Featured Articles...

Showing posts with label DVC. Show all posts
Showing posts with label DVC. Show all posts

January 15, 2014

DVC begins work on Raghunathpur project - phase II…

 

DVC begins work on Raghunathpur project - phase II…

Damodar Valley Corporation (DVC) today started work on its 1,320-MW (660MWx2) phase II project for Raghunathpur thermal power plant that would entail a total investment of Rs 10,000 crore.

“We have begun the civil work for boiler of the first unit of 660MW for the second phase of Raghunathpur thermal power project,” Debashis Mitra, Chief Engineer, Raghunathpur Power Plant said.

He said this is just a beginning and it will take not less than two years to complete.

The development holds significance as DVC in November was planning to shift the project from West Bengal after officials were attacked by locals in protest.

Mitra said work had also resumed for ash pond and water corridor which is needed for first and second phase of the project.

The project got stuck and generation could not be commenced as DVC was not able progress with the 10 km water corridor pipeline for the plant due to law and order problem.

DVC has almost completed first unit of 600 MW for first phase 1200 MW (600MW x2) Raghunathpur project.

Source

Read More...

December 26, 2013

Damodar Valley Corporation power project stares at dead end...

 

Damodar Valley Corporation power project stares at dead end...

Damodar Valley Corporation (DVC) was one of Jawaharlal Nehru's 'temples of modern India'. But decades of conflict with beneficiary state governments and mismanagement have turned the eastern powerhouse into a 'temple of doom', presiding over a financial dead end.

In a confidential report to the power ministry, Arup Roy Choudhury, chairman of India's biggest generation company NTPC, said the government should either give the company a complete makeover or consider pulling the plug. Roy Choudhury was last month given additional charge of DVC.

"A total paradigm shift is required if DVC has to survive," Roy Choudhury said, putting four posers: Does the original philosophy behind forming DVC still hold good? Should DVC give up the activities that are in conflict with state government's role? Should DVC become just a generator and distributor only for bulk power? Is it a good time to reverse the 1943 initiative and wind up DVC?

DVC was set up under a special Act with the aim of controlling the wild and erratic Damodar flowing through West Bengal and Jharkhand. The two states are stakeholders along with the central government.


"When DVC was formed, probably the Centre-state and state-to-state dynamics were totally different. Today, the main stakeholders for whose benefit it was created do not feel that DVC is working for their benefit... Somehow, today it (DVC) is stepping on each others' toes and not synergizing with any beneficiary," Roy Choudhury said in a telling commentary on the company.

No wonder, the states have stopped acting as stakeholders. But Roy Choudhury also blamed the management, which went for expansion without observing the golden rule of first securing land, water, environmental clearance, coal linkage and power purchase arrangements. As a result, most of the projects are stuck.

Such carelessly planned expansion and lack of corporate vision have put DVC in dire straits: Arrears of Rs 6,880 crore, mostly from Jharkhand; negative cash flow of Rs 110 crore per month; IDC (interest during construction) liability rising to Rs 2,941 crore on account of delays and no recovery of even fixed costs of 1,100 mw in the absence of power purchase agreements.

The future too appears grim. New plants have an average tariff of Rs 4.5 per unit, which would make it tough for them to get merit order — a queue in which plants with lower marginal cost are called to switch on first for meeting demand.

Roy Choudhury also found fault with the mining foray, saying the coal tariff agreed with the mine operator had been vitiated in the absence of contractual safeguards due to changes in the coal pricing policy.

Source

Read More...

December 6, 2013

DVC seeks World Bank funding for 1,000 mw solar plan...

 

DVC seeks WB funding for 1,000 mw solar plan...

Damodar Valley Corporation (DVC), owned jointly by the centre, West Bengal government and Jharkhand government, has lined up plans to reach up to 1,000 mw of solar generating capacity by 2022, which would entail a cumulative capital investment of nearly Rs 8,500 crore over this period and it is seeking a 30-year long-term World Bank funding to reach its goal, top DVC officials told Financial Chronicle.

DVC is anyway required to scale up its solar capacity to a minimum of 235 mw by financial year 2017, in line with its solar RPO (renewable purchase obligations) obligations for the existing distribution business of the company. The solar PV potential of the company in the command area is 410 mw across irrigation canals.

