Featured Articles...

December 31, 2013

Alstom T&D wins orders worth Rs 162 cr for substations in West Bengal...

 

Alstom T&D wins orders worth Rs 162 cr for substations in West Bengal...

Alstom T&D India on Tuesday said that it has bagged three contracts worth Rs 162 crore (€24 million) from West Bengal State Electricity Transmission Company Ltd (WBSETCL) for projects across the State.

The first two contracts include design, engineering, manufacture, supply, erection, testing and commissioning of 220/132 kV gas-insulated substation (GIS) package for Vidyasagar Industrial Park at Kharagpur and 220 kV GIS package at Dharampur. The orders are worth approximately Rs 60.7 crore (€9 million) and Rs 30.9 crore (€5 million), respectively.

As part of the third contract, worth Rs 63 crore (€10 million), Alstom will supply a 400 kV substation and a 220 kV transformer bay at Gokarna, and a 220 kV substation and feeder bays at Krishnanagar.

The 400 kV air-insulated substation (AIS) is constructed to evacuate power from the 1,000 MW Sagardighi Power plant (Phase II). It will be directly connected to the substation of PowerGrid.

“With these orders, Alstom T&D India has secured leadership position with more than 50 per cent market share in eastern India for GIS and AIS substations,” Rathin Basu, Managing Director, said in a statement.

West Bengal has planned major investments in the transmission and distribution sector. The aim is to build the transmission backbone of the State, through which power will be channelled from the eastern part of the country.

Source

Read More...

Vedanta seeks nod to use IPP power for smelter...

 

Vedanta seeks nod to use IPP power for smelter...

Vedanta Aluminium Ltd (VAL), a unit of Anil Agarwal controlled Vedanta Resources, has sought the nod of the Odisha government for using 600 Mw power from Sterlite Energy (also a Vedanta Group firm) to run its smelter at Jharsuguda.

VAL’s 1.25 million tonne per annum (mtpa) aluminium smelter set up as a sector specific Special Economic Zone (SEZ) at Jharsuguda is lying idle presently for want of power. Sterlite Energy, an independent power producer (IPP), runs 2,400 Mw (4x600 Mw) coal-fired station at Burkhamunda near Jharsuguda.

“We have set up our aluminium smelter in Jharsuguda in line with the state’s SEZ policy 2003 and are awaiting approval. We will be very pleased if approval can be granted immediately. The company also requests the government to allow use of 600 Mw power plant to run our smelter for value addition which is lying idle,” Vedanta Resources chairman Anil Agarwal wrote to Odisha Chief Minister Naveen Patnaik. Agarwal said a quick decision by the government can help start operations of the smelter resulting in generation of economic activities, huge local employment and additional revenue creation for the state.

The company had recently sought extension of SEZ benefits for its aluminium smelter project at Jharsuguda.

VAL has already invested Rs 12,000 crore on the smelter complex. The commissioning of VAL’s multi-product SEZ at Jharsuguda has been delayed considerably due to non-finalisation of the state specific SEZ policy. Due to lack of the policy, various government departments were unable to extend the SEZ benefits. Commissioning of the SEZ facility promised to boost the local economy by generating business potential worth Rs 15,000 crore every year. Direct and indirect employment opportunities for nearly 12,000 persons are set to be created.

The facility is also expected to develop local infrastructure besides boosting numerous small scale enterprises. Since the Odisha government has granted its concurrence to grant the SEZ status to the smelter plant, VAL had pointed out earlier that the state SEZ policy should be applicable to the establishment. The company had also suggested that developing and setting up of downstream industries in the area adjoining to the smelter should be made mandatory.

Source: Business Standard

Read More...

Indonesian coal to be part of index determining power tariffs...

 

Indonesian coal to be part of index determining power tariffs...

Power sector regulator CERC has decided to provide 50% weightage for Indonesian coal in the benchmark index that is used to determine escalation rates for electricity generated using imported dry fuel.

The move would help in having a benchmark in deciding the escalation rates for electricity generated by power plants that are fired by Indonesian coal.

It also assumes significance amid deadlock between various power generators and procurers over increasing the electricity tariff due to rise in imported coal prices.

The Central Electricity Regulatory Commission has decided to include Indonesian coal, besides South African and Australian dry fuel, in the composite index for imported coal for payment purposes.

Currently, for payment purposes, the index takes into account only Australian and South African coal.

The Commission said that the decision to revise the index has been taken after considering the composition of steam coal imports as well as the importance and acceptability of indices in international contracts.

The Commission said in an order dated December 23rd that "The weights of different coal in the composite index shall include 25% Australian coal, 25% South African coal and 50% Indonesian coal."

CERC has the mandate to notify the escalation rates for imported coal used to fire power plants. These rates are notified every 6 months.

According to the watchdog, Indonesian coal has been included in the index considering that it makes up for a pre dominant share of steam coal imports into the country.

In 2010 to 2011, period about 73% coal was imported from Indonesia while 24% was from South Africa.

Average import of steam coal for the last 3 years shows about 76% from Indonesia and 19% from South Africa.

During the same period, the dry fuel import from Australia was just about one per cent.

The Commission said that despite insignificant steam coal imports from Australia, it would have 25 per the Commission said in an order dated December 23rd weightage in the index.

Thr soiurb said that Australian coal has been retained in the composite index despite very low volume of consumption in India due to its liquidity, acceptability for contracts, and possibility of increased use of Australian coal in future."

The new index should be used to determine the escalation rates from April 1st 2014.

Source: Business Standard

Read More...

Solar power a lucrative new opportunity for Punjab SMEs...

 

image

Vishav Mohan (name changed), a small entrepreneur based in Ludhiana, Punjab, was running a sewing machine company that was losing money owing to the decline in demand caused by a glut of cheaper models imported from China. He is now setting up a unit to manufacture solar panels for solar photovoltaic power generation on the same premises.

Other entrepreneurs in the region have already embarked on this road.

Vikram Hans, managing director of Multi Overseas India Private Limited, Chandigarh, said that owing to the increase in opportunities in solar power generation, he is manufacturing solar power inverters with high charging capacity. "There is huge demand from the telecom sector, as solar gen-sets are more cost effective than diesel gen-sets. Solar power is not an option but a strategic compulsion now. So there is a lot of scope for business expansion."

Jagat Jawa, director general of the Solar Energy Society of India, said that due to a fall in the cost of solar power generation in the past four to five years, the business had become lucrative for SMEs. "Four years back the Central Electricity Regulatory Commission had fixed the tariff of solar power at Rs 17.91 per unit, and this has now decreased to one-third. SMEs can make modules, solar cells, cables and small electronic parts. They can register as channel partners with the ministry of new and renewable energy to avail of business opportunities."

The Jawaharlal Nehru National Solar Mission launched in January 2010 by the Union government has set the ambitious target of deploying 20,000 Mw of grid-connected solar power by 2022. One of the ways through which the mission aims to reduce the cost of solar power generation in the country is through domestic production of critical raw materials, components and products. This is expected to open new opportunities for small and medium entrepreneurs.

"There is a huge demand-supply gap in the availability of grid-tied photovoltaic inverters and bi-directional electricity meters. Most of these are either imported or provided by the big players, and are expensive. SMEs can make use of available technologies to manufacture such items. This would not only cut the government's import bill but also slash the cost of power generation," said Santosh Kumar, director, Science and Technology, Union Territory of Chandigarh, and also the director of CREST (Chandigarh Renewal Energy and Science & Technology Promotion Society).

Chandigarh is one of the four model solar cities (the others are Nagpur, Pune and Mysore) selected by the Union government for setting up rooftop solar photovoltaic power systems. In a model solar city, a subsidy of either 50 per cent of the project cost or Rs 19 crore is given for solar power generation.

