. of Cells/Module : 72 Pcs
  • Matrix : 6 × 12 (Cell Size:156 × 156)
  • Yearly working Days : 365 Days
  • Working hours/ day : 24 Hours
  • Total Hours : 8760 Hours
  • Watts/Module : 288 Watts
  • Lamination Cycle time : 17 min (with fast cure EVA)
  • Uptime : 90 %
  • Yield : 99%

Technical Specifications:

  • Module size : Up to 2000 mm x 1000 mm or larger
  • Solar Cell Type : Mono and Multi crystalline
  • Solar Cell size : 156 ×156 mm, Half & One third of 156 × 156 mm
  • Cell Geometry : Square / Pseudo square
  • Cell Thickness : ≥ 180 μm
  • Cell breakage (Line) : ≤1%
  • Remote assistance & supervision via internet

Earnest Money Deposit by bidders

Rs. 20,00,000/- (Rupees Twenty lakhs only) OR US$ 32,000 (US Dollar Thirty two thousands only)

Bid Validity

90 days fro date of bid opening (i.e. January 10, 2014)

 

More details on the tender can be found here.

Read More...

December 6, 2013

Tata Power completes restoration work at Mundra plant...

 

Tata Power completes restoration work at Mundra plant...

Tata Power today said the restoration work at its Mundra plant, which was impacted by fire, has been completed and the insurance claim is being processed.

“Restoration of the impact of fire on conveyor was achieved on November 20, 2013 and the company has processed the insurance claim as per coverage,” Tata Power said in a regulatory filing to the stock exchanges.

Tata Power’s 4,000-MW ultra mega power project at Mundra in Gujarat caught fire on November 18 last month, partly affecting coal feeding conveyors.

According to sources, the procurer states will suffer loss of availability of electricity to the extent of 433 million units (Gujarat), 182 million units (Maharashtra), 91 million units each (Haryana and Rajasthan) and 114 million units (Punjab). The share of these states is 47.5 per cent, 20 per cent, 10 per cent, 10 per cent and 15 per cent, respectively.

The power tariff of this plant is Rs 2.26 per unit.

Source

Read More...

GERMI says the Solar PV Projects can be done at the Fixed cost of Rs. 3.5 Crores/MW...

 

GERMI says the Solar PV Projects can be done at the Fixed cost of Rs. 3.5 Crores/MW...

Successful research and development carried out by Gujarat Energy Research and Management Institute (GERMI) has brought down the fixed cost of setting up of a solar power plant to just Rs 3.5 crore per megawatt.

“About seven year ago, the fixed cost attached with a 1 MW solar power plant was about Rs 15 crore, which we have brought down to Rs 7 crore. GERMI’s R&D efforts have successfully brought down the cost further to Rs 3.5 crore by using graphite and silicone in solar cells.

The laboratory experiments are successful and now we are trying it for industrial scale,” Dr. T. Harinarayana, Director, GERMI, said at the ongoing Sixth CII Energy Expo and “India Energy Conclave” here.

Dr. Rahool Panandiker, Partner & Director, Boston Consulting Group, said the domestic power situation in India could become more severe as the demand-supply mismatch in coal is projected to increase from 137 million tons in 2012 to 326 million tons by 2030. “So we need to increase LNG imports by ten times in order to meet the power sector needs.”

Dr Harinarayana said India has a landmass 10 times that of Germany but had a solar power generation capacity of only 1.3 gigawatt (GW), vis-à-vis 31 GW of installed capacity in the European nation. “To use this resource of energy, we need to bring down the cost of solar energy and to serve this purpose, we should be more focused on research & development activities.”

N. Srivastava, Managing Director, Uttar Gujarat Vij Company Ltd, said the transmission and distribution losses in some of the Indian states remained very high at 30% in some cases, which makes it difficult to keep the electricity rate at a reasonable level. However, as implemented by Gujarat, these states could now have an open access policy for large consumers, which enables them to source power with rates ranging from Rs 3.50 per unit to Rs 3.90.

Source

Read More...

AIPEF opposes provision of supply licensee in proposed amendments of Electricity Act 2003...

 

image

All India Power Engineers Federation (AIPEF) has opposed the proposed amendment in Electricity Act 2003 regarding provision of supply licensee who will supply electricity in a particular area.

V K Gupta A spokes person of Federation said that since AIPEF is major stake holder on the issue it has requested the Union Power Minister of State that a meeting on the subject may be granted to Federation to discuss the issue threadbare before it is finalized and presented to Parliament for approval.


He further said that as per proposal the supply licensee shall not require a license to undertake trading in electricity and can further appoint any number of franchisees to distribute electricity within his area of supply.