DVC also has additional utilisation potential in terms of dams with a combined length of 16,538 meters, reservoirs with combined top of gate area of 362.92 sq km and possession of barren lands, TG hall roof-top etc.

Significantly, taking a cue to the success of 1 mw canal top solar power project set up by Gujarat state electricity board (GSEB) over 1 km long stretch of Narmada branch canal, DVC has already initiated 15 mw canal top solar power project on DVC canal, for which DPR has been done and EOI has been floated and NIT has also been floated.

It is expected that the ordering for the project will be done by this month and the plant is expected to be installed by the end of 2014.

According to officials the proposed canal top solar power will eliminate use of additional land but will certainly have some additional cost implication, for which it is seeking long term World Bank financing.

The estimated investment requirement for meeting the solar RPO obligation will be Rs 70 crore for financial year 2014, Rs 230 crore for FY15, Rs 600 crore for FY16, Rs 700 crore for FY17 and Rs 580 crore for FY18 respectively.

Source

Read More...

November 15, 2013

DVC hopes delays will not affect 2,520 MW Purullia thermal project cost...

 

DVC's 2520 MW Purulia Thermal Project

Damodar Valley Corporation (DVC), which is setting up a 2,520-MW thermal power plant in Purulia, West Bengal, has said the delay occurred in laying water pipes required for the plant would not lead to a major cost escalation.

The pipeline-laying work, stalled on October 21 due to land acquisition woes, will resume on Friday, R N Sen, Chairman of DVC, told Business Line here on Thursday.

“This is a manageable situation, even though the contractors have been clamoring for compensation for frequent work stoppages in laying the pipeline and other related civil work,” he said. “If the work could be carried out smoothly from now on, the residual corridor work can complete in the next four months.”Local residents have been resisting the use of land not only for the water corridor but also for a railway line for bringing coal, and building a fly ash pond. For the railway line, DVC needs about 24 acres out of a total of 80 acres required for the project.

These three auxiliary facilities—water corridor, railway line and fly ash pond—are now the major bottlenecks for executing the the power project. Apart from these three, the first project work was “ready”, DVC has said.

COMPLETION DATE

Added Sen: “The situation appears to have eased, but eruption of trouble in the future cannot be ruled out.”The first 600-MW unit in the first phase of the Raghunathpur Thermal Power Project was originally set for commissioning in November 2010.

The second phase of the project is expected to complete in six months after the commissioning of the first unit. The first and second phases are slated to cost around Rs 6,000 crore and Rs 10,000 crore, respectively.

Source

Read More...

November 7, 2013

Work in DVC's Raghunathpur project to resume soon: Partha Chatterjee...

 

DVC's Raghunathpur Project

West Bengal industry minister Partha Chatterjee said, the state government expected work in DVC's Rs 10,000 crore second phase of Raghunathpur thermal power plant in Purulia to resume in a day or two.

"We had a meeting with the DVC chairman R N Sen and local residents and discussed the contentious issues. We think construction work will resume in a day or two," Chatterjee said here, barely two days after the Damodar Valley Corporation (DVC) issued a letter threatening to shift the project from the state.

Sen, who was present in the meeting, said the discussions were fruitful and DVC had no intentions to shift the project from the state.

DVC had written to the Purulia district magistrate stating all facts about the delay in implementing the project and said, if necessary action was not taken by the state administration, the company would be left with no other option than to shift the Rs 10,000 crore project from Raghunathpur.

Chatterjee said there were some eight demands of the villagers, of which around four could be met easily.

He also offered an alternate route for the main water supply pipeline to the project, if the present route posed problems with the villagers.

DVC has not been able to commence generation from the first phase of the 1200 MW (600 MW X 2) project due to lack of water and ash pond.

"Construction of the second phase of the 1320 MW (660 MW X 2) project cannot commence unless we excavate 20 lakh cubic feet of soil and complete the ash pond, but we are unable to work due to ongoing agitations," DVC officials said.

The villagers' representatives had blamed DVC for not carrying out adequate CSR activities in the area.

DVC could not progress with the 10 km water supply pipeline as it was forcibly stopped by local residents since October 21 and for the ash pond since June.

Source

Read More...

November 6, 2013

DVC failed to keep its promises over power plant: WB govt...

 

DVC Plant in Dark

In a bid to put the blame on DVC for the impasse over the Rs 10,000 crore thermal power plant in West Bengal's Purulia district, state Industry Minister Partha Chatterjee today accused the power utility of not keeping their word regarding compensation to land losers.