Uni-directional meters are used when the power is drawn from the grid. But in case of power generation by the consumer, a bi-directional meter is required which can register the electricity consumed and can also measure the surplus power supplied to the grid by the consumer. Such meters are presently available at an exorbitant price (about Rs 20,000 each). These meters can be sourced at a third of the price if manufactured by SMEs, added Santosh Kumar.

SMEs can also manufacture grid-tied invertors. These inverters can 'sense' the grid. When the grid shuts down, they divert power from the grid to the battery, saving power.

The Energy and Resources Institute (TERI) has been conducting a high-resolution satellite imaging survey to develop a web-based GIS tool for assessing the availability of rooftop space and radiation in Chandigarh. Amit Kumar, director (energy-environment) at TERI, said that SMEs can start making photovoltaic inverters, charge controllers, electrical components and metallic mounting structures.

With the tariffs for conventional power increasing owing to the high cost of coal and diesel, and the cost of renewable energy declining owing to the availability of better technologies, India is expected to reach grid parity (when the cost of renewable and conventional power equalises) by 2017. And since the Indian climate supports solar power generation, the investment in this field would be sustainable.

Source: Business Standard

Read More...

200 kWp Rooftop Solar plant commissioned by an Educational Society in Andhra Pradesh

 

200 kWp Rooftop Solar plant commissioned by an Educational Society in Andhra Pradesh

A roof top, solar photovoltaic power plant has been commissioned at the Sri Vishnu Educational Society, Bhimavaram Campus in West Godavari district.

The Vice-Chairman and Managing Director of the New and Renewable Energy Development Corporation of Andhra Pradesh, M. Kamalakar Babu commissioned the plant on Saturday, which has an installed capacity to generate around 3 lakh units per year.

The 200 kWp grid-tied unit has the capacity to produce 820 units per day average. However, in summer, the peak capacity of 1000 units can be generated while during rainy season, the minimum units produced would be around 600 per day. K.V. Vishnu Raju, Chairman of the Educational Society, said the installed project will meet about 10 per cent of the campus power requirement in base case i.e. 10 per cent of energy shall be off settled in the power imported from the grid and diesel generator.

The total project cost is Rs 2.6 crore. Of this, 30 per cent was obtained as grant from the Ministry of New & Renewable Energy as capital subsidy.

The remaining has been funded by the Vishnu Educational Society, he said in a press release.

The break even for the project is four-five years.

The power plant has been designed, supplied, installed and commissioned by Varshini Power Projects, Hyderabad. It is the biggest solar power plant in the district as well as the biggest roof top project under APEPDCL, the release said. Recently, the educational society also installed a solar PV plant on the rooftop of its engineering college in Narsapur, Medak district near Hyderabad.

Source

Read More...

GAIL gets environment nod for 220-Mw power plant...

 

GAIL gets environment nod for 220-Mw power plant...

GAIL India Ltd, the nation's biggest gas marketing company, has received environmental clearance for setting up a 220 MW gas-based power plant at Raigad in Maharashtra at a cost of Rs 1,028 crore.

The state-owned firm plans to use 1 million standard cubic meters per day of natural gas to generated 220 mega-watt of electricity at the proposed combined cycle power plant.

The State Level Environmental Impact Assessment Authority of Maharashtra in its 63rd meeting "decided to accord environmental clearance to the project under the provisions of Environment Impact Assessment Notification, 2006," R A Rajee, Principal Secretary in Environment Department of Maharashtra Government, wrote to GAIL on December 23.

GAIL plans to set up the combined cycle gas based power plant within the existing LPG plant boundary. Electricity generated at the plant will be sold to Maharashtra.

The project, which will use natural gas or imported liquefied natural gas (LNG) as fuel, is proposed to be located within GAIL's existing LPG recovery plant at Raigad.

GAIL has appointed Tractebel Engineering Pvt Ltd as consultant for preparation of Detail Feasibility Report (DFR).

According to the company's proposal, natural gas requirement for use in the proposed project would be about 1 million standard cubic meters per day.

The supply of fuel is proposed to be available from GAIL pipeline network. A new pipeline of about 400 meters is to be laid to connect the power plant.

GAIL in the project reported stated that about 1 mmscmd gas is available for the proposed project. Gas can be made available for the project either from domestic fields or imported LNG).

Source: Business Standard

Read More...

Clearances of Odisha power project coal blocks may be de-linked: Report

 

Clearances of Odisha power project coal blocks may be de-linked: Report

The government may de-link forest clearance of coal blocks for 4,000-MW Odisha ultra-mega power project (UMPP) with the environmental clearance accorded to the entire plant, so that delay in development of mines does not affect the construction of the thermal station, according to a source close to the development.

This development comes after the Coal Ministry last week issued show-cause notice to Power Finance Corporation seeking explanation for delay in commencement of production from the allocated mines.

"MoEF (Ministry of Environment and Forests) is likely to de-link forest clearance of coal blocks for 4,000 MW Odisha UMPP with the environmental clearance accorded to the entire plant so that delay in development of mines does not affect the construction of the thermal station," the source said.

The Coal Ministry has also said that if these firms fail to give reasons for the delays it would be presumed that it has no explanation to offer and appropriate action will be taken against the company.

As many as nine companies have qualified the first bidding round for the Odisha UMPP and are likely to participate in the second and final round also.

NTPC, Tata Power, NHPC, Adani Power, JSW Energy, Jindal Power, an arm of Jindal Steel & Power, Sterlite

Infraventures, CLP India and Larsen & Toubro had submitted applications for the Odisha project.

Odisha UMPP is a pit-head power project. Based on domestic coal, to be sourced from allocated captive coal blocks, it is expected to cost around Rs. 25,000 crore.

Source

Read More...

Trial linking of national and southern power grids to start from today...

 

Trial linking of national and southern power grids to start from today...

The Power Grid Corporation of India Limited (PGCIL) will start synchronising the national power grid with the southern power grid on a trial basis on Tuesday. The much-awaited synchronisation is expected to ease electricity shortage in Karnataka, Tamil Nadu, Kerala and Andhra Pradesh.

The synchronisation was to begin in the first week of January 2014. But the PGCIL decided to begin testing the synchronisation on Tuesday itself as work on the 800 kV line between Raichur in Karnataka and Solapur in Maharashtra had accelerated, officials explained.

Nevertheless, this synchronisation of the two grids would only be a testing phase and continue for sometime, officials with the Southern Regional Load Dispatch Centre told Deccan Herald.

It is said that this synchronisation testing will continue for the next four to six months until the possibility of sustained power reaching the southern states from the north of the country is ascertained. For Karnataka, the synchronisation of the two grids may bring good news. Once the two grids are linked, the State may get close to 1,000 MW of additional power, according to officials. The State has a medium-term Power Purchase Agreement (PPA) with three to four states in the western and northern parts of the country, including Maharashtra and Gujarat.


The KPTCL has, however, estimated that 1,000 MW of power will be received only after the ‘hierarchy of power supply’ is committed. The hierarchy means upper states will have the first right in the supply of power.  At present, the KPTCL estimates that it receives only 500 MW of the 1,500 MW under the PPA which it has signed with the western and northern states. The PPA continues till April-May 2015.

Source

Read More...

Power losses halved in Haryana, but little gain for consumers...

 

Power losses halved in Haryana, but little gain for consumers...

Seen in pure revenue terms, the year 2013 was good one for the power discoms. According to reports, operational losses were reduced by 52%, thanks to financial restructuring.

But from the viewpoint of the consumer, there are few causes for celebration. First of all, there were around half a dozen tariff hikes in this year alone.

In October, when the domestic tariffs were ratcheted up by 34 paise a unit, there were many voices of protest. Especially from the industrial community, which has been pressed the hardest by rising power costs. Industrial power costs as much as Rs 7 per unit, and this is without taking into account added tariff components like fixed charges and fuel surcharge.

