Bharat Heavy Electricals Ltd (BHEL) has recently received an Rs. 380 Crore order from Rajasthan Vidyut Utpadan Nigam Limited (RRVUNL) for setting up a 160 MW gas based power plant in Rajasthan.
The order is to set up the 160 MW Combined Cycke Power Plant at Jaisalmer District of Rajasthan.
The scope of work under the order includes design, engineering, manufacture, supply, erection and commissioning of the Main Plant and providing equipment for the Gas-based power project.
The equipment for the project will be supplied by Bhel's Hyderabad, Trichy and Bangalore plants, while the company's power sector Northern Region will undertake erection and commissioning of the equipment.