Referring to the land acquisition process for the plant at Raghunathpur which began in 2007 and when the local residents were promised jobs, Chatterjee said, "Damodar Valley Corporation (DVC) should honour the agreement they signed during the Left Front regime".

Reacting to the letter written by DVC chief engineer and project head Debashis Mitra to the Purulia district magistrate, Chatterjee said, "His (Mitra's) primary responsibility is to run the site and resolve the dispute and give weight to the agreement which was signed in 2007, instead of making it an issue time and again threatening to pull out from the project. This is in very bad taste."

Chatterjee's comments came after Mitra said he had written to the DM, Purulia stating facts about the delay in project implementation and if necessary action was not taken by the state administration, the company would be left with no option other than shifting project from Raghunathpur.

Source

Read More...

October 28, 2013

630 MW Bokaro Thermal Plant of DVC closed down due to pollution issues...

 

bokaro plant pollution

630 MW Bokaro hermal Station of Damodar Valley Corporation (DVC) was ordered to shut down on October 24 as it was found polluting the Kolar River.


The Ash ponds of Bokaro thermal station were overflowing and the ash was being released to the Kolar River which is a subsidiary of Damodar River in gross violation of pollution norms. The Jharkhand State Pollution Control Board had raised serious objection which DVC was unable to address. The Chief Secretary Jharkhand has ordered the total shutdown of the station to save the Damodar River from further degradation.


All India Power Engineers Federation (AIPEF) in a letter to Union Power Minister has alleged that the shutdown of this station is a case of management failure on part of DVC. An enquiry into the events leading to the closure of Bokaro thermal unit and management failure needs to be ordered.


The closure of this station will cause immediate and direct financial loss to DVC as the DVC tariff is governed by CERC and capacity charges get reduced when station availability falls. Capacity charges are recovered through tariff and when station power is zero the revenue loss is immediate.


AIPEF has suggested that a task force or crisis management group may be set up to tackle the ash problem and to revive the plant.

Read More...

October 27, 2013

Damodar Valley Corp switches to SBI loan to trim interest cost...

 

DVC switch to SBI for financing

At a time when power companies are facing stress in managing debt, state-owned Damodar Valley Corporation has successfully swapped a Rs 2633-crore high cost existing project loan with SBI to save on interest cost.

"We have repaid the remaining project loan of Rs 2633 crore of the Power Finance Corporation with a new loan from SBI that lowers our interest cost to 10.6 per cent from 12.5 for our 1000 MW (500x2) Koderma thermal power project," DVC Director (Finance) T K Gupta.

Over the next 10 years, DVC would save a substantial amount, he said.

One unit of Koderma 500MW has been commissioned and another will be commissioned in the next few days.

Gupta said the company is aiming to swap another project loan of Rs 3,000 crore with a low cost one on similar lines.

"We will share the details once we complete the deal," he said.

DVC chairman R N Sen said in the past the company has switched to low cost loan when a thermal project is commissioned.

During project implementation period, banks normally do not prefer or lend at higher rate due to execution uncertainty risk.

When a project gets commissioned, banks agree for credit at cheaper rate as risk is minimised.

DVC registered a net profit of Rs 392 crore in 2012-13.

 

Source

Read More...

April 28, 2012

CIL to set deadlines for signing FSAs for coal supply with power producers..

image

Power India found that Coal India plans to take an aggressive stand against power producers and set a deadline after which it will not sign fuel supply agreements (FSAs) with the companies, as the state monopoly fights back after being arm-twisted to commit long-term fuel supply. Coal India's board has already decided to impose negligible penalties if it defaults on FSAs and has asked companies to accept its price if CIL needs to import coal.

 

CIL is concerned about slow growth in output and blames delays in environmental clearances for the coal shortage. However power companies accuse the state-run firm of abusing its monopoly and offering FSAs from which it can easily back out.

 

Most power producers have not come forward to sign the FSAs, making Coal India officials impatient. "Depending on the final response (from power companies) we will take a decision next week. We also intend to ask for the ministry's view on the same," Coal India chairman S Narsing Rao.

 

Another official said the company can't wait forever. "We are planning to introduce a cut-off date for signing the agreements because we cannot keep on waiting indefinitely for all the firms to come and enter into contracts," a senior Coal India official explained.