Many are now anticipating another hike as a New Year gift. The discoms, including the DHBVN, are aiming to further slash their annual losses by around 21%. And putting the burden on the consumer, especially on the industrial users - who account for around 42% of the total power consumed in the region - has been common practice."The power authorities have implemented unreasonable hikes all these months, and the same is likely to happen next year.

Industrialists are paying fixed charges and a fuel surcharge on an already high tariff. Buying electricity off the grid here is becoming as costly as diesel-based backup," said S K Sharma, a local entrepreneur.

Source

Read More...

50 Substations across the state has been inaugurated in Tamil Nadu...

 

50 Substations across the state has been inaugurated in Tamil Nadu...

With a view to ensure uniform power supply to all and to reduce transmission loss as well as maintenance cost, Chief Minister J Jayalalithaa on Monday inaugurated 50 sub-stations across the State, set up at a cost of Rs. 509.88 crore, through video conferencing facility at her camp office at Kodanadu in Nilgiris district.

Jayalalithaa also launched the distribution of 14.62 lakh CFL lamps that consume less power to hutment dwellers, instead of incandescent bulbs.

The 50 sub-stations include a 33 KW facility at Mahatma Gandhi Nagar in Madurai, as well as two each of 230 KW capacity, 29 each of 110 KW capacity and 18 each of 33 KW capacity across the State.

The Chief Minister had unveiled the Solar Energy Policy 2012 with a thrust on tapping the abundant natural resources in the State since it is environment friendly.

Jayalalithaa also inaugurated a 60 KV solar energy panel on the rooftop of the Tamil Nadu Generation and Distribution Corporation office in Chennai, set up at a cost of `55.80 lakh. This could generate one lakh units of power per year to meet a substantial quantum of electricity required for running the office. Besides, on holidays, this solar panel would be connected to the grid.

To encourage power saving and considering the market price of CFL lamps, the government has decided to provide them to 14.62 lakh hutment dwellers at a cost of `8.77 crore. In the first phase, 7 lakh lamps would be distributed. The Chief Minister gave away 9 watt CFL bulbs to seven beneficiaries. With this scheme, the State could save 40 MW of power.

Source

Read More...

December 30, 2013

Government has no authority to reduce power tariffs: DERC

 

Government has no authority to reduce power tariffs: DERC

Delhi's electricity regulator has said the government cannot interfere in fixing tariff though it can subsidise consumers, highlighting the potential difficulties facing Arvind Kejriwal, the new Delhi CM, whose party has promised to halve electricity prices in the Capital.

"The government cannot interfere in tariff fixation. It is a regulatory issue," PD Sudhakar, chairman, Delhi Electricity Regulatory Commission, told ET.

"We fix the tariff as per law, taking into account all economic considerations. The government cannot interfere in the process. But if it wants to support people, it can offer a subsidy to reduce power tariff," he said.

"How do they (Aam Aadmi Party) propose to reduce the tariff? We fix the tariff after due diligence and it is difficult to reduce tariff beyond a point as 70% of Delhi's power comes from outside and we have no control over the cost of power," the state power watchdog said.

"But by law, the state government can offer subsidy. To what extent they would want to subsidise is up to them," Sudhakar said.

The meteoric rise of AAP, which eventually led to Kejriwal becoming the chief minister of Delhi, was fuelled, at least in part, by promises which many economists would term populist.

These include providing 700 litres of free water, the promise to cut electricity rates in the city and conducting audit of power distribution companies (discoms). While many Delhi residents were enthused by the prospects of cheaper power, the power distribution companies have said it will be "nearly impossible" to lower the rates, given that their accumulated losses amount to Rs 11,000 crore.

Discoms argue that in the past 10 years, cost of power has increased 300%, mainly because of higher coal prices and a rise in the financing charges due to higher interest rates, while the rate at which it is sold to retail consumers has increased by only 70% during the period.

Delhi has three power discoms, two controlled by Reliance Infrastructure and one by Tata Power. The state government owns a 49% stake in each discom.

"If they (AAP) feel the accounts are fraudulent and have been under-reported by 50%, it's a matter of their perception. Now they have formed the government, which is a part owner of the discoms. We have done our job carefully, but if they want they can get auditors and fix any issue they may come across," Sudhakar said. The total annual revenue of the three discoms in Delhi is around Rs 15,000 crore. If the government offers to lower tariff by 50%, it may result in an additional annual burden of Rs 7,500 crore on the state, experts tracking the sector said.

Sudhakar also dismissed arguments that the state's discoms were making profits on surplus power available to them. "Delhi has 20-30% surplus power during nonpeak hours, which is fed back into the grid at rates fixed by the Central Electricity Regulatory Commission. Due to change in norms, the returns the state gets are low and we are actually making losses on it." Industry sources said during the 2010 Commonwealth Games, the Delhi government had asked discoms to tie up additional power to meet the spike in demand.

Post the event, the city has had surplus power which it can feed back into the grid at rates fixed by CERC or sell on the power exchanges or through bilateral pacts. However, most state power distribution companies choose load shedding over buying power as they are sitting on huge losses. Consequently, there are not too many takers for the surplus power from Delhi and the city state ends up selling it back to the national transmission grid.

Long before his election campaign, Kejriwal had alleged the Sheila Dikshit-helmed government was in cahoots with the discoms, which resulted in wrongful gains to the latter. He had cited a 2010 estimate by Brijnder Singh, the chairman of DERC at the time. Singh had said that discoms were making large profits and had recommended reducing rates by 23%.

According to Singh, discoms would have made profits of Rs 3,577 crore from sale of surplus energy, but his recommendation was rejected and was not incorporated in the final tariff order.

This issue was contested by social worker and former MLA Nand Kishore Garg through a public interest litigation in the Delhi High Court, to which AAP leader Prashant Bhushan was also a party. But the court ruled that Singh's recommendation was not the official tariff order.

In its judgement in May 2011, the Delhi High Court said, "The notings on the files by the commission do not constitute an 'order' under the 2003 Act...The commission shall proceed afresh by following the due procedure and do the needful and not afford any kind of opportunity for criticism and determine the tariff."

Sudhakar said the court order had settled the issue: "This argument (citing Singh's order) keeps resurfacing, but the Delhi High Court has already dismissed this since there was no official DERC order on it. The so-called profit that was mentioned was based on certain assumption that did not come true."

Officials at the regulator said during Singh's tenure, he had expected that Delhi would get an additional 5,000 mw capacity in 2010-11 which could be sold at a premium to make profits. However, these projects were either delayed or shelved. The state, thus, never got this capacity and therefore there were no profits.

Source

Read More...

Adani Power Board approves demerger of transmission business...

 

Adani Power Board approves demerger of transmission business...

Adani Power Board today approved the demerger of its transmission lines business to its wholly owned subsidiary company besides appointing Vinod Bhandawat as the chief financial officer of the generation company.

In a statement to the Bombay Stock Exchange (BSE), Adani Power said that its board has approved the "demerger of the transmission line business of the company to its wholly owned subsidiary company (WOS) subject to requisite approvals and also approved the valuation report (by BSR & Associates, Chartered Accountants), fairness opinion (by ICICI Securities Ltd.) and the Scheme of demerger."

The shares of Adani Power were down 0.38% to Rs 39.35 in day's trade on the BSE.

The transmission unit of Adani Power will compete with the likes of JSW Energy, Torrent Power and Reliance Infrastructure apart from the state-run Power Grid Corporation of India. Adani Power currently operates four transmission lines including one between the company's Mundra plant and Dehgam near Ahmedabad, another 1,000 km long line between Mundra and Mohindragarh in Haryana apart from two in the state of Maharashtra.

The estimated investments on these lines is around Rs 10,000 crore. Adani Power got its first transmission license in July 2013 and thereafter it had filed a petition for tariff determination at the Central Electricity Regulatory Commission (CERC).

Source: Business Standard

Read More...

PSERC passes on customs duty benefit of Rs.600 crore to consumer...

 

PSERC passes on customs duty benefit of Rs.600 crore to consumer...