Padamjit Singh Chairman AIPEF in his letter has stated that supply licensees would sell power to high revenue identified consumers such as large supply consumers, industry, shopping malls etc. This will impact revenue of state Discoms and make them financially sick.


The system of a supplier arranging power from outside to be given to a large no. of scattered consumers embedded in the Discoms distribution system is not compatible with the prevailing scheduling system wherein every generator / supplier has to give the power supply to the Discoms as per day ahead schedule.


Moreover the energy accounting and losses not yet developed / streamlined by state Discoms as has been done in USA and Australia to handle the work of supply licensee using network of Discoms and Transco. In case supplier’s generator / source trips the unscheduled overdraws impact will come on state Discoms. How this unscheduled overdrawl will be loaded on to supplier.

Discoms are supposed to apply power cuts as per guidelines of regional load dispatch centers. In applying power cuts, the feeder being common, the consumers getting supplier licensee power will also get cut which could lead to disputes.


Consumer will have to deal with two agencies the network owner and the supplier. Ownership of metering equipment/meters could create problems -supplier may not agree to meters of Discoms and vice versa.


In case a LS consumer above 1 MW gets power from outside source as permissible now, through open access, he has to get the power as per a schedule. By contrast with a supplier giving power to large number of scattered consumers in the state, it would not be possible to give any kind of schedule on day ahead basis accurately.

Source

Read More...

Imphal Solar City project's Development status...

 

Imphal Solar City project's Development status...

Imphal City is one of the 11 cities selected by Indian Government in 2009 for development as "Solar Cities", but not much progress could be seen here for this project during the last five years.


According to a highly placed source, the Solar City Project has been taken up under "Solar Mission" of the Indian Government.


Imphal was among the 11 cities selected for this project in 2009.The main objective of this project is to augment utilization of renewable energy up to 10 percent by 2020 .


Imphal Solar City Project is being implemented by Manipur Renewable Energy Development Agency (MANIREDA).


As per the project, solar plates and other necessary equipments have to be installed atop all buildings in Imphal City.
However, there is not much work progress.


Solar plates have not been installed on any of the buildings till date.


So far, MANIREDA has lit up some places of Imphal with solar street lamps as a component of the project.


This solar street lamp automatically charges itself during daytime and switches on automatically during night time.
The street lamps have benefitted the public to some extent.


On the other hand, MANIREDA has successfully lit up 155 villages in the hill districts through solar energy.


Villagers of Henglep, Singhat and Thanlon in Churachandpur district, Chingai in Ukhrul district, Tamei and Tousem in Tamenglong district and some other villages in Senapati district are beneficiaries of MANIREDA's solar project.


Significantly, MANIREDA is also working to harness all sources of renewable energy in the State by setting up wind mills, small micro-hydel and biomass energy projects at various places.

source

Read More...

Lanco Tanjore Power receives SWORD OF HONOUR award...

 

Lanco Tanjore Power receives SWORD OF HONOUR award...

Lanco Infratech Limited (LITL), one of India’s largest integrated infrastructure enterprise, has announced that its unit, Lanco Tanjore Power Company Limited (LTPCL), operating 120 MW combined cycle power plant in Tamil Nadu has bagged the coveted SWORD OF HONOUR award from British Safety Council in the category of ‘Health and Safety Management System’ for the year 2013.
 
The award which acknowledges the company’s excellence in the health and safety bracket was presented to LTPCL’s Chief Executive Officer P. Panduranga Rao from Alex Botha, Chief Executive Officer of the British Safety Council in a grand ceremony at the Goldsmith’s Hall in London.
 
Commenting on the occasion, P. Panduranga Rao, CEO, Lanco Tanjore said: “This is a proud moment for Lanco Group. Very few companies have received this award from the British Safety Council till now. It marks the sincere and responsible efforts that Lanco put into each of its projects to ensure the maintenance of the highest safety standards and creation of an amicable, secure work environment for its employees.”
 
In order to compete for the SWORD OF HONOUR award, LTPCL first had to attain FIVE STAR rating in the British Safety Council’s health and safety management audit scheme with a minimum score of 92%. LTPCL had to achieve another 80% to receive SWORD OF HONOUR, making it the first ever gas-based combined cycle power plant in India to scale the heights of achievement in the field of Health and Safety.
 
British Safety Council’s SWORD OF HONOUR award is designed to recognize and celebrate health, safety and welfare management excellence. The award is open to organizations around the world who have achieved the maximum five stars in the British Safety Council’s audit programme.

Source

Read More...