 

Coal India's board agreed to sign FSAs after top industrialists jointly approached Prime Minister Manmohan Singh and sought his intervention to help power projects that had not fuel to burn. Subsequently, the company was directed to sign supply pacts.

 

Power companies say they are discouraged by the draft FSA prepared by Coal India. NTPC and Damodar Valley Corporation along with a number of large private sector companies are viewing the draft of the fuel supply contract as heavily biased towards the coal company.

 

About 50 firms are expected to sign the contracts but only about 10 has approached Coal India so far. Almost all biggies who would be consuming bulk of the additional coal have not yet approached the company.

 

NTPC does not intend to sign separate fuel supply agreements for new units and old units at the same power station as is now required by Coal India. It intends to sign the same set of contracts - the one it has already signed for some its units. It will be consuming almost 50% of the incremental coal that will be supplied by CIL under the new draft agreement.

 

"We have already written to Coal India expressing our intention because it is not practically possible to sign two sets of fuel supply agreements for different generating units of a single power station. We would like to sign the same old set of for the new units as well," NTPC chairman Arup Roy Choudhury.

 

Following a presidential directive, CIL has prepared a new draft of fuel supply agreement that it wants to sign for units which have come up between April 1, 2009 and December 31, 2011. This draft is different from the ones that NTPC has signed for units installed prior to April 2009.

 

The new draft contract has fixed the penalties in case of supply falling below 80% of the committed amount to 0.01% which will be effective after three years. While the penalties for existing agreements are 10%.

 

 

-------------------------------

Power India – A popular blog on Indian Power Sector

This work is licensed under a Creative Commons license.
Read More...

January 18, 2012

DVC’s thermal unit to go on stream soon…

image The maiden 500 mw unit of Durgapur Steel Thermal Plant being established by Damodar Valley Corporation is set to start commercial generation by end of January. The unit was put on stream in July 2011.

In a bid to achieve completion of 2 x 500 mw capacity addition in the 11th Plan Period, another unit of the same size is expected to be commissioned by March 2012.

The company is presently operating a total capacity of about 3,800 mw of which about 3710 mw is thermal while the rest at 144 mw is hydel. DVC has decided to add 4000 mw of fresh power generation capacity in the 12th Plan Period which starts from April 2012. The units will be put up depending on coal availability for the units.

The company is in talks with Life Insurance Corporation for raising funds through government guaranteed bonds, in order to finance its expansion plans. The power generator plans to raise a total of Rs 4400 crore from LIC and a clutch of banks for financing its capital expenditure through such bonds.

The company has been financing its projects on a 70:30 debt equity ratio.

Read More...

January 16, 2012

Power play: DVC bends for RInfra…

image The Damodar Valley Corporation (DVC) has come under further cloud regarding the commissioning of six power plants to supply power to Delhi during the 2010 Commonwealth Games (CWG).

According to Sources such as DNA, Spark  found that DVC violated rules to award the Anil Ambani-owned Reliance Infra Limited an Engineering Procurement and Construction (EPC) contract worth Rs4,000 crore to construct a 1,200 MW power plant in Raghunathpur, West Bengal.

DVC also gave Reliance an interest-free loan of Rs354.07 crore in violation of Central Vigilance Commission (CVC) guidelines. The loan was given to Reliance before it submitted all bank guarantees (BGs) and before an agreement was signed.
The contract for the Raghunathpur Thermal Power Plant (RTPP), located in WB’s Purulia district, was awarded to Reliance on a single tender basis without re-tendering despite other bidders, including BHEL, formally asking that the tender opening date be extended.

DNA has documents that show that AK Barman, ex-chairman, DVC; Subrata Biswas, ex-secretary, DVC, and currently principal secretary, animal husbandry, Govt of Kerala; Gautam Chatterjee, ex-Chief Vigilance Officer (CVO), DVC, now vice-president & CEO, Maharashtra Housing and Area Development Authority (MHADA), and top officials of the ministry of power were involved in awarding this questionable contract. It is alleged that the contract was given in lieu of kickbacks and the matter needs to be investigated further.