Punjab State Electricity Regulatory Commission (PSERC) has decide to pass on custom duty benefit of Rs. 600 crore availed by Sterlite Energy limited on account of grant of mega power project status to Talwandi Sabo thermal project be passed on to consumers.

PSERC in its order of December 27 on petition no. 41 directed the Sterlite Energy limited executing theTalwandi Sabo thermal project to render true and full account of benefits to PSPCL that ought to have accrued to it on account of grant of mega power status to project.

The Punjab consumer is going to benefit to the tune of Rs. 104 crore per annum for the next 25 years as the fixed charges of project will come down by 8 paise per unit. With a generation potential of the plant being 13000 million units, the Punjab consumer shall gain by Rs. 2600 crore over a period of next 25 years.

PSPCL has filed a petition before Commission seeking directions to Sterlite Energy limited on account of mega power status granted to 1980 MW Talwandi Sabo project and pass on all financial benefits claimed to PSPCL as per power purchase agreement.

PSPCL has claimed that the benefits of status were not applicable at the time of bidding in 2006 as per existing laws .In December 2009 Government of India revised the policy guidelines and modified the mega power policy. Talwandi Sabo thermal project was granted this status in August 2010.

Punjab Government issued the essentiality certificate to obtain necessary customs duty benefits and the company executing the project gave the undertaking and claimed all the benefits The company claimed that it is not liable to pass the benefits of new policy to PSPCL claiming that this was not a change of law. The benefits were granted to keep the power tariff low in the public interest.

Sterlite has been benefitted to the tune of Rs. 600 crore for duty draw back the non - payment of customs duties. As per article 13 of power purchase agreement the fixed charges of 135.4 paise per unit comes down by 8.064 paise per unit.
Similarly the Commission had granted a relief of Rs 74 crore per annum last November from power generated from Rajpura thermal plant on similar grounds thereby passing on a benefit of 8 paise per unit totaling to Rs.1850 crore to the consumers over next five years.
Round up of PSERC in 2013
Punjab consumer is going to gain about Rs. 300 crore during 2013-14 on as an impact of fuel audit conducted by PSERC for reducing the use of coal and other fuels at PSPCL thermal plants. This will reduce tariff by about 7.5 paise per unit.
Thus the vigilant eye of PSERC on private and PSPCL thermal plants is likely to reduce the electricity tariff by about 23.5 paise per unit during 2014-15, thus reducing the burden of 63 paise per unit proposed to be passed on to the consumer by PSPCL to 40 paise per unit.
According to In case PSERC applied the regulations strictly on PSPCL ‘s ARR petition in stringent manner ,there is a possibility of reducing the tariff during 2014-15 keeping in view the profit of PSPCL and PSTCL during 2012-13 and 2013-14 . These sources indicate that courtesy consistent tariff rises given by PSERC, the profits of PSPCL and PSTCL during last 2 years have crossed a figure of few hundred crore which the companies are hiding from the public to manage a rise in tariff during 2014-15.

Source

Read More...

Kerala must plan switchover to 100% renewable energy: Report

 

Kerala must plan switchover to 100% renewable energy: Report

Kerala must plan for a transition to 100 per cent renewable energy for sustainable development and energy security.

The State has meagre fossil fuel resources and most of the hydro potential is already harnessed, says G.M. Pillai, Founder Director-General of Pune-based World Institute of Sustainable Energy.

REPORT RELEASED

He was here to attend a function to officially release ‘The Energy Report-Kerala’ brought out by the Institute in partnership with WWF-India.

The report maps energy requirements up to 2050 in order to assess the feasibility of meeting 100 per cent of the energy demand through renewable resources.

Emissions from coal or gas-based power projects may adversely affect both the forests and the fragile marine ecosystems and could also pose a public health hazard.

Given such constraints, the State faces a threat to its energy security, Pillai said. On the other hand, most renewable energy technologies have low environmental impacts.

The Energy Report assesses that the State has a potential for 60,000 MW in renewable energy across multiple sources.

ALTERNATE ENERGY

If only the State manages to convert at least 20 per cent, it could rest assured of what Pillai described as orderly development and sustainable future.

Alternate energy is a misnomer, according to him. What we would like to call as ‘alternate’ will turn out to be the ‘only’ choice, going forward.

It has been acknowledged that changeover from an existing regime of energy consumption to the next happens in cycles of 30 years.

This is why the report looked at the likely scenario emerging in 2050, Pillai explained. “We need to start planning right now,” he said.

According to the Report, the largest potential among individual sources of renewable energy is in rooftop photovoltaic in which Kerala has announced major initiatives.

Rooftop PV (domestic, or flats and individual dwelling units) has a potential of 13,079 MW and rooftop PV (institutional, or offices and public institutions) has 18,066 MW.

The next big source is offshore wind (13,447 MW), but this has not been tried out in the country; it is capital-intensive and therefore generates costly power.

But it is a major resource in Europe, with the UK and Denmark topping the list in terms of generation.

The Union Ministry of New and Renewable Energy has appreciated the prospects in India and is expected to come out with a policy on offshore wind energy by March, Pillai said.

Grid-tied solar PV over wasteland (4,273 MW) and grassland (2,543 MW), too, are dependable resources. Floating PV panels (in rivers, reservoirs: 3,845 MW) are another.

Source

Read More...

OIPL drafting PPA for Odisha UMPP...

 

OIPL drafting PPA for Odisha UMPP...

The Odisha Integrated Power Ltd (OIPL), a fully owned subsidiary of Power Finance Corporation (PFC) is in the process of preparing the draft power purchase agreement (PPA) for the first ultra mega power plant (UMPP) in the state.

The maiden UMPP with a capacity of 4,000 Mw is coming up at Bhedabahal in Sundargarh district. OIPL is a special purpose vehicle formed for implementing the UMPP. Odisha would get 1,300 Mw as state share from this power project. The project will be implemented as per the terms and conditions of the PPA.

The selection of bidder is being done as per the tariff based competitive bidding guidelines issued by the Central government on design, build, finance, own and transfer (DBFOT) basis.

The Request for Qualification (RFQ) for the UMPP was issued on September 25. OIPL has received applications from nine prospective developers — Adani Power Ltd, CLP India Ltd, Jindal Power Ltd, JSW Energy Ltd, Larsen & Toubro Ltd (L&T), National Hydro Power Corporation Ltd (NHPC), NTPC Ltd, Sterlite Infraventures Ltd and Tata Power Ltd.

The award under Section 11 (of Land Acquisition Act) for private land measuring 2,733.54 acres was issued by the Sundargarh collector from August 8-10 this year in all affected villages- Kandabahal, Kirei, Rupidihi, Kopsingha, Lankahuda and Bhedabahal.

OIPL had deposited the land compensation amounting to Rs 634.92 crore with the Odisha Industrial Infrastructure Development Corporation (Idco) on June 21 this year. Idco, in turn, deposited the same with the Sundargarh district administration in August 2013.

Till December 19, compensation of Rs 125 crore has been disbursed.

The district administration, meanwhile, is processing 36 cases of alienation of non-forest, government land measuring 512.43 acres. The UMPP needs 3,100 acres of land in all.

Three coal blocks — Meenakshi, Meenakshi B and dip side of Meenakshi with combined deposit of 838 million tonne have been allocated for the UMPP. Presently, Central Mine Planning & Design Institute (CMPDI) is demarcating the coal blocks. Notification under Section 11 of Coal Bearing Areas (Acquisition and Development) CBA Act has been issued for the Meenakshi coal block.

OIPL has submitted a revised proposal for environment clearance in October 2013 . The proposal is under consideration of the Union ministry of environment & forests (MoEF).

