Rajasthan issues RfP for 50 MW Solar PV Plants having capacity of 1 MW each...

 

RfP 50 MW RRECL

The Rajasthan Renewable Energy Corporation Limited (RRECL) has released an RfP for the selection of 50 Solar PV plants of 1 MW (AC) to be connected on 11 kV level at 33/11 kV Discom’s substation in the state.

Some of the highlights of the RfP are

  • PPA duration – 25 Years
  • Selection process – Tariff based Competitive bidding (L1 process)
  • Last date of submission of electronic bid – October 26, 2013
  • PPAs signing date: February 28, 2014
  • Distribution of projects – The 50 projects will distributed among the 3 Discoms in the state – 20 projects in Jaipur Discom, 14 projects in Ajmer Discom and 16 Projects in Jodhpur Discom.
  • Bidders shall be selected for each Discoms separately. However, tariff to be awarded for a Zone (Discom) shall not exceed by more than 10% of the Zone (Discom) having lowest tariff.
  • Commissioning deadline – Within 12 months of signing the PPA.
  • The names of the 33/11 kV Sub-stations for each Discoms/Zone for which bidders may bid is available in the bid document.
  • The plant has to generate minimum energy corresponding to a CUF of 12% during first year and 16% during remaining years.

The bid documents can be downloaded from this link.