Even as questions were raised over the awarding of the contract, the main contract file disappeared from the DVC office, making it impossible for the CAG to begin an audit of the contract. While DVC bent several rules to award Reliance the RTPP project using the urgency of the 2010 Games as an excuse, the project along with five others commissioned, is still incomplete. The projects are part of a power purchase agreement (PPA) executed between DVC and Delhi Transco Ltd in August 2006 for the supply of 2,500 MW of power for the CWG.

The contract: Tailor-made for Reliance Infra
A notice inviting tender (NIT) was issued in May 18, 2007, through the international competitive bidding (ICB) route for which the extended bid submission date (during the pre-bid conference) was July 31, 2007. Three out of the four bidders — Dongfang Electric Corporation, China; China Machinery Engineering Corporation (CMEC) and Bharat Heavy Electricals Limited (BHEL) in letters dated July 9, July 18 and July 21 requested that the dates be extended to August 31, August 14 and September 10 respectively.

However, the DVC management denied an extension, stating that it would impact the project schedule geared towards supplying the CWG with power. This denial is against a chief technical examiner’s organisation (CTEO) manual of the CVC that states that for any big project, extensions asked for by a majority of bidders, may be considered in the interest of the project. Because of this non-extension, the other three bidders couldn’t submit bids and Reliance Infra was the only company to do so.

DVC opened the Reliance bids by August 31. In the negotiations that followed, Reliance submitted a revised price of Rs 3,725 crore on September 14. During negotiations, DVC officials accepted Reliance’s request for interest-free loans.

Controversially, DVC also accepted a modification of a coal specification that Reliance wanted along the lines of its plant in Hisar. This violated another CVC guideline that specifies neither party can change any tender specification after the bid is opened.

“Accepting this is a clear favour by DVC management which includes the then chairman, secretary and CVO,” says Padamjit Singh, chairman, All India Power Engineers’ Federation (AIPEF).
After the deed was done, the DVC board curiously decided to seek the CVC’s advice regarding its decision not to extend the date of submission of bids as per the request of the three other potential bidders.

DNA has a copy of a letter dated October 4, 2007, to the CVC on behalf of the DVC board by the company’s CVO Gautam Chatterjee in which the CVO suggests the DVC board was justified in not extending the date for the submission of bids and that the decision did not lack fairness or transparency.

Chatterjee’s role in sending the letter is questionable since he should not have been party to processing and decision-making as a vigilance functionary.

To this, the CVC replied that “an extension of time or snap bid” is the preferred option. A ‘snap bid’ is a period of time given to those who have made a bid but do not fulfill tender specifications. This allows bidders to bring their bid up to required specifications. The DVC management seemed so desperate to ink the deal that it approached the CVC again via Chatterjee. This time, Chatterjee personally met Pratyush Sinha, the then CVC. The result was that the CVC removed the option of an ‘extension of bid’ and suggested ‘snap bid’ as the only option. “Such an intervention on the part of a CVO clearly suggests his intentions,” said AIPEF’s Singh.

Since technically, ‘snap bids’ are open to those who have made a bid in the first place, the ‘snap bid’ was an unfair option as of the four bidders who purchased bid documents, only Reliance Infra actually submitted the bid and was technically eligible for the ‘snap bid.’ DNA has a copy of a letter written by chief engineer, central electricity authority (CEA), part of Ministry of Power, dated October 30, 2007, where he suggests the ‘snap bid’ option was unfair since the other three bidders had not participated in the earlier tender and therefore it was inappropriate to invite snap bids from these bidders.

The letter adds that bidders need to be given adequate time in view of the complexity involved in the preparation of tender documents. However, the DVC went ahead with the ‘snap bid’ with the clause of revised coal specifications and the provision of an interest-free advance.

DNA has documents which prove that the inclusion of ‘interest free advance’ during the snap bid was not passed by the finance department. In a tender process, two bids are made. One deals with the project cost and the other details technical specifications.

While Reliance was asked to submit the price bid, the others were asked to submit the techno-commercial bid, too. To this, the chief engineer’s letter referred to earlier said: “Coal quality to be considered has been modified in the new bid proposal. Since the change in coal quality will involve major changes in the design of boilers, coal mills, electrostatic-precipitator & ash handling system, bidders should be given a reasonable time to submit the offer.”

Documents suggest that the other three bidders were not given any details of the issues that DVC and Reliance Infra had negotiated upon. “Since DVC have held a series of discussions with Reliance, who was the only bidder against their earlier bid, it is desirable that deviations/clarifications that have been given to REL are also made available to all bidders so as to provide a level playing field to all of them,” said the CEA letter. The result: No other bidder submitted a bid and Reliance Infra was awarded the contract.