Two more UMPPs are set to come up in Odisha. It has been decided to set up the second UMPP at Bijoypatna in Chandbali tehsil of Bhadrak district and third UMPP at Narla under Kesinga sub-division in Kalahandi district. The sites have been selected after field visits by PFC. Two subsidiaries — Sakhigopal Integrated Power Company Ltd and Ghogarpalli Integrated Power Company Ltd have been formed by PFC for executing these two UMPPs. The second and third UMPPs would contribute 2,000 Mw each to the state grid.

Source: Business Standard

Read More...

Jharkhand electricity board divided into four parts...

 

Jharkhand electricity board divided into four parts...

The Jharkhand cabinet Monday gave its approval for division of the state electricity board into four parts, an official said.

"The state cabinet today gave its approval for the division of the JSEB (Jharkhand State Electricity Board) into four parts.

Four companies will be formed after the division. The companies will be holding, distribution, transmission and generation," state Energy Secretary Vimal Kirti Singh told reporters after the cabinet meeting.

The JSEB division was deferred 28 times in the last eight years due to protests by its employees.

According to sources in JSEB, the central government had informed the state that if the division was not done it will not get the Rs.4,000 crore assistance in future. Dec 31 was the deadline for the decision.

The Jharkhand cabinet also approved Rs.298 crore to be given to Bihar as pension liabilities.

Source

Read More...

IRENA Demystifies Renewable Energy Costs...

 

IRENA Demystifies Renewable Energy Costs...

On the occasion of the sixth meeting of its Council in Abu Dhabi, the International Renewable Energy Agency (IRENA) launched a unique web portal dedicated to renewable energy cost analysis (www.irena.org/costs). The portal provides access to IRENA’s data and analysis at no cost to users.

“IRENA has developed the most current and comprehensive global database of renewable energy project costs available to the public. Our new portal makes this resource available for policy makers, businesses and the renewable energy community worldwide,” said Dolf Gielen, Director of the IRENA Innovation and Technology Centre in Bonn, Germany, and project leader for this initiative.

“The data shows that the costs of renewable energy are declining, sometimes rapidly. Investment and policy decisions can now be based on the latest, verified data from a trusted source,” added Mr Gielen. “Recent cost reductions, notably for solar photovoltaics, have profound implications for social and economic development opportunities and for millions of people’s aspirations for a better life. On economic grounds, their access to modern energy should be renewable based,” he said.

The new portal showcases IRENA’s position as the global source for cost and performance data of all renewable energy technologies. The web portal makes the latest and best cost data, as well as the Agency’s analysis, publications, presentations and charts accessible to the public. It provides an important service for the further development of renewable energy globally. Often, the lack of up-to-date, accurate and reliable data on cost and performance was seen as a barrier to the uptake of renewable energy technologies. IRENA’s new web portal is ensuring that this will not be the case in the future and the debate about the role of renewable energy technologies in the energy sector can be based on the facts.

The portal is accessible to the public at www.irena.org/costs, free for all users.

Source:IRENA

Read More...

December 28, 2013

120 MW thermal power plant in Ganjam district of Odisha on the anvil...

 

120 MW thermal power plant in Ganjam district of Odisha on the anvil...

A 120 mega watt (MW) thermal power plant is on the anvil to be established near Chatrapur in Ganjam district.

This power plant would need an investment worth around Rs. 600 crore. It would be established by Dr. Ramakrishna Prasad Power Private Limited (RKPPL) of Hyderabad. Speaking to The Hindu, Ganjam district Collector, Krishan Kumar said the RKPPPL has already obtained clearance from Government of Odisha for this 120 MW coal-based thermal power project. According to company sources it has applied for clearance of the project from the Ministry of Environment and Forests (MoEF) of Central government and has obtained Terms of Reference (TOR) from the MoEF.

As per the instructions of the State Pollution Control Board (SPCB), a public hearing for environmental impact assessment of the project would be held on January 10 at the proposed site of the project.

According to the authorities this proposed coal-based thermal power plant would be established near Sri Ramchandrapur village of Chattrapur block in Ganjam District. According to a director of the RKPPL, Naveen Venigalla, who was in Ganjam district regarding the project, the land for the project has been earmarked. This thermal power plant would come up on 85.78 acres of land. Out of it 74.2 acres are government land and rest is private land.  

As per the authorities this project would need around three years for its construction. The company claims that this thermal power plant would be a non-polluting one. Its pollution level would be too low as it would use modern technology and imported coal. The imported coal it proposed to be used by this power plant would have six per cent ash in comparison to Indian coal which has 40 per cent ash, the company authorities claimed.

It is envisioned that the Gopalpur port which is at its final stages of completion to become an all weather port would provide scope for import of coal for this thermal power plant. This power plant would need around 200 cubic meters of water every day. It has been decided to use ground water for the purpose.  When this thermal power plant would start its production, it would evacuate the power generated by it through 132 KV power transmission line of Odisha’s GRIDCO. Around 30 MW of its production would be provided to Odisha government while the rest would be marketed by the company. This project is expected to solve power problem in Ganjam district and other parts of south Odisha.

Source

Read More...

UPPCL signs power purchase agreement for 110 MW solar power with the solar power developers...

 

UPPCL signs power purchase agreement for 110 MW solar power with the solar power developers...

The UP Power Corporation Limited (UPPCL) has entered into an agreement with solar power developers for purchasing 110mw of power.

The agreement was entered in the presence of UP chief secretary, Javed Usmani, who said that under the state solar policy the state government will be setting up 500mw of power solar power plants in the state.

The UP New Energy Development Authority (UPNEDA) had invited bids for setting up of power plants compositely to the tune of 200mw. The authority had also put in place a competitive bidding process for power tariff from these power plants. Against this, the authority received bids for 130mw. On Friday, the UPPCL signed the agreement for 110mw power.

The solar power plants with which the agreement was signed included, 10mw by Azure Surya Private Limited, 50mw by M/s Essel Infra Project, 20mw by Moser Baer, 10mw by M/s Refex Energy, 10mw by M/s Jackson Power and 10mw to be set up by DK Infracon. All these power plants are proposed to be set up in Bundelkhand region. Usmani said that NEDA would soon invite bids for the rest 370mw.

Source

Read More...

DERC turns down discoms power tariff-hike plan in Delhi...

 

DERC turns down discoms power tariff-hike plan in Delhi...

The Delhi power regulator has turned down a request by the distribution companies to hike power tariffs in the Capital, a day before the Aam Aadmi Party (AAP) chief Arvind Kejriwal takes oath as chief minister. This is probably the first time that a claim by the distribution companies has been turned down.


Distribution companies BSES Rajdhani Power Limited (BRPL), BSES Yamuna Power Limited (BYPL) and Tata Power Delhi Distribution Limited had sought the hike as power purchase cost adjustment (PPAC) which would have been effective for the quarter of January to March 2014.

This increase was sought to cover the increased expenses incurred by the companies from July 1 to September 30, 2013, and is done every quarter. While BYPL had asked for a steep seven per cent hike, BRPL had sought a 3.5 per cent hike, TPDDL had asked for two per cent hike.

“There is a formula to work out PPAC, which was approved in the tariff order announced in August. After studying their claims and verifying them, we found that there was no need for an increase as they have not incurred additional cost over what has been allowed to them,” said PD Sudhakar, chairman of the Delhi Electricity Regulatory Board (DERC).

The power tariffs were last revised for the quarter of May to July when the power regulator had approved a 3 per cent hike for TPDDL, and a 4.5 per cent hike for areas under BRPL and BYPL.

AAP’s election manifesto says that the party will slash power tariff in the Capital by 50%. The party, set to form the government in Delhi, has also promised to conduct audits of the distribution companies.

A possible fallout of the political changes in Delhi was witnessed recently when TPDDL, which supplies electricity to north Delhi, submitted its annual revenue requirement (ARR) to DERC and didn’t seek a hike. “They have left it on us to decide. They submitted their papers giving out financial details and have admitted that there is a shortfall,” said a senior official. BRPL and BYPL are yet to submit the ARR.

Source

Read More...

Progress of OPGC, NTPC power & coal mine projects in Odisha...

 

Progress of OPGC, NTPC power & coal mine projects in Odisha...

The progress of the power plant and coal mine projects allocated to OPGC is satisfactory.

This has come to light in the State level Steering Committee Meeting held under Chairmanship of Chief Secretary Jugal Kishore Mohapatra in secretariat conference hall today wherein Energy secretary Pradeep Kumar Jena presented the present status of the projects and outlined issues for discussion.

The progress of work NTPC and UMPP projects in Odisha was also reviewed in the meeting.   Discussions in the meeting reveal that Manoharpur and Dip side Manoharpur, a contiguous coal block was allotted to OPGC for fuel connectivity to Unit-3 & Unit-4 2x660 MW supercritical units ( expansion units of OPGC).

The fuel supply to these power plants is totally dependent upon these coal blocks. On 23rd December, 2013 Ministry of Coal, after a review by IMG has asked for explanation to OPGC regarding slow progress in development of coal mines.  Review reveal that Ministry has issued notice to 48 coal mines in various States which includes show cause to 27 and explanation for slow progress to 21 allottees. OPGC has been issued letter of explanation for slow progress. 

Available data shows that in the meanwhile, all permits for setting up power plants have been secured and EPC contract has also been awarded. The work of power plant has commenced in work site. Regarding Manoharpur coal block, Stage-1 forest clearance has been secured. Land acquisition has been expedited with over 80% of Govt. land sanctioned in favour of the coal block and 77% of compensation amount disbursed for private land acquisition. It has been resolved in the meeting that land acquisition will be completed by end of Jnauary, 2014.  Bidding process has been expedited. Request For Proposal ( RFP) has been issued to qualified bidders.

It has been decided in the meeting that contract award will be completed by February, 2014. Directorate of Geology and Steel & Mines department will expedite the process of drilling and work execution in Monaharpur dip side. Similarly, for MGR ( Mary Go Round) Stage-1 forest clearance has been secured. Over 50% of Govt. land has been sanctioned in favour of the project and processes of disbursement of compensation to private land owners have been expedited. Request for Proposal has been issued for EPC contract.   

Replying to queries of media after the meeting Energy Secretary Sri Jena said that the progress of work for OPGC Power Plant expansion units and allotted coal blocks is almost ahead of the schedule. The work will be further expedited. Sri Jena added that we are waiting for mining approval form Government of India. Sri Jena has also said that we will comply with all the queries made by the Ministry within the prescribed time; and, we are confident that Ministry will be satisfied by the progress achieved till today.  

The meeting also reviewed the progress of NTPC projects like Darliplai Super Thermal Power project, Dulanga coal mining project, Gajmara Super Thermal power Project and Talcher Super Thermal Power Station. The issues relating to Resettlement & Rehabilitation, land acquisition, disbursement of compensation, exemption of stamp duty on Govt. land compensation to patta holders under forest rights act, renewal of water allocation etc were discussed and finalized in the meeting.

The progress of 4000 MW Ultra Mega Power Projects (UMPP) in Odisha, a wholly owned subsidiary of Power Finance Corporation (PFC) was also figured in the meeting. The bottlenecks relating to private land acquisition, diversion of forest land, acquisition of land for Marry Go Round (MGR), Petroleum, Oil and Lubricant (POL), water corridors were discussed and necessary decisions were taken for removal of those bottlenecks.  

Additional Chief Secretary Revenue & Disaster management Dr. Taradatt, Principal Secretary Forest & environment Sri Raj Kumar Sharma, Secretary Steel and Mines Gudey Srinivas, Secretary Energy Sri P.K.Jena along with senior officers from State Pollution Control Board, Forest Corporation, NTPC, OPGCL and PFC participated in deliberations.

Source

Read More...

PowerGrid gets shareholder approval to hike FII limit to 30 per cent...

 

PowerGrid gets shareholder approval to hike FII limit to 30 per cent...

Power Grid Corporation of India has received shareholder approval to increase the limit of holdings by foreign institutional investors to 30 per cent from 24 per cent currently.

FIIs can acquire and hold, on their own account and on behalf of each of their Sebi-approved sub-accounts, shares of the company up to an aggregate limit of 30 per cent of the paid up capital, the state-owned company said in a filing to the BSE on Friday.

Shareholders also approved a proposal to increase the company's borrowing limit to Rs 1,30,000 crore from the current cap of Rs 1,00,000 crore.

Both proposals were cleared through postal ballots. The plans had been approved by Power Grid's board of directors at a meeting on October 23.

Last month, Power Grid had said that increasing the limit would provide more headroom for FII investments in the company. FII holdings have been on the rise since the company's first follow-on public offer in 2010.

Power Grid had hit the capital market with an initial public offering in October 2007.

Shares worth about Rs 7,000 crore were sold in the company's second follow-on offer, which closed earlier this month.

The government got about Rs 1,600 crore from the sale of 18.51 crore shares, while Power Grid raised close to Rs 5,400 crore from its offer of 60.18 crore new shares.

Proceeds from the offer would be utilised by the company for 27 transmission projects.

Source

Read More...

December 27, 2013

NTPC to start mining coal from Dulanga block by Mar 2015...

 

NTPC to start mining coal from Dulanga block by Mar 2015...

NTPC Ltd, the country's biggest power generating utility hopes to start coal production from the Dulanga block by March 2015.

With a mineable reserve of 152 million tonne, the Dulanga block located in the Ib valley coalfields, is linked to NTPC's 1600 Mw super thermal power station coming up at Darlipalli in Sundargarh district. The power plant is scheduled to be commissioned by 2018.

The cost of developing the coal block is estimated at Rs 1556.65 crore. So far, NTPC has spent Rs 76.92 crore on the coal mine project.

The coal block has got in-principle environment clearance in March 2012. Final green clearance is expected after receipt of Stage-I forest clearance.

Development of the coal mine needs 464.15 acres of private land. Notification under Section 11 of Coal Bearing Areas (Acquisition & Development)- CBA Act, 1957 has been issued. Land rates have been finalized and disbursement of compensation would commence after approval from the NTPC board.

Similarly, development of township, rehabilitation & resettlement (R&R) colony and necessary infrastructure needs another 410.07 acres of land. The state revenue & disaster management department has approved the proposal to issue notification under Section (7) for R&R colony, CISF colony and infrastructure area. Proposal for Section 4 (1) notification for 210.63 acres for overburden dump area is being processed by the state government.

Requirement of government land for the coal block is 432.21 acres out of which an amount of Rs 17.65 crore has been deposited with the tahsildar office for 263.23 acres.

Forest land of 794.13 acres also needs to be diverted for the coal mine project. Acquisition of forest land will be initiated after receipt of Stage-II forest clearance from the Union ministry of environment & forests (MoEF) and subsequent permission from the state government for tree felling.

It may be noted that the Ministry of Coal (MoC) recently sought explanation from NTPC in respect of slow progress in developing the Dulanga coal block. The notice to NTPC was on the basis of recommendation by the inter-ministerial group mandated to review the progress of development of allocated coal blocks and associated end-use projects and to recommend action, including de-allocation, if required. The IMG observed that many critical milestones were still pending for developing the coal mine.

Source: Business Standard

Read More...

Monthly review of Indian Power Sector for the month of November 2013...

 

Monthly review of Indian Power Sector for the month of November 2013...

During the month of November 2013, around 1635 MW of generating capacity has been installed under the Indian Power Sector reaching the total cumulative generating capacity at around 232.16 GW.

Further around 1226 Circuit Kms of transmission lines are also added.