A day after the DVC board met to consider the bid on December 11 2007, it sent a letter of acceptance (LOA) to Reliance. Giving an LOA within a day is unprecedented. In DVC’s case, the LOA was given even before the board meeting’s minutes were circulated.

When DNA spoke to some DVC employees, they said the then power minister Sushil Kumar Shinde and power secretary Anil Razdan visited the DVC office on December 11, 2007 to ensure the deal was passed. However, DNA has been unable to verify this independently. Interest free in Reliance’s interest
This was not all. DNA found that besides irregularities in the tender-awarding process, DVC favoured Reliance by granting it an interest-free loan in complete violation of CVC guidelines. Though bid documents said DVC would grant the successful bidder a loan @12.75%., Reliance was offered an interest-free loan after the bid was opened. This is in violation of CVC guidelines that stipulate that if an interest-free loan is necessary, it should clearly be stipulated in tender documents itself. In exchange for this relaxation, Reliance reduced its bid amount by Rs100 crore. But even by a conservative estimate, DVC lost Rs 50 crore because of the interest-free loan. There are questions over the loan disbursement too.

The Letter of Acceptance (LOA) issued on December 11, 2007 mentions that a mobilisation advance would be given only after Reliance issued all bank guarantees (BGs). CVC guidelines also stipulate that an advance should only be given after all BGs are submitted. But Reliance was paid the first installment of Rs173.56 crore on December 17, 2007 even though it had not submitted all BGs. DVC justified the haste, saying it was done because it needed to fix the zero date (date project officially begins) as December 14, 2007 given the Commonwealth Games deadline.

But even the second loan installment of Rs183 crore was given ignoring provisions made in the letter of intent (LOI) issued on February 29, 2008. The LOI says an advance cannot be given without signing a contract agreement. A Reliance spokesperson said that the company was not ready with its reply to DNA’s and it would formally communicate with DNA on Monday. When contacted, Chatterjee said: “I have nothing to add on this
matter. I am not aware of any of this.”

The mystery of the missing file
When CAG attempted an audit to see whether the interest-free loan to Reliance was justified, the DVC management informed it that the main file for the Rs4,000 crore project was missing. Not only that, the DVC management did not bother to file an FIR regarding its loss, a procedure ordinary people follow after the loss of simple documents like a driving licence or passport.
DNA has copies of letters exchanged between the CAG and the DVC management between November 2009 and till the end of 2011. The letters astonishingly suggest that the DVC management intended to hush up the matter. In one letter, from M. Mukherjee, Sr audit officer, DVC HQ, to the director (projects), DVC, dated February 12, 2010, Mukherjee asks for the exact date the main contract file went missing. The letter asks whether any action was taken and if not, the reasons thereof. It also asks whether DVC filed an FIR reporting the loss.

The CAG also wrote two more letters asking for the same, to no avail. Finally, on May 11, 2010, the chief engineer, DVC, replied, saying that the exact date was not known and that a one-man committee had been constituted to look into the loss.

DNA found that the DVC management was misleading the CAG by giving such information since GS Sarna, who submitted a CVO report following a complaint by MP Rabindra Kumar Rana, said the file was missing since August 2008, months after Reliance was paid the advance.

DNA has a copy of minutes of a December 18, 2011 meeting held by P Umashankar, secretary (power), where he emphasises that reconstituting a new contract file would be enough to address the issue of the missing file. “The main file of a contract worth Rs4,000 crore has gone missing but the management didn’t bother filing an FIR. This clearly shows it wanted to hide its misdeeds,” said a senior DVC official.

Subsequently, the CAG wrote several letters dated December 13, 2010, January 14, 2011, January 20, 2011 and March 17, 2010 seeking the findings of the one-man committee. To this, the DVC management directed the CAG to approach one department or the other. In a letter dated September 20, 2011, the CAG wrote to the additional secretary, DVC, saying: “I am to state that reply to the same (above dated letters) has not yet been received from your end despite issuance of repeated reminders/several personal persuasions. Since the matter is urgent and needs to be sent to C&AG’s office, New Delhi, the same may please be furnished to this office expeditiously.” The file is still missing.

Read More...