 

Summary of the review of Indian Power Sector for the month of November 2013 is depicted below:

  • Electricity Generation for the month was at 79.52 BUs
  • Generating Capacity Addition for the month was 1635 MW
    • Dhariwal TPP U-1 (300 MW) in Maharashtra  by Dhariwal Infastructure (P) Ltd on 3/11/2013
    • Shre Sangaji TPP U-1 (600 MW) in Madhya Pradesh by MPPGCL on 18/11/2013
    • Barh STPS St-II, U-4 (660 MW) in Bihar by NTPC on 30/11/2013
    • Nimmo Bazgo HE Project U-1 (15 MW) in J&K by NHPC on 2/11/2013
    • Uri-II, U-2, (60 MW) in J&K by NHPC on 16/11/2013
  • The all India installed capacity reaches at 232164.94 MW
  • Transmission Lines for 1226 Circuit Kms installed during the month
  • Transformation Capacity Addition during the month was 4580 MVA
  • Average Power Supply deficit was around 4.1% during the month
    • Northern Region - 6.5%,
    • Western Region - 1.1%,
    • Southern Region - 5.9%,
    • Eastern Region - 1.5%,
    • North Eastern Region - 4.6%
  • Peak Power Supply deficit was at 2.9%
    • Northern Region - 1.1%,
    • Western Region - 0.8%,
    • Southern Region - 6.8%,
    • Eastern Region - 1.4%,
    • North Eastern Region - 3.9%
  • All India Plant Load Factor maintained was around 65.44%
    • Central Generating Plants -  77.12%,
    • State Generating Plants - 58.67%,
    • Private Generating Plants - 69.47%

Complete report can be downloaded from this link.

Source: CEA

Read More...

Reliance Power up 3% as CBI likely to close enquiry in Sasan project...

 

Reliance Power up 3% as CBI likely to close enquiry in Sasan project...

Shares of Reliance Power today rose by nearly 3 per cent on the possibility of CBI closing its preliminary enquiry to probe coal block allocation to a power project in Sasan in Madhya Pradesh run by Anil Ambani's firm.

Reacting to this, Reliance Power's scrip went up by 2.89 per cent to Rs 74.7 on the BSE.

On the NSE, the stock rose by 2.89 per cent to Rs 74.70. The CBI is of the view that the allocation is a policy decision vetted by group of ministers.

CBI sources said it has come to light that use of surplus coal from the Sasan UMPP was approved on two separate occasions by two EGoMs. They said since it was a policy decision, CBI was not likely to question it.

However, they added that any final decision has not been taken over the closure and any such decision can only be taken after taking into consideration the views of the Supreme Court.

The sources said they have informed the Supreme Court about the preliminary enquiry in their status report and agency would proceed according to further directions of the apex court.

After the registration of the preliminary enquiry, ADAG spokesperson had said in a statement that "we welcome the independent time-bound enquiries by the CBI, monitored by the Supreme Court, which will clearly establish our bonafides".

It will "once and for all prove beyond doubt that we have been the unfortunate victims of a mischievous campaign of calumny and vilification conducted at the behest of our unscrupulous corporate rivals over the past 5 years," the statement said.

The allocation of coal mines to the Sasan project was done to a 100 percent government-owned company in the year 2006 when Reliance Power had not even won the project, it said adding the government disinvested its shares to Reliance pursuant to a global tender in the year 2007.

The preliminary enquiry was registered on the directions of the Supreme Court that had asked the CBI to probe 14 issues including supply of low floor buses by Tata motors to Tamil Nadu government, grant of spectrum and alleged market manipulations and hammering of stocks by Unitech.

Source

Read More...

Year end review of Indian Coal Sector for the year 2013 by Coal Ministry...

 

Year end review of Indian Coal Sector for the year 2013 by Coal Ministry...

Coal Ministry has done an year end analysis of the progress made by the Indian Coal Sector during the year 2013.

The same has been depicted below:

 

 

Major Highlights:

  • Regulator proposed for Coal Sector
  • Public Private Partnership to augment coal production
  • Thirty eight captive coal blocks comes under production
  • Year End Review of Ministry of Coal

Coal sector witnessed a number of initiatives during 2013 to augment coal production and supply. Regular reviews of captive coal blocks were held by Inter-Ministrial Group to expedite their development, fuel supply agreements were signed with Power Sector and setting of Coal regulator approved. Under the bidding policy, seventeen coal blocks allotted to the Government Companies and thirty eight coal blocks brought under production. Highlights and achievements of the Coal Ministry during the year are as follows:

Assured coal supplies to 78,000 MW projects to boost power production

In a major boost to the power sector, the Government approved supply of coal to power plants with a capacity of 78,000 MW. Commissioned or to be commissioned during April 2009 to March 31, 2015. Coal India Limited(CIL) has already signed 157 Fuel Supply Agreements for a capacity of 71,145 MW. This will not only increase the power generation further but will also fast track several power project which are under consideration.

Coal Regulator proposed for Coal Sector

The Government has approved the setting up a Regulatory Authority for Coal Sector on June 27, 2013. As the enactment of the legislation through the Parliament would take some time, therefore, it was decided that a non-statutory regulator be set up through an appropriate executive order. Accordingly, the matter has been referred to the Ministry of Law for advice/ consultation for framing the executive order. The Coal Regulatory Authority Bill was also introduced in theLok Sabha on December 13, 2013 for its consideration.

Public Private Partnership to Augment coal production

The Government has decided to initiate Public Private Participation (PPP) to augment coal production in the country. Accordingly, a committee has been set up under the chairmanship of Secretary (Coal) with representatives from Planning Commission, Ministry of Finance (DEA), Ministry of Labour, Ministry of Law & Justice (DLA) among others to recommend a framework for the PPP. The committee deliberated on the various models including engaging Mine Developer cum Operators (MDO) & In consultation with all the stake holders, the Government is in the process of finalizing a Model Concession Agreement (MCA) for engagement of MDO in CIL.

Further Disinvestment of Neyveli Lignite Corporation

Disinvestment of 3.56% paid up equity capital of Neyveli Lignite Corporation (NLC) out of Government of India’s shareholding (93.56%) has taken place through Institutional Placement Programme (IPP). This has made NLC compliant with the norms as per SEBI regulations. The 59701260 shares have been sold @ Rs. 60/- per share and total sale proceeds received by the Government are Rs.358.29 Crores.

Allocation of Coal Blocks to Government Companies

Under newly initiated bidding policy seventeen coal blocks, fourteen blocks for specified end-use i.e. Power and three blocks for Mining were allocated to various State Government Companies/Corporations/CPSUs. The proposed Coal Mines Production and Development Agreement to be signed by the Government with the respective eligible Companies is under finalization.

Further, the Government has also decided to put on offer five lignite blocks located in the states of Gujarat and Rajasthan for Power/Commercial mining/ Underground Coal Gasification, for allocation to Government Companies and invited applications July 29, 2013 from Government Companies/Corp. particularly from the state of Gujarat and Rajasthan, keeping in view the fact that lignite cannot be transported over long distances due to its low calorific value, high moisture and soft/brittle nature of mineral, making it susceptible to catch fire. The applications received in response to the NIA are under process.

Four coal blocks have also been identified for allocation to power projects on the basis of competitive bids for tariff and applications for the same were invited on December 20, 2013. Besides this, procedure for allocation of area containing coal through auction by competitive bidding is under process.

Thirty eight captive coal blocks come under Production

The target fixed for coal production from the captive coal blocks for the year 2013-14 is 46.15 million tonnes.As on date (upto October, 2013), 38 captive coal blocks have come under production. The production achieved during the year 2013-14 (upto October, 2013 provisional) is 21.740 million tonnes (13.645 million tonnes for private companies and 8.095 million tonnes for government companies).

Third Party sampling of coal supplies introduced

Various consumers of Coal India Limited have been raising their concern about the quality of coal supplied. In order to address these concerns, CIL has introduced Third Party Sampling and analysis of coal supplied to various power plants in the country. For this purpose, CIL has engaged independent third Party agencies for sampling and analysis of coal at suppliers’ end and the system has been made operational from October 1, 2013

Source: Coal Ministry

Read More...

Odisha to float tenders soon for 48 Mw solar power...

 

Odisha to float tenders soon for 48 Mw solar power...

In its efforts to maximize solar power generation and also to fulfill the renewable purchase obligation (RPO) of its bulk power purchaser Gridco, the state government would soon float tenders for new soar power capacity of 48 Mw.

Presently, on-grid solar power projects with a total capacity of 13 Mw are operational in the state. According to RPO fixed for 2013-14, Gridco has to buy six per cent of its energy from renewable sources out of which 0.20% has to be from solar power.

Gridco has signed power purchase agreements (PPAs) for eight solar photo voltaic (PV) projects of 1 Mw under Roof Top PV and Small Solar Power Generation Programme (RPSSGP) scheme.

Gridco has also entered into power sale agreement with NTPC Vidyut Vyapar Nigam Ltd, a 100% subsidiary of NTPC Ltd, to avail solar power bundled with equivalent capacity of thermal power from unallocated share of upcoming NTPC stations under 'New Solar Projects' scheme of Union ministry of new and renewable energy (MNRE). Under the said scheme, 20 Mw of solar power has been allocated to Gridco.

NTPC would be supplying solar power to Gridco in bundled form along with thermal power and the tariff for solar power will be in the range of Rs 4.74-5 per unit.

The Green Energy Development Corporation of Odisha Ltd (GEDCOL) has planned to go for solar PV generation to the tune of 20-40 Mw immediately for which it has already held two rounds of discussions with Gridco. GEDCOL is also setting up 50 Mw solar power project at Manmunda in Boudh district. Around 250 acres of land will be needed to set up the project. The project will cost Rs 400 crore.

Source: Business Standard

Read More...

CIL to begin final exploration round in Mozambique early next financial year...


CIL to begin final exploration round in Mozambique early next financial year...

Coal India Ltd (CIL), the Kolkata-based world’s largest coal miner, will begin third and final round of exploration in two of its blocks in Mozambique early next financial year. This brings the miner a step closer to commissioning mining in its maiden overseas project by 2016.
 
“The second phase of exploration, which is currently on, has seen minor delays owing to the onset of monsoon in that nation. That made the site inaccessible for some time. We will definitely award drilling contracts for the third phase coming March after which the exploration work will start,” said a senior CIL official.
 
The company has already completed 17,000 meters of the overall 30,000 meters of drilling in the ongoing phase. The miner was allocated two blocks with reserves exceeding a Billion Tonne (BT) in a government-to-government deal in Maotize in Tete province in the African nation in 2009.
 
The idea is to import the entire quantity of coal available in the two blocks to India to bridge the gap in demand and supply of coal which currently stands at over 135 million tonne (MT) for domestic industries. However, CIL has already missed the original deadline of starting production by 2013.
 
The progress on the project has been slow owing to procedural delays in outsourcing drilling contracts and the inter-governmental differences over the pattern of funding apart from the lack of local infrastructure support, including roads and ports. The official said the company hopes by the time mining begins in 2016, Mozambique government builds infrastructure for evacuation.
 
“The Mozambique government is building infrastructure. Also, we expect a railway carrying capacity of 6 MT annually to be free next year after the work of another mining company which is currently working there closes,” the executive said. Apart from infrastructure issues, the extent and mode of local expenditure has been a bone of contention between the Indian and the Mozambique governments and a major irritant stalling progress of the project.
 
CIL has been allocating Rs 6,000 crore annually over the past few years for overseas investments but has failed repeatedly in its acquisition plans. The miner had earlier shortlisted Australian miner Peabody Energy’s Wilkie Creek mine and US-based Massey Energy Co’s Sidney mines but failed. It had also considered buying stake in Indonesia’s PT Golden Energy Mines Tbk (GEMS) but lost the deal owing to bureaucratic hurdles.

Source: Business Standard

Read More...

Update on REC Trading for the month of December 2013: Non-Solar RECs Up by 31%, Solar RECs by 7%...

 

Update on REC Trading for the month of December 2013: Non-Solar RECs Up by 31%, Solar RECs by 7%...

The 10th REC Trading Session of the Financial Year 2013-14 was conducted on 26th December 2013 marking the end of Q3 on both the Power Exchanges, IEX and PXI.

This REC trading session shall bring some comfort and shall develop faith over REC Mechanism, as the market has shown a substantial positive growth and there are good indicators to grow even more.

Overall the results have sustained optimism as compared to the preceding trading month.

The increment in the overall Buy bid of both Solar and Non Solar has re-infused the faith in the future of REC market. Though, the Solar REC market has grown by a thin margin in this trading session, but the increasing participation from the buyers will ensure a promising future for solar market.

In comparison to last trading session of November 2013, the buyer’s participation has substantially increased by 30.73% for Non-solar and by 7.18% for Solar REC Market. The effect of RPO enforcement over the obligated entities has started showing the effect and it is expected to create more demand of certificates in the near future.

As per REC Registry, the market crossed 0.4 million marks in terms of REC redeemed. This volume (4,11,744 RECs) traded in a single session is the highest redeemed volume of this fiscal and more importantly marginally matches the volume of March 2013 (last month of FY13).

With last three months still remaining in this year and chances of higher buyer-side participation in the subsequent sessions REC markets may revers the earlier trends.

A more detailed analysis for each kind of RECs can be found as under:

Non-Solar RECs :

Buy bids for non-solar credits increased by 30.73 percent in comparison to last month’s stats. The most encouraging fact, considering a holistic view of FY14, was the cleared volume crossing the 0.4 million mark. Clearing percentages at both exchanges (IEX and PXIL) were recorded at parity (over 9%). With a total transactional value of non-solar RECs was 605.8 million INR, with price of each non-solar REC remaining at Rs. 1500 per REC.

Solar RECs:

The change in demand and supply as compared to previous month was up this month by 7.18 percent and 47.37 percent respectively. Although, the prices here also remained at floor we can still expect a jump in demand as we slip in the last quarter.

Analysis of Non-Solar REC Segment

Non-Solar REC Segment

Parameter

IEX

PXI

Total

Trend

Buy Bids

   2,50,722

   1,53,140

   4,03,862

31%

Sell Bids

 27,12,444

 16,03,154

 43,15,598

4%

Cleared Volume

   2,50,722

   1,53,140

   4,03,862

31%

Cleared Price

1,500

1,500

1,500

0%

Cleared Volume as % of Total Sell Bids

9.36%

Transaction Amount (Rs. Crs)

60.58

 

  • The Cleared Volume of Non-Solar RECs have been increased by more than 31%
  • However, the above was mainly on account of the observed increased of more than 157% on IEX; on PXI a decline of 27% was observed.
  • The Clearance Ratio in terms of Perc over Sell Bids has been increased to 9.36% from 7.45% in the previous month.
  • The Market Clearing Price observed was the Floor Price i.e Rs. 1500 per RECs.
  • Below charts shall give more clarity this.

image

image

Analysis of Solar REC Segment

Solar REC Segment

Parameter

IEX

PXI

Total

Trend

Buy Bids

          6,983

        989

   7,972

7%

Sell Bids

        77,180

   13,240

 90,420

47%

Cleared Volume

          6,983

        989

   7,972

7%

Cleared Price

          9,300

     9,300

   9,300

0%

Cleared Volume as % of Total Sell Bids

8.82%

Transaction Amount (Rs. Crs)

7.41

  • The Cleared Volume of Solar RECs have been decreased by around 7%.

  • However, the above was mainly on account of the observed decrease of more than 167% on PXI; on IEX,  marginal decrease of of 1.3% was observed.

  • The Clearance Ratio in terms of Perc over Sell Bids has been decreased to 8.8% from 12.0% in the previous month.

  • The Market Clearing Price observed was the Floor Price i.e Rs. 9300 per RECs.

  • Below charts shall give more clarity this.

image

image


Source: IEX and PXI

